B-400581.5, JSW Maintenance, Inc., September 8, 2009
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective Order. This redacted version has been approved for public release.
Decision
Matter of: JSW Maintenance, Inc.
Michael A. Gordon, Esq., Fran Baskin, Esq., and Maria Patente, Esq., Law Office of Michael A. Gordon, PLLC, for the protester.
Jennifer
M. Miller, Esq., and Anna G. Kizer, Esq., Wyrick Robbins Yates & Ponton
LLP, for Ashley-Marie Group, Inc., an intervenor.
Maj. Jonathan P. Widmann, Department of the Air Force, for the agency.
Edward Goldstein, Esq., and Christine S. Melody, Esq., Office of
the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Agency’s determination that awardee was entitled to a “confidence” past performance rating was based on a reasonable consideration of the relevance of the awardee’s past performance information, which included a comparative assessment of the size, scope, and complexity of the awardee’s contracts with the solicitation requirements.
DECISION
JSW Maintenance, Inc. of Warner Robins, Georgia, protests the award of a contract to Ashley-Marie Group, Inc. (AMG) of Elizabethtown, North Carolina, by the Department of the Air Force under request for proposals No. FA8501-08-R-0039 for grounds maintenance services for Robins Air Force Base (AFB), Georgia. JSW alleges that the agency’s evaluation of AMG’s past performance was unreasonable and that the agency failed to reasonably consider the fact that JSW and AMG did not have a similar understanding of the agency’s requirements when they submitted their proposals.
The RFP, issued on June 20, 2008 as a Small Business
Historically Underutilized Business Zone
(HUBZone) set-aside, contemplated the award of a fixed-price contract (to
include several time-and-material line items) with a 1-year base performance period
plus four 1-year option periods, to provide grounds maintenance services
(including, but not limited to, mowing, edging, composting, and irrigation system
maintenance) for Robins AFB. The RFP
indicated that award would be made to the offeror whose proposal represented
the “best value” to the government based on consideration of past performance
and price, with past performance being “significantly more important” than
price. RFP at 153.
Regarding past performance, the
RFP provided that the agency would consider information regarding any critical
subcontractors and key personnel. Based
on a consideration of the relevance of the past performance information
provided and an assessment of the qualitative aspects of the offerors’
performance, the agency would assign each offeror an overall confidence rating
of “substantial confidence,” which was defined as “a high expectation that the
offeror will successfully perform the required effort,” “satisfactory
confidence,” defined as “an expectation that the offeror will successfully
perform the required effort,” “limited confidence” defined as a “low
expectation that the offeror will successfully perform the required effort,”
“unknown confidence,” defined as “the offeror’s performance record is so sparse
that no confidence assessment rating can be reasonably assigned,” or “no
confidence” where “the government has no expectation that the offeror will be
able to successfully perform the required effort.” RFP at 154.
For the purpose of assessing relevance, the RFP
established the following scale:
VERY RELEVANT:
Present/past performance efforts involved essentially the same magnitude
of effort and complexities this solicitation requires. Examples may include such things as 612 or
more acres of improved grounds services, 23 or more acres of enhanced grounds
services, 83 or more acres of semi-improved grounds services, composting
operations and airfield maintenance of essentially the same size as Robins AFB
airfield. These quantities represent a
facility 80% the size of Robins AFB.
RELEVANT: Present/past
performance efforts involved much of the magnitude of effort and complexities
this solicitation requires. Examples may
include such things as smaller areas of grounds services in the three
categories listed above, composting operations, and airfield maintenance.
SOMEWHAT RELEVANT:
Present/past performance efforts involved some of the magnitude of
effort and complexities this solicitation requires.
NOT RELEVANT:
Present/past performance efforts did not involve any of the magnitude of
effort and complexities this solicitation requires.
RFP at 153.
Additionally, as it relates to the protest, the RFP
provided that when an offeror’s contracts were performed concurrently, “the
Government may consider these contracts in the aggregate in determining the
confidence rating, should the offeror’s present and past performance lend
itself to this approach.” RFP at 154.
Regarding price, the RFP indicated that offerors’ prices
would be evaluated for reasonableness and balance. RFP at 154.
