B-310927.2, Tremco Incorporated--Costs, April 21, 2008
Decision
Matter of: Tremco Incorporated--Costs
Peter F. Garvin, III, Esq., and Grant H. Willis, Esq., Jones Day, for the protester.
Charlma
Quarles, Esq., Kenneth MacKenzie, Esq., and Edward Carney, Esq., Department of
Veterans Affairs, for the agency.
Susan K. McAuliffe, Esq., and Christine S. Melody, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Request for reimbursement of
protest costs is denied where record fails to establish that the agency delayed
taking corrective action in the face of a clearly meritorious protest.
DECISION
Tremco Incorporated requests that we recommend reimbursement of the costs it
incurred in connection with filing and pursuing a protest challenging the
selection of Alliance Roofing as the successful vendor under request for
quotations (RFQ) No. VA-241-07-RQ-0179, issued by the Department of
Veterans Affairs (VA) for roof replacement work at the
On
By letter of January 14,
Tremco filed its current request for a recommendation for reimbursement of the firm’s
costs of filing and pursuing its protest.[1] Tremco alleges that the agency’s corrective
action was unduly delayed and that it was taken in response to meritorious
protest contentions.
Where a contracting agency takes action which renders a
protest academic prior to our issuing a decision resolving the merits of the
protest, our Office may recommend that the protester be reimbursed the costs of
filing and pursuing the protest. Bid
Protest Regulations, 4 C.F.R. sect. 21.8(e) (2007); Information Ventures,
Inc.--Costs, B-294567.2,
In our view, the
protester’s request for reimbursement of protest costs is based on an argument
that neither establishes the meritorious nature of its protest issues (which,
in any event, are unrelated to the basis upon which the agency took corrective
action) nor demonstrates that the agency unduly delayed taking corrective
action. The protester instead essentially
suggests that, since the agency had told it, during its agency-level protest,
that a bond had been submitted by Alliance, but apparently had not noticed the
untimely nature of the bond, the agency’s subsequent rejection of the Alliance
quotation based on the untimely bond after Tremco filed a protest with our
Office constitutes unduly delayed corrective action. Tremco generally contends that if the
impropriety regarding the bond had been discovered during the agency-level
protest (even though Tremco did not raise any issue regarding the bond), and if
the Alliance quotation had been rejected earlier because of the impropriety, Tremco
would not have had to file its protest to our Office, and, as a result, it should
be reimbursed for the costs of doing so.
We see no basis to recommend
recovery of protest costs here, since Tremco’s theory lacks the essential
elements necessary to support a recommendation for reimbursement of protest
costs. As an initial matter, there is no
nexus between Tremco’s protest contentions and the basis for corrective action;
Tremco never raised the timeliness of the awardee’s bond in its protest to our
Office. Thus, Tremco has no basis for
reimbursement on that issue. See Takota
Corp.--Costs, B‑299600.2,
The request for reimbursement of costs is denied.
Gary L. Kepplinger
General Counsel
[1] On the same date, Tremco also filed a protest of the agency’s intended corrective action, contending that instead of resoliciting the requirement, the agency should select Tremco as the successful vendor to perform the work required under the RFQ. The agency filed a report on the merits of that protest responding to Tremco’s protest contentions. Tremco failed to file comments on the report, as required, and its protest was dismissed.

