B-310801; B-310801.2, NHIC Corporation, February 12, 2008
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective Order. This redacted version has been approved for public release.
Decision
Daniel R. Forman, Esq., John E. McCarthy Jr., Esq.,
Shauna E. Alonge, Esq., and Jonathan M. Baker, Esq., Crowell & Moring LLP,
for the protester.
W. Jay DeVecchio, Esq., Kevin C. Dwyer, Esq., Daniel E.
Chudd, Esq., Eric R. Haren, Esq., and James C. Cox, Esq., Jenner & Block
LLP, for Palmetto GBA, LLC, an intervenor.
Christine Simpson, Esq., and Douglas Kornreich, Esq., Department
of Health & Human Services, for the agency.
Sharon L. Larkin, Esq., and James A. Spangenberg.,
Esq., Office of the General Counsel, GAO, participated in the preparation of
the decision.
DIGEST
Protest challenging cost realism analysis is denied, where agency performed a comprehensive analysis of all major cost elements and relied on subject matter experts to reasonably determine that proposed costs were consistent with each offeror’s technical approach and were realistic for the work to be performed.
DECISION
NHIC Corporation protests the
award of a contract to Palmetto GBA, LLC, issued by the Department of Health
& Human Services, Centers for Medicare & Medicaid Services, for the
administration of Medicare claims. NHIC
challenges the agency’s cost realism evaluation.
The RFP provided for award of a cost-plus-award-fee
contract for the combined administration of Part A and Part B Medicare
fee-for-service claims. Under this
contract, a “Medicare Administrative Contractor” (MAC) is to provide claims
processing, payment, and other administrative services for “Jurisdiction 1,”
which consists of
The RFP contemplated a 5-year period of performance, which
included a 12‑month “implementation” period, a 9-month “base period,”
four 1-year option periods, and a 6‑month period for “outgoing contractor
workload transition activities.” RFP sect.
F.2. The RFP provided that award of the
contract would be made on a best-value basis, considering the equally weighted
factors of technical approach, implementation, management controls, past
performance, and corporate experience; when combined, these factors were more
important than cost, which was not a weighted factor.
[t]he purpose of this cost realism [analysis] will be to determine what the Government should realistically pay for the proposed effort, if the offeror’s proposed costs reflect the offeror’s understanding of the Government’s requirements, and if the proposed costs are consistent with the various elements of the offeror’s technical proposal.
The RFP instructed each offeror to provide a technical
proposal explaining its technical approach to performing the requirements
described in the statement of work, and a business proposal explaining the
bases for its proposed costs. To prepare
the cost estimates contained in the business proposal, offerors were instructed
to use the “annual workloads” for the base and option years as provided in the
RFP. These workloads estimated the
number of items to be processed annually for various functions that the MAC
would perform under Medicare Parts A and B, including annual workloads for
claims processing; appeals processing; provider customer service; provider
reimbursement and audit; provider enrollment, inquiries, and oversight; medical
review; and other “Medicare Integrity Program” services.
Both NHIC and Palmetto submitted technical and business
proposals in response to the solicitation that were found to be in the
competitive range. Palmetto’s initial
proposed cost was [REDACTED] and NHIC’s initial proposed cost was [REDACTED]. Agency Report (AR), Tab 56, Source Selection
Determination, at 2. A technical
evaluation panel (TEP) evaluated the technical proposals and a business
evaluation panel (BEP) evaluated the business proposals.[3] To assist the BEP, a cost subject matter
expert (SME) initially performed a cost realism analysis based on historical
data from prior contracts. This analysis
estimated that the cost to the government of performance by Palmetto would
likely be $709,558,450, and the cost of performance by NHIC would likely be
$600,294,065.[4] AR, Tab 91, Initial Cost Realism Analysis,
at 33, 38. However, the SME stated
that this analysis “does not reflect any adjustments to account for any program
requirements changes which may
have been implemented during or subsequent to FY2006 that may be reflected in [each offeror’s] proposed cost and
fee.”
After discussing the analysis with the cost SME and the evaluation teams, the contracting officer determined that this initial cost realism analysis had “limited applicability” because the analysis did not take into account changes to program requirements, efficiencies or innovations due to each offeror’s unique technical approach, or differences in cost reporting requirements between the MAC contract and prior contracts; in addition, the cost realism analysis for Palmetto’s proposal included costs associated with a team member who performed prior contracts but who was not proposed to perform the MAC contract here. Tr. at 43-55; Contracting Officer’s Statement paras. 5-6, 20-22. For these reasons, the contracting officer and evaluation teams decided not to rely on this analysis and, instead, decided to take a “bottom up” approach to the cost realism evaluation. This “bottom up” approach was to “break [the proposal] down so that we do account for [the offeror’s] approach, that we can determine if it reflects a clear understanding of the statement of work, and is it realistic for the work to be performed?” Tr. at 51, 174; AR, Tab 56, Source Selection Determination, at 4.