The Air Force received 12 timely offers in response to the
solicitation, including proposals from AMG and JSW, and made an initial award
on September 9, 2008 to Family Entertainment Services (FES). JSW filed a protest challenging the award to
FES, which was dismissed as academic on October 3, based on the agency’s
decision to terminate the award and eliminate FES from the competition. Thereafter, the Air Force decided to make
award to AMG as the best value offeror; AMG had received a “satisfactory
confidence” past performance rating and submitted the lowest price of the
remaining offerors in the amount of $7,155,951.
JSW, which received a past performance rating of “substantial
confidence” and proposed a price of $8,742,463.40, then filed this protest.[1]
JSW challenges AMG’s “satisfactory confidence” past
performance rating. According to JSW,
the rating was unreasonable because, as a newly formed company, AMG had no past
performance record itself and the past performance record of its key personnel
involved contracts that were, in JSW’s view, significantly smaller in size,
magnitude, and complexity, as compared to the Robins AFB requirements. JSW also argues that AMG’s rating was flawed
because it was based on an unreasonable aggregation of AMG’s contracts. According to JSW, AMG should have received
“at best, a limited confidence rating.”
Protest at 4. In addition, JSW
argues that the best value decision was flawed because the Air Force failed to
resolve an “apparent latent ambiguity” in the specifications or to consider
AMG’s “unreasonably low price” as part of its best value decision. Protest at 2.
Our Office examines an agency’s evaluation of past
performance to ensure that it was reasonable and consistent with the stated
evaluation criteria and applicable statutes and regulations; however, the
necessary determinations regarding the relative merits of offerors’ proposals
are primarily matters within the contracting agency’s discretion. Kay & Assocs., Inc., B-291269,
Dec. 11, 2002, 2003 CPD para. 12 at 4. In
this regard, our Office will not question an agency’s determinations absent
evidence that those determinations are unreasonable or contrary to the stated
evaluation criteria. Id. Moreover, a protester’s mere disagreement
with the agency’s judgment does not establish that an evaluation was
unreasonable. UNICCO Gov’t Servs.,
Inc., B-277658, Nov. 7, 1997, 97-2 CPD para. 134 at 7.
As an initial matter, JSW’s suggestion that AMG was not
entitled to a satisfactory confidence rating because AMG was a newly formed
company is misplaced. While the record
reflects that AMG was in fact a newly formed company, and therefore did not
have a past performance record itself, the Air Force based its assessment of
AMG’s past performance on information submitted for AMG’s key personnel. Given that the RFP expressly authorized the
Air Force to consider past performance information regarding “any critical
subcontractors and key personnel,” RFP at 154, there is no basis for
challenging the agency’s evaluation in this regard.
JSW’s arguments regarding the relevance of AMG’s past
performance record are also without merit.
The record reflects that the Air Force considered past performance
information submitted by AMG with respect to four contracts performed by AMG’s
key personnel. These included: (1) a base-wide grounds maintenance contract
for Cannon AFB, New Mexico, which the Air Force considered to be “relevant”;
(2) a grounds maintenance services contract for the Federal Law Enforcement
Training Center (FLETC), Glynco, Georgia, which the Air Force also evaluated as
“relevant”; (3) a base-wide grounds maintenance services contract, for the
Naval Support Activity in Mechanicsburg, Pennsylvania, which the Air Force,
evaluated as “somewhat relevant”; and (4) a post-wide grounds maintenance services
contract at Fort Jackson, South Carolina, which the Air Force considered to be
“somewhat relevant.” Agency Report (AR),
Tab 12b, Performance Confidence Assessment Group Report, at 3-4.
In challenging the agency’s assessments regarding the
relevance of AMG’s contracts, JSW highlights the fact that AMG’s contracts were
for lower dollar values and did not involve some of the requirements of the
Robins contract. In this regard, JSW
argues that the Air Force’s relevancy assessments of the Cannon AFB and the
FLETC contracts were unreasonable given that the dollar values of the two
contracts were approximately one-quarter and one-half of the Robins AFB
contract, respectively. In addition, JSW
argues that the Cannon AFB contract is dissimilar because the air base is
located in a desert climate, which presents fewer grounds maintenance
challenges than Robins AFB, and because the contract did not involve composting
operations. According to JSW, the FLETC
contract should not have been considered relevant because, in addition to being
smaller in dollar amount than the Robins AFB contract, it did not require
composting operations or airfield maintenance.
JSW also takes issue with the Air Force’s assessment of the Navy contract
in Mechanicsburg and the Fort Jackson contract as “somewhat relevant.” JSW contends that, unlike the Robins AFB
contract, these contracts are for smaller values and do not involve many of the
Robins contract requirements.
