B-299906, Bighorn Lumber Company, Inc., September 25, 2007
Decision
Matter of: Bighorn Lumber Company, Inc.
Alan
I. Saltman, Esq., Saltman & Stevens, P.C., for the protester.
Lori
Polin Jones, Esq., Department of Agriculture, for the agency.
Nora K. Adkins, Esq., and James A. Spangenberg, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
An agency may not correct an obvious mistake if the bidder’s intended bid amount is neither ascertainable from the face of the bid nor supported by clear and convincing evidence.
DECISION
Bighorn Lumber Company, Inc. protests the award of a timber sales contract to Trapper Peak Timber Company by the U.S. Department of Agriculture, Forest Service, under the Two Elks timber sale in the MedicineBow-Routt National Forest, Colorado.
On
|
14. Bid Information |
Rates Per Unit of Measure |
|||||||||
|
Species (a) |
Product (b) |
Unit of Measure (c) |
Estimated Quantity (d) |
Base Rate (e) |
Minimum Acceptable
Bid Rate (f) |
Weighted Average Bid (g) |
Additional Deposits
for Slash Disposal (h) |
Base Indices (i) |
||
|
Lodgepole Pine and Other, Live and Dead |
Sawtimber |
CCF |
23,505.00 |
$9.87 |
$11.82 |
*////////// |
$1.25 |
130.32 |
||
|
True Fir, Live |
Sawtimber |
CCF |
96.00 |
$9.87 |
$19.92 |
*////////// |
$1.25 |
116.60 |
||
|
Minimum
Acceptable Weighted Average Rate, 14(j) $ 11.85 |
||||||||||
|
Bidder’s Weighted Average Minimum Bid
Rate, 14(g) |
$ |
|
||||||||
|
* Weighted Average Bidding: |
||||||||||
AR, exh. 3, Bid Form at 1. Because this is a sale, rather than a procurement, award was to be made based on the highest WAM bid rate.
On
After bid opening, the agency bid official found that
Trapper’s bid evidenced an obvious mistake in that the bidder apparently
inserted a “total sale value bid,” rather than the WAM bid rate, in section
14(g) of the bid form.[4] The official noted that the mistaken bid, when
divided by 23,601 ccf, would equate to a WAM bid rate of $22.13.[5] AR, exh. 4, Bid Official Memorandum (
In response, Trapper indicated that it had made two
mistakes: (1) entering the total value
of its bid, instead of a WAM bid rate as required in the bid instructions, and (2) only
bidding for the 23,505 ccf of Lodgepole Pine and Other, instead of the 23,601 ccf
of combined sawtimber included in the sale.
AR, exh. 5, Contracting Officer’s Request for Correction, at 1. Trapper requested that its bid be corrected
to reflect a WAM bid rate of $22.13 for the total 23,601 ccf of sawtimber.
Based on the foregoing, the regional Deputy Forest Ranger