The TEP and BEP were asked to perform a new cost realism
analysis to determine whether proposed costs (including labor hours, labor
rates, fee structure, and other costs) were realistic based on each offeror’s
approach. The functional areas evaluated
for cost realism included (1) implementation costs, (2) level of effort as
it relates to claims processing, provider customer service program, appeals,
audit and reimbursement, medical review/local coverage determinations, fraud
and abuse, Medicare secondary payer, and provider enrollment, (3) travel, (4)
subcontracts, and (5) fee proposed (base and award). E.g., AR, Tabs 59-62, Final Cost
Realism Analysis Memos and Supplemental Memos (Palmetto and NHIC).
As part of this cost realism analysis, the BEP consulted with the Defense Contract Audit Agency (DCAA), which reviewed the proposed costs (including labor rates) and accounting practices of each offeror and their major subcontractors.[5] AR, Tabs 71-81, DCAA Audit Reports. In addition, the TEP was tasked to review whether the mix of labor categories and number of hours proposed reflected a clear understanding of the requirements, were consistent with the offeror’s proposed approach, and were reasonable and realistic for the work to be performed. Contracting Officer’s Statement paras. 32-33; Tr. at 492-93. Although several of the TEP members had expertise in particular areas and performed their own independent analysis, Tr. at 431-32, 499-502, SMEs for the functional areas were also consulted and asked to assist with this analysis.[6] The SMEs reported their analyses to the TEP, each indicating that there was no basis for adjustment in all but one of the functional areas for one of the offerors,[7] and provided the TEP with a list of questions about the proposals to be forwarded to the offerors. E.g., NHIC Hearing exhs. 24(c) and 28(c),
SME’s Cost Realism Adjustments and Question Summaries of NHIC’s and Palmetto’s Initial Business Proposals; exh. 31, Cost Realism Analysis Worksheets, at 69-74. The TEP considered the SMEs’ questions and, in some cases, was able to answer the question without forwarding it to the offeror or determined that a discussion question was unnecessary; other questions were presented to offerors during discussions. Tr. at 234, 506-07.
Several rounds of discussions were held with offerors that
resulted in each offeror making adjustments to proposal pricing. As reflected in final proposal revisions
(FPR), NHIC decreased its proposed cost to $450,598,174 (based on approximately
[REDACTED] labor hours), and Palmetto increased its proposed cost to
$357,663,785 (based on approximately [REDACTED] labor hours). AR, Tab 56, Source Selection Determination,
at 2; Tab 58, SSB Presentation, at 10.
As part of the ongoing cost realism analysis, the TEP evaluated the
discussion responses and FPRs by “verify[ing]” and “validat[ing]” the responses
provided by the offerors. Tr. at
512. In most instances, further
input from SMEs was deemed unnecessary, although some consultation with SMEs
did occur. Tr. at 503, 508-09. Ultimately, the TEP was responsible for
making recommendations to the BEP as to whether adjustments to proposed labor
hours were warranted. Tr. at 455,
532. No adjustments were recommended. AR, Tabs 59-62, Final Cost Realism Analysis
Memos and Supplemental Memos (Palmetto and NHIC).
The results of the SME and TEP analyses were forwarded to the BEP for consideration. Based on all of the information before it, the BEP concluded that each offeror’s proposed costs “are realistic for the work to be performed; reflects a clear understanding of the requirements; and are consistent with the unique methods of performance and materials described in the Offeror’s Technical Proposal.” E.g., AR, Tab 59, Final Cost Realism Analysis Supplemental Memo (Palmetto), at 2, 4; see Tab 60, Final Cost Realism Analysis Supplemental Memo (NHIC); Tabs 61-62, Final Cost Realism Analysis Memos.
