B-400065, Aquaterra Contracting, Inc., July 14, 2008
Decision
Matter of: Aquaterra Contracting, Inc.
Timothy
A. Sullivan, Esq., Payne Hackenbracht & Sullivan, for the protester.
Parag
J. Rawal, Esq., and Deena G. Braunstein, Esq., Department of the Army, Corps of
Engineers, for the agency.
Susan K. McAuliffe, Esq., and Christine S. Melody, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest of agency’s rejection of bid as late is denied where bidder’s failure to address and label its bid package as instructed by the solicitation was paramount cause of its late arrival to bid opening location.
DECISION
Aquaterra Contracting, Inc. protests the rejection of its bid as late
under invitation for bids (IFB) No. W912P8-08-B-0019, issued by the Department
of the Army, Corps of Engineers, for dolphin replacement work at Calcasieu
Lock, Calcasieu Parish, Louisiana.
The IFB, as amended,
required that sealed bids be submitted by
Aquaterra submitted its bid
via commercial carrier in a sealed envelope that failed to identify in any way
that the package was time-sensitive or contained a bid (no solicitation number
or bid opening information was marked on the envelope); the protester failed to
address the envelope to the amended point of contact and failed to address the
package to the post office box address identified in the IFB for the submission
of bids. Rather, Aquaterra submitted its
bid in an envelope addressed to “Contracting Officer” at the street address of
the agency’s contracting division, which address was identified in the
solicitation amendments as the office that issued the amendments.[2]
Aquaterra’s bid package
arrived in the agency’s mailroom at
The protester’s bid package
and another firm’s bid package were delivered to the contracting division at
approximately
The next day, the contracting
officer handling the procurement reasoned that, since Aquaterra’s bid package
and the other firm’s bid package had been received at the mailroom
approximately 4 hours prior to bid opening, it was government mishandling that
caused the bids to arrive at the bid opening location late. After applying the applicable 10-percent
price preference for Historically Underutilized Business Zone firms, Aquaterra’s
bid became low and award was made to the firm.
However, in reviewing an agency-level protest filed by the bidder next
in line for award, alleging that the Aquaterra bid was submitted late, the
contracting officer for the first time recognized that Aquaterra’s bid package
envelope had not been addressed or labeled as directed by the solicitation. The contracting officer concluded that the
firm had significantly contributed to the lateness of its bid, and, finding
that government mishandling was not the paramount cause of the lateness of the
bid, the contracting officer terminated the award, rejecting the protester’s
bid as late.[3] This protest followed.
Aquaterra contends that its
bid was not late, since it was received by the agency’s mailroom, and possibly,
by the contracting division, before the
As a general rule, bidders
are responsible for delivering their bids to the proper place at the proper
time, and late delivery of a bid generally requires its rejection even if it is
the lowest bid. J.C.N. Constr. Co.,
Inc., B-270068, B-270068.2,
While a late hand-carried
bid may be considered if it is determined that the late receipt was due
primarily to government mishandling after receipt at the government
installation, a late bid should not be accepted if the bidder significantly
contributed to the late receipt by not acting reasonably in fulfilling its own
responsibility to submit its bid in a timely manner. Comspace Corp., B-281067,
The protest is denied.
Gary L. Kepplinger
General Counsel
[1]Amendment No. 2 to the solicitation notified all prospective bidders that the contracting specialist initially identified in the IFB would no longer be the point of contact for the procurement and identified another contracting specialist as the new point of contact.
[2] Aquaterra notes that the contracting division address is the only office location identified in the amended solicitation and that the post office box provided for bid submission is inapplicable to handcarried bids submitted by commercial carriers that require a street address for delivery.
[3] The agency reports that, since the firm had already ordered the required steel for the work, it only partially terminated the award in order to receive the ordered steel.
[4] To the extent the protester speculates that even if it had properly identified on its bid envelope that a bid was enclosed, the agency would have mishandled its bid, as it allegedly did for the other bid delivered late with Aquaterra’s bid package (where that other bid was apparently marked with the solicitation number and bid opening information), we do not find Aquaterra’s speculation in this regard persuasive as it provides no basis for us to question that Aquaterra’s own actions were the paramount cause of its bid’s late receipt. The protester’s speculative surmise in this regard merely anticipates improper action by the agency on what would be a materially different set of facts than is present here. In any event, the argument fails to account for an additional defect in Aquaterra’s bid submission, the firm’s failure to address its bid package to the appropriate contact, which alone has been found to preclude a finding of government mishandling (i.e., even where a bid package is labeled with solicitation and bid opening information). See Comspace Corp., supra.