We find the Air Force’s assessments of the relevance of AMG’s
past performance references to be reasonable and consistent with the evaluation
scheme set forth in the solicitation. As
noted above, the RFP defined the various degrees of relevance principally in
terms of the type and extent of the work effort in comparison to the work
required at Robins AFB, as opposed to particular dollar values. Thus, the fact that the dollar values of
AMG’s contracts were lower than the Robins AFB contract is not determinative of
the reasonableness of the agency’s evaluation. In this regard, the definition of “very
relevant” past performance included benchmark examples of the types of grounds
maintenance activities and numbers of maintained acres. These examples provided a guide to the
various relevancy ratings, since the ratings were defined by reference to these
activities and the amounts, and kinds, of acreage specified.
In assessing AMG under the past performance factor, the
record reflects that the Air Force compared the types of activities performed
and the number of acres involved under AMG’s referenced contracts, with the
activities and acres identified in the RFP’s definitions of relevance. Specifically, the Air Force concluded that
the Cannon AFB contract, which was a performance-based contract, was relevant
based on the fact that it required similar grounds maintenance activities, such
as maintaining 63 acres of enhanced grounds, 346.6 acres of improved grounds,
1,584 acres of semi-improved grounds, and 18.4 miles of perimeter fence
grounds.[2] The Air Force indicated that the Cannon AFB
contract was not considered “very relevant” because it lacked composting
operations. AR, Tab 12b, Performance
Confidence Assessment Group, at 4. Similarly,
the FLETC contract was considered relevant where it involved maintaining 17
acres of enhanced grounds, 680.54 acres of improved grounds, and 456.35 acres
of semi-improved grounds, amounts and kinds of acreage which were comparable to
those required at Robins AFB. In rating
this contract as relevant, as opposed to very relevant, the Air Force
specifically considered the fact that the contract did not include airfield
maintenance and composting operations. Id.
at 5.
The Navy Mechanicsburg and Fort Jackson contracts were
considered only “somewhat relevant,” which, as indicated above, was defined as
involving some of the magnitude of effort and complexities required under the
RFP. The Air Force’s evaluation of these
contracts as only “somewhat relevant” was based in part on the fact that they
did not involve airfield maintenance or composting operations. In addition, the number of acres maintained
under the Navy Mechanicsburg contract was considered to be “significantly less
than what is required by the solicitation,” and, while the acres maintained
under the Fort Jackson contract were comparable to the Robins AFB contract, the
effort did not include maintenance around runways, maintenance of irrigation
systems, or perimeter fencing. Id.
at 6.
Based on this record, which reflects the Air Force’s
consideration of the activities, scope, and complexity of AMG’s past
performance information, we have no basis to conclude that the Air Force’s
evaluations regarding the relevance of AMG’s past performance references was
unreasonable.
JSW also challenges the agency’s consideration of AMG’s
past performance record in the aggregate when it assigned AMG a “confidence”
past performance rating. Notwithstanding
the fact that the solicitation expressly authorized the Air Force to consider
an offeror’s past performance information in the aggregate for the purposes of
making its overall confidence assessment, aggregation of AMG’s contracts was
not appropriate, according to JSW, because the smaller values of its contracts
do not reasonably lend themselves to aggregation. In JSW’s view, a long-term, high dollar value
contract such as the Robins AFB contract is objectively different in terms of
magnitude and complexity from AMG’s smaller contracts, and therefore presents
fundamentally different challenges from the contracts which formed the basis of
AMG’s past performance record. The
agency, however, decided aggregation was appropriate given that AMG’s past
performance record was based on contracts that were in many instances performed
concurrently, and the obligations, when combined, exceeded the Robins
requirements for maintaining improved grounds, semi-improved grounds, airfield
grounds, and perimeter fencing. AR, Tab
13B, Source Selection Decision, at 6.
While JSW may ultimately disagree with the agency’s aggregation
assessment, its disagreement does not render the agency’s decision
unreasonable.
Finally, JSW argues that the agency failed to address a
“latent ambiguity” in the RFP regarding the agency’s requirements, which
purportedly caused JSW and AMG to submit proposals based on different
understandings of the agency’s requirements, and thereby allowed AMG to gain a
competitive advantage in terms of price.
