B-310661; B-310661.2, Karrar Systems Corporation, January 3, 2008
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective Order. This redacted version has been approved for public release.
Decision
Matter of:
Karrar Systems
Corporation
Kevin P. Connelly, Esq., Seyfarth Shaw LLP,
for the protester.
Ross Aboff, Esq., Archer & Greiner, PC,
for BANC3, Inc., an intervenor.
Daniel Pantzer, Esq., Denise M. Marrama,
Esq., and James F. Ford, Esq., Department of the Army, for the agency.
Mary G. Curcio, Esq., and John M. Melody,
Esq., Office of the General Counsel, GAO, participated in the preparation of
the decision.
DIGEST
1. Protest that agency failed to
hold meaningful price discussions with protester regarding reasonableness of
its proposed price is denied where agency did not find its price unreasonable
and brought its only pricing concern to protester’s attention.
2. Protest that awardee had an impermissible
conflict of interest is denied where agency thoroughly considered circumstances
in which awardee could have a conflict, and reasonably determined that there
was no actual or potential conflict.
DECISION
Karrar Systems Corp. protests the award of a contract to BANC3, Inc.,
under request for proposals (RFP) No. W15P7T-07-R-A226, issued by the
Department of the Army for program and administrative services for its R2
program. Karrar principally asserts that
the Army failed to provide it with meaningful discussions, and that BANC3 had
an impermissible organizational conflict of interest (OCI).
The solicitation
contemplated a “best value” award of a 5-year indefinite-quantity/ indefinite‑delivery
(ID/IQ) contract based on four evaluation factors (in descending order of
importance): technical (with subfactors
for three sample task orders--pre-award, post-award and budget), management
(with subfactors for transition plan to Aberdeen, transition plan, and
management plan), performance risk, and price.
RFP at 59. Four offerors
responded to the RFP. A source selection
evaluation board (SSEB) assigned the initial proposals adjectival ratings under
the technical and management factors and subfactors based on the proposals’
evaluated strengths and weaknesses.[1] Following the initial evaluation, a
competitive range determination, discussions, and the submission and evaluation
of final proposal revisions, Karrar’s proposal was rated good for the technical
factor, with subfactor ratings of good for the pre- and post-award sample task
orders, and acceptable for the budget sample task order, Final Source Selection
Briefing at 21; acceptable for the management factor, with subfactor ratings of
acceptable for transition to Aberdeen, good for transition plan, and acceptable
for management plan, id. at 37; and low for performance risk. BANC3’s proposal was rated overall acceptable under
the technical factor, with acceptable ratings for each subfactor, id. at
13; overall good under the management factor, with ratings of good for each
subfactor, id. at 29; and low for performance risk. Karrar’s proposed price was $25,119,864, and
BANC3’s was $17,251,531.92.
DISCUSSIONS
Karrar asserts
that the Army failed to provide it with meaningful discussions with respect to
its price proposal. The solicitation
contained historical workload data. In
its proposal, Karrar referred to an anticipated increase in workload during the
option years of the contract. Based on
this language, the Army questioned whether Karrar had based its price proposal on
the historical data in the RFP, and whether it understood that the contract was
being awarded as a 5-year ID/IQ contract, and not as a contract with option
years. AR at 14. During discussions, the Army advised Karrar
that: “Your proposal refers to Option
years. This will be a Five (5) Year
Indefinite Quantity Indefinite Delivery Type contract. Please confirm that your offer is based on
the historical workload provided in the Performance Work Statement.”
Karrar argues that
the price discussions were not meaningful because the Army did not specifically
ask what factors the firm had considered in determining its price. In this regard, Karrar asserts that it was
clear from its proposal that it had used factors other than the historical data
in determining its price. Karrar maintains
that the Army was obligated to point out the specific additional elements that
Karrar should not have considered in formulating its price, rather than merely
asking it to confirm that its price was based on the historical workload
information.
Discussions, when
conducted, must be meaningful; that is, they may not
mislead offerors and must identify deficiencies and significant proposal weaknesses
that could reasonably be addressed in a manner to materially enhance the
offeror’s potential for receiving award. Lockheed Martin Corp., B-293679 et al.,
The protester’s
discussions challenge is without merit.