The contracting officer presented the results of the technical and cost evaluation to the source selection board (SSB) and source selection authority (SSA). Tr. at 108-09. With regard to the technical evaluation, both NHIC’s and Palmetto’s proposals were rated “very good” overall and found to be “essentially technically equal.” AR, Tab 56, Source Selection Determination, at 2. With regard to the cost evaluation, the contracting officer explained how the cost realism analysis was performed and identified the costs of each offeror’s proposal for direct labor, fringe, overhead, travel, subcontractors, other direct costs, and base and award fee. AR, Tab 57, Supplemental SSB Presentation, at 5; Tab 58, SSB Presentation, at 10, 13. Recognizing that there was a $92 million delta between NHIC’s and Palmetto’s proposals, the contracting officer advised the SSB and SSA, in some detail, that Palmetto’s proposed costs were realistic due to its business strategy, proposed innovations, and efficiencies.[8] AR, Tab 57, Supplemental SSB Presentation, at 2-4; Tr. at 89-92, 105-06. For example, among the various reasons identified by the contracting officer why Palmetto’s proposed costs were realistic (described more fully below), she noted that, unlike NHIC, Palmetto [REDACTED]. See Tr. at 26. After reviewing all of the presented information, the SSA selected Palmetto’s lower cost and technically equal proposal for award. NHIC protested to our Office, complaining that the agency’s cost realism analysis was inadequate, undocumented, and flawed, and did not reasonably account for the $92 million difference between proposals.[9]
When an agency evaluates a proposal for the award of a
cost-reimbursement contract, an offeror’s proposed estimated costs are not
dispositive because, regardless of the costs proposed, the government is bound
to pay the contractor its actual and allowable costs. Federal Acquisition Regulation (FAR) sections
15.305(a)(1); 15.404-1(d); Tidewater Constr. Corp., B-278360,
NHIC contends that the cost realism analysis was not adequately documented. Although the record consists of multiple documents and reports reflecting the analysis performed by the SMEs, TEP, and BEP, NHIC contends that the documents themselves do not explain the agency’s rationale and contain only “checked boxes [referring to worksheets where a SME or TEP member checked “yes” or “no” as to whether there was a basis for adjusting costs], conclusory assertions, and discussions questions” to show that costs were realistic. NHIC’s Post-Hearing Comments at 2.
We find that the record shows that the agency performed a comprehensive and thorough cost realism analysis that considered all of the major cost elements for each of the functional areas to be performed under the contract. The agency relied on the TEP members and SMEs, each of whom has special expertise in the functional areas, to review whether the proposed labor hours and mix of labor categories were realistic for the work to be performed and were consistent with the offeror’s technical approach. In addition, the BEP consulted with the DCAA to verify that labor rates and other costs were reasonable.
The record contains extensive contemporaneous documentation--numerous spreadsheets, worksheets, discussion questions and responses, and reports--that were created by the SMEs, TEP, and BEP. Although it is true that the documents are replete with conclusory statements that proposed costs were realistic, the record nonetheless evidences that a comprehensive cost realism analysis was performed and contains documents, such as the briefing slides to the SSB and the source selection determination, that provide the rationale for the agency’s cost realism conclusions.[10] E.g., AR, Tab 58, SSB Presentation, at 10-13; Tab 57, Supplemental SSB Presentation, at 2-4; Tab 56, Source Selection Determination, at 3-4; see also Contracting Officer’s Statement paras. 61-73.
During the hearing held by our Office, and as reflected in the contemporaneous documents, the agency explained why, and how, the evaluators determined that Palmetto’s proposed costs, including labor costs, were realistic, even though they were lower than the costs proposed by NHIC.[11] Specifically, as stated above, Palmetto took advantage of the opportunity, throughout its proposal, to [REDACTED]. Tr. at 26. Other identified reasons for Palmetto’s lower costs were that Palmetto [REDACTED] and identified a number of “efficiency drivers” for claims processing, appeals, and medical review. AR, Tab 56, Source Selection Determination, at 2-3; Tab 57, Supplemental SSB Presentation, at 2‑4; Contracting Officer’s Statement paras. 61-73; Tr. at 17-27, 30-31, 34, 38-39, 105-06, 406-17. Specific examples of some of these “efficiency drivers” for three of the major activities (claims processing, appeals, and medical review), as enumerated in the contemporaneous documents, include:
· Claims Processing
[REDACTED]
·
Appeals
[REDACTED]
·
Medical
Review
[REDACTED]
AR, Tab 56, Source Selection Determination, at 3; Tab 57, Supplemental SSB Presentation, at 2-4.