Specifically, JSW asserts that the performance work statement is
ambiguous where it requires the contractor to “maintain” enhanced grounds to a
specified height, while requiring a contractor to “mow” improved grounds to a
specified height. RFP, Statement of Work
at 2. According to JSW, it interpreted
the terms “maintain” and “mow” as synonymous, thereby requiring the contractor
to ensure that the grass does not exceed the specified height between
cuttings. JSW asserts that the term
“mow” could have been interpreted to simply mean cutting the grass to a
specific height, without also maintaining it at that height in between
mowings. The difference is significant,
according to JSW, because in order to maintain the fast growing grass at Robins
AFB, JSW anticipated using costly chemicals to control growth between mowings;
the other option--mowing the improved grounds almost constantly--would be even
more costly. Protester’s Comments at 9
n.2. According to JSW, AMG’s price was
based on simply cutting the grass of the improved grounds, and not maintaining
the grass to a particular height between mowings, and, as a consequence, AMG’s
price was “unreasonably low.”[3]
Even assuming that the RFP’s use of the terms “maintain”
and “mow” created an ambiguity regarding the grass cutting requirements at
Robins AFB, JSW offers no evidence to show that AMG and JSW submitted proposals
based on different interpretations of the requirements. Absent such a showing, JSW has failed to
establish that it was prejudiced as a consequence of the alleged
ambiguity. See McDonald-Bradley,
B‑270126, Feb. 8, 1996, 96-1 CPD para. 54 at 3 (prejudice is an essential
element of any viable protest). In this
regard, JSW theorizes that AMG based its proposal on the more relaxed
interpretation as reflected by AMG’s price, which is “too low” to otherwise
perform the work. The mere fact that
AMG’s price is low, however, does not necessarily support the inference drawn
by JSW regarding AMG’s understanding of the requirements since an offeror may
have numerous legitimate business reasons for proposing a low price, including
submitting a below cost offer.[4] See M-Cubed Info. Sys., Inc.,
B-284445, B-284445.2, Apr. 19, 2000, 2000 CPD para. 74 at 8 (indicating that there
is no prohibition against an agency accepting a below-cost offer on a
fixed-price contract).
JSW also argues that AMG’s understanding of the
solicitation requirements is demonstrated through statements allegedly made by
AMG’s vice president to JSW’s owner.
Specifically, JSW’s owner submitted an affidavit representing that he
had asked AMG’s vice president how AMG was going to maintain the improved grass
at its “low price,” and AMG’s vice president indicated that he intended to mow
the improved grounds and did not plan to use chemical “spray” as JSW had
planned. Declaration of JSW’s Owner,
Jan. 26, 2009. These statements,
however, do not demonstrate that AMG’s understanding of the requirements was
any different from JSW’s since, by its own admission, mowing the improved
grounds was a method of maintaining the grass at a particular height. See Protester’s Comments at 9
n.2. Because the record fails to
establish that AMG actually interpreted the solicitation provisions as JSW now
claims, JSW has failed to establish that it suffered any prejudice associated
with the latent ambiguity it now alleges.
The protest is denied.
Daniel I. Gordon
Acting General Counsel
[1] JSW filed two prior protests challenging the award to AMG. The agency took corrective action in response to each of these protests.
[2] The RFP included a requirement to maintain perimeter fences at Robins “to be free of all vegetation growth” and to “trim any vegetation encroaching through the fence.” RFP at 162.
[3] In
each of JSW’s prior protests challenging the award to AMG, JSW argued that the
award to AMG was improper because AMG’s price was unreasonably low. Recognizing that whether AMG’s price is too
low concerns the question of whether its price is “unrealistic,” rather than
“unreasonable,” since price reasonableness concerns whether a price is too
high, we summarily dismissed JSW’s arguments in this regard because they failed
to set forth a valid basis of protest.
The solicitation did not require the agency to evaluate prices for
realism and an offeror, in its business judgment, properly may decide to submit
a price that is extremely low. Brewer-Taylor
Assocs., B-277845, Oct. 30, 1997, 97-2 CPD para. 124 at 4. To the extent JSW has again challenged the
agency’s failure to consider the fact that AMG’s price was too low, we again
dismiss this aspect of JSW’s protest for the reasons stated previously.
[4] The question of whether AMG is capable of performing the work at the price it has proposed is ultimately a matter of responsibility. In this case, the Small Business Administration, which has authority regarding responsibility determinations of small businesses such as AMG, specifically found AMG responsible through the issuance of a certificate of competency for AMG after the agency had initially found AMG nonresponsible.