First, the agency was not even required to conduct price discussions
here. In this regard, where an offeror’s
price
is not so high as to be unreasonable and thus unacceptable for award,
the agency is not required to advise the offeror during discussions that its prices are considered high. MarLaw-Arco MFPD Mgmt., B-291875,
OCI
Karrar asserts
that the agency improperly failed to consider that BANC3 has an impermissible OCI
due to the fact that it is a subcontractor to, and has a mentor‑protégé
agreement with, Lockheed Martin Corporation, one of the eight prime contractors
for the R2 program. Karrar’s assertion is
based on its claim that BANC3’s Internet website references the mentor-protégé
relationship.
The situations in
which OCIs arise are addressed in Federal Acquisition Regulation (FAR) subpart
9.5 and in decisions of our Office. As
relevant here, one type of OCI, which reflects concerns about a firm’s “impaired
objectivity,” consists of situations where a firm’s work under one federal
contract could entail its evaluating its own or a related entity’s performance
under another federal contract, thus undermining the firm’s ability to
render impartial advice to the government. FAR sect. 9.505-3;
The responsibility
for determining whether an OCI exists, and the extent to which a
firm should be excluded from the competition, rests with the contracting
agency, SRS Techs., B-258170.3,
The Army reports
that it was aware of the potential OCI here--the possibility that BANC3’s
relationship with Lockheed would undermine its ability to render impartial
advice to the agency under the contract--because BANC3 was performing in the R2
project office as a subcontractor under a task order issued to Lockheed, which
was to expire in August 2007, but was extended to October 31. AR at 10. The Army determined that, if BANC3 were
awarded the contract, it would have an impermissible OCI if it continued to work
with Lockheed or any other R2 prime contractor.
Accordingly, on Oct. 15, after BANC3 received the award, the Army met
with the firm to discuss its transition plans.
At this meeting, BANC3 indicated that it was withdrawing from all
teaming arrangements with R2 prime contractors and would not compete as a prime
contractor or subcontractor for any future R2 contract. BANC3 further indicated that it would not
have any contractual relationship with Lockheed after the current work order
expired on October 31. The Army concluded
that, since any services that could result in an OCI issue would not be ordered
until after the relationship between Lockheed and BANC3 ended, no impermissible
OCI existed. As for the alleged mentor‑protégé
agreement between BANC3 and Lockheed, the Army and BANC3 state that there is not
and never has been such an agreement.
BANC3 explains that the statement on its website was included in a draft
version of its company brochure because it explored the possibility of such an
agreement, but the agreement was never completed. The protester has provided no evidence to the
contrary. We find that, after thoroughly
and reasonably considering the possibility of an OCI, the agency reasonably
concluded that there existed no OCI that precluded BANC3 from participating in
the procurement or from receiving the award.
This argument thus provides no basis for questioning the award.
ABANDONED ISSUES
In its initial and supplemental protests, Karrar challenged the evaluation of its proposal under the technical and management factors on several grounds: its proposal should have been rated outstanding under the technical factor and subfactors; its proposal should have received evaluation credit for providing flow charts; the evaluators erroneously found that Karrar failed to notice an error on a sample form for the budget sample task; its proposal should have been rated outstanding or good, rather than acceptable, under the management factor; its proposal should have been accorded a strength for avoiding potential OCIs and for its willingness to satisfy the agency’s desire for a corporate partnering agreement; and that its proposal should have been accorded significant strengths for its extensive discussion of its approach to supporting R2 personnel requirements, and for its discussion of the role of its facility manager in coordinating the preparation for the R2 office relocation.
In its report in response to the protest, the Army conceded
one minor error in the evaluation, but refuted the remainder of the allegations,
specifically explaining the basis for Karrar’s proposal ratings, as well as the
reasons why its proposal was not assigned the strengths Karrar argued should
have been assigned. In its comments in
response to the agency report, Karrar did not dispute the agency’s explanation
of the basis for the technical and management evaluations. Accordingly, we consider these issues
abandoned and will not consider them.[2]
See Council for Adult &
Experiential Learning, B-299798.2,
The protest is
denied.
Gary L. Kepplinger
General Counsel
[1] Under the technical factor and subfactors, proposals were rated outstanding, good, acceptable, or unacceptable. Under the management factor and subfactors, proposals also could be rated as susceptible to being made acceptable.
[2]Karrar also abandoned its arguments that BANC3 had an OCI due to its relationship with a second R2 prime contractor; that BANC3 had access to information that provided it with a competitive advantage; and that the agency failed to hold meaningful discussions with Karrar with respect to its technical proposal.
[3] Karrar has filed a supplemental protest in which it further challenges the evaluation of its proposal and argues that the agency did not treat offerors equally. We are developing the record in that protest and will address these arguments in a separate decision.