NHIC contends that there is no basis to conclude that any
of the proposed “efficiency drivers” would result in cost savings, since the
agency failed to quantify any of the asserted cost savings. However, an adequate cost realism analysis
does not require an in‑depth verification of each and every item; an
agency may reasonably rely on statements in an offeror’s proposal which
demonstrate the realism of its proposed costs, without independently verifying
each item of proposed costs. Pacific
Architects and Eng’rs, Inc., B‑274405.2, B-274405.3, Dec. 18, 1996,
97‑1 CPD para. 42 at 7; Ferguson-Williams, Inc.; Hawk Mgmt. Servs.,
Inc., B-232334, B‑232334.2, Dec. 28, 1988, 88-2 CPD para. 630 at 6. Here, Palmetto’s proposal explained that its
“labor estimating approach” was based on [REDACTED]. Palmetto’s proposal identified [REDACTED].[12]
Agency Hearing exh. A, Palmetto’s
Initial Proposal, at 26-61. As the
contracting officer explained, Palmetto “did a really good job of laying out
‘this is what we’ve been doing, this is what we’re going to do for you now, and
this is the impact.’”[13]
Tr. at 91, 174. The SMEs and TEP members considered this
information contained in Palmetto’s proposal, looked to see whether the
approach was feasible, and based on their own experience, could find no basis
to upwardly adjust Palmetto’s proposed costs.[14] Tr. at 453, 483, 492-93, 522‑23. NHIC has not shown that the agency’s evaluation
was unreasonable.
NHIC also complains that the evaluation cannot be found reasonable
because the agency needed more information to conduct its analysis. In this regard, it notes that the SMEs
advised the TEP that there was no basis to adjust Palmetto’s proposed costs,
but at the same time posed questions that suggested that information was needed
before such a determination could be made.
NHIC points to the analysis of Palmetto’s initial proposal in the
functional area of provider education and training, which is one aspect of the
provider customer service program.
There, the SME reported that Palmetto’s subcontractor “did not provide a
description of the labor categories used for the [provider customer service
program]” and thus it “is not clear what kind of work people in each of these
categories will be doing,” and therefore recommended that this be a discussions
question. NHIC Hearing exh. 28(c), SME’s
Cost Realism Adjustments and Question Summary of Palmetto’s Initial Business
Proposal, at 4. NHIC notes that despite
this statement, the contemporaneous worksheets of the SME’s analysis show a
check mark in the box indicating that there was no basis to adjust Palmetto’s
proposed costs.[15] NHIC Hearing exh. 31, Cost Realism Analysis
Worksheets, at 69.
As the SME who evaluated this area explained at the
hearing, “the title of [the labor] category did provide some description of
what that [full time equivalent] would be doing. So there was some basis to make a
determination” as to whether the proposed costs were realistic. Tr. at 368-69; see Tr. at 371-72,
377. Where, for example, she saw a
category that was identified as “representative,” she assumed it referred to a
“customer services representative” or “written correspondence
representative.” Tr. at 369. However, she recommended to the TEP that a
discussion question be presented to Palmetto seeking further description of the
labor categories. A discussion question
was presented to Palmetto, and the firm responded. Although the SME was not asked to review
Palmetto’s response, one of the TEP members reviewed the information and
determined that there was no basis to adjust Palmetto’s proposed labor
hours. Tr. at 377, 471.
We acknowledge that the record does not contain any
documentation confirming that a TEP member analyzed Palmetto’s costs for
provider customer service after receipt of that firm’s discussion responses,
other than a conclusory statement by the BEP that Palmetto “adequately
addressed this issue” during discussions.
AR, Tab 61, Final Cost Realism Memo (Palmetto), at 3. However, even if we were to conclude error
here, NHIC has not shown that it has been prejudiced as a result.[16] That is, NHIC has not shown that Palmetto’s
costs are understated for the provider customer service program (or any other
area for that matter), or that the agency was incorrect in concluding that
adjustments were not warranted.
Furthermore, we note that the quantity of hours for the provider
customer service program is very small in relation to the overall
contract. Agency Hearing exh. A, Palmetto’s
Initial Proposal, at 28. Thus, we
cannot see how an adjustment in this area, even if warranted, would overcome
the $92 million cost difference between proposals.[17]
NHIC also asserts that the agency should have relied more
heavily on the initial cost realism analysis, which the agency rejected in
favor of performing its “bottom up” approach, particularly given that this was
a cost analysis technique permitted by the FAR.
NHIC’s Comments at 20; see FAR sect. 15.404-1(c)(2)(i)(B). However, the FAR does not require that
agencies rely on historical data comparisons, and, in any event, the agency
reasonably explained why the historical data used here to compile the initial
cost realism analysis (as well as the independent government estimate) was of
“limited applicability,” especially since it did not take into account each
offeror’s specific approach. Tr. at
49-50. Similarly, NHIC contends that the
agency should have compared proposals to reconcile labor hour disparities. NHIC’s Comments at 9; FAR sect.
15.404-1(c)(2)(iii)(C). Again, the FAR
does not mandate such comparisons and, in this case, such a comparison would
not be meaningful without considering the differences in technical
approaches. See The Futures
Group Int’l, B‑281274.2,
In sum, NHIC has not shown the agency’s “bottom up”
cost realism evaluation to be unreasonable.
As discussed above, the agency followed a process that is consistent
with the FAR, in that the agency “independently review[ed] and evaluat[ed]
specific elements of each offeror’s proposed cost estimate to determine whether
the estimated proposed cost elements are realistic for the work to be
performed; reflect a clear understanding of the requirements; and are
consistent with the unique methods of performance and materials described in
the offeror’s technical proposal.” FAR
sect. 15.404-1(d)(1). Moreover, except
for its arguments that historical data should have been the basis for the cost
realism analysis, which we have rejected, NHIC has not demonstrated, or even
attempted to quantify, that cost realism adjustments in the challenged areas
would have eliminated the $92 million cost differential and resulted in NHIC’s
most probable cost being lower than Palmetto’s; thus, NHIC has not shown that
its proposal, which was technically equal to Palmetto’s, had a substantial chance
for award.
NHIC also asserts that the contracting officer provided
the SSB and SSA with “materially inaccurate and unsupported information”
upon which to base the source selection decision. NHIC’s Post‑Hearing Comments at
42. For example, it asserts that the
briefing slides presented to the SSB and SSA “grossly understated the delta in
proposed labor hours.”
As another example, NHIC contends that the contracting
officer falsely represented in the briefing slides that Palmetto proposed less
expensive labor rates than NHIC, contending that its fully burdened labor rates
are, in fact, lower than Palmetto’s.
However, the contracting officer explained that her reference to lower
labor rates referred to direct labor costs only and that she made that clear to
the SSB and SSA, Tr. at 208-09, and the briefing slides identified all of the
cost elements for each offeror for both their original and final proposals,
including direct labor, fringe, overhead, travel, subcontractors, other direct
costs, general and administrative costs, base fee, and award fee. AR, Tab 58, SSB Presentation, at 10. The record does not show that the SSB or SSA
was misled.
Finally, NHIC complains that discussions were “misleading”
in that the agency asked only “superficial and narrow questions” and failed to
alert NHIC that its direct labor hours were overstated, thus leading NHIC to
believe that its staffing levels were competitive. NHIC’s Comments at 36-45. However, unless an offeror’s proposed cost is
so high as to be unreasonable or unacceptable, an agency is not required to
tell an offeror during discussions that its proposed cost is high in comparison
to a competitor’s proposed cost, even where cost is the determinative factor
for award. DeTekion Sec. Sys., Inc.,
B‑298235, B-298235.2,
Cherry Road Techs.; Electronic Data Sys. Corp.,
B-296915 et al.,
The protest is denied.
Gary L. Kepplinger
General Counsel
[1] Although both contractors have performed this work, NHIC is an incumbent contractor for Jurisdiction 1. Tr. at 89.
[2]
Transcript citations refer to the hearing on the protest that our Office held
on
[3] A past performance evaluation panel evaluated past performance.
[4] The independent government estimate, which was also based on historical data, was $536,897,009. AR, Tab 91, Initial Cost Realism Analysis, at 37, 42.
[5] Where the DCAA recommended adjustments, the agency notified the offeror during discussions, and the offeror made the appropriate adjustments in subsequent revised proposals. Agency’s Legal Memorandum at 46.
[6] The areas analyzed by SMEs were claims processing, provider customer service program, appeals, audit and reimbursement, medical review/local coverage determinations, comprehensive error rate testing, Medicare secondary payer, unique requirements, fraud and abuse, and implementation. AR, Tab 56, Source Selection Determination, at 4.
[7] An
initial upward adjustment to Palmetto’s proposal was recommended for its
proposed audit and reimbursement costs, based on the agency’s belief that the
costs of one of Palmetto’s proposed subcontractors were understated. However, Palmetto addressed the agency’s
concerns during discussions and upwardly adjusted its proposed costs
accordingly, thus making an adjustment to the proposed costs unnecessary. AR, Tab 61, Final Cost Realism Analysis Memo
(Palmetto), at 8-9.
[8] The RFP placed a premium on the offeror’s use of innovations. RFP sect. M.3; Statement of Work, sect. C.4.3.
[9] In
its initial protest, NHIC also challenged the technical and risk evaluation,
contending that it was unreasonable for both proposals to receive the same
technical rating because the agency “failed to give proper consideration to the
technical impact of Palmetto’s low pricing” and NHIC, as an incumbent, better
“understands what is required to successfully perform [the agency’s]
requirements.” Protest at 17‑19. In its comments, NHIC provided a number of
specific examples to support its protest, all of which are premised on its
belief that Palmetto’s staffing must be unrealistically low because NHIC’s
proposed staffing was higher. We find
this argument unpersuasive, given that both offerors have previously performed
this work and their proposals offered different technical approaches. The agency has explained that it evaluated
each offeror’s proposed staffing to ensure that the proposed labor mix and
number of hours were consistent with their approach and were feasible, Tr.
at 483, 493, and specifically with regard to Palmetto, the agency has
shown how the firm based its proposed labor mixes and number of hours on
[REDACTED]. Tr. at 17-40; Agency Hearing
exh. A., Palmetto’s Initial Proposal, at 25-61. NHIC has provided no convincing evidence that
the agency’s evaluation, or Palmetto’s technical approach, was unreasonable or
inconsistent with the RFP.
[10]
NHIC relies on National City Bank of Indiana, B-287608.3,
[11]
While we generally accord greater weight to contemporaneous evidence of an
evaluation and source selection decision, we will consider post-protest
explanations that provide a rationale for contemporaneous conclusions where, as
here, those explanations are credible and consistent with the contemporaneous
record. EDO Corp., B-296861,
[12] NHIC contends that its proposal identified similar efficiencies and innovations, but the agency persuasively explains that NHIC’s proposal [REDACTED]. Tr. at 26, 151, 154-55, 169, 417-18, 520-21, 577, 580.
[13] For example, Palmetto identified that [REDACTED]. Similarly, Palmetto [REDACTED], which translated into [REDACTED], and proposed to [REDACTED]. Agency Hearing exh. A, Palmetto’s Initial Proposal, at 34-35. NHIC asserts that because [REDACTED], the expansion of [REDACTED] would result in savings that are “immaterial.” NHIC Post-Hearing Comments at 57-58. However, we note that besides the foregoing efficiencies, Palmetto’s proposal identifies a number of other efficiencies and innovations that, in the aggregate, the agency could reasonably conclude demonstrated the realism of Palmetto’s proposed labor hours and costs. Agency Hearing exh. A, Palmetto’s Initial Proposal, at 26-51. NHIC has failed to show that the claimed savings would not be achieved.
[14] In some instances, where technology innovations did not have a great impact on historical data, the evaluators used historical data to validate the cost realism of Palmetto’s approach. Tr. at 335, 339-40, 424-25.
[15] It is unclear from the record who checked the box. As various agency witnesses explained, some worksheets were completed by the SMEs, and others were completed by the TEP based on the SMEs’ analysis. Tr. at 438, 464, 497, 534. Although NHIC argues that the agency’s “confus[ion]” over who was responsible for checking the box reveals a flawed evaluation, NHIC’s Post-Hearing Comments at 11, we find this to be inconsequential as to whether the underlying analysis was reasonable.
[16] Competitive
prejudice is a necessary element to every protest; we will not sustain a
protest unless the protester shows that but for the agency’s error, it has a
substantial chance for award. McDonald-Bradley,
B-270126,
[17]
NHIC points to another example, where the SME evaluating NHIC’s proposal for
the provider outreach and education function noted that NHIC had not provided
its assumptions regarding the percentage of calls it expected to handle by
“interactive voice response” (IVR) technology.
NHIC Hearing exh. 24(c), SME’s Cost Realism Adjustments and Question
Summary of NHIC’s Initial Business Proposal, at 3-4. Citing a SME comment in the contemporaneous
documentation, NHIC concludes that the SME made inappropriate assumptions
regarding NHIC’s IVR usage.
[18] That is, NHIC contends that including additional subcontractor to NHIC’s labor hours, as the slide represented, would have increased the [REDACTED] labor hour total. Conversely, excluding Palmetto’s service center labor, as the slide represented, would have reduced Palmetto’s [REDACTED] labor hour total. Thus, NHIC argues, the labor hour differential was even larger than represented in the slide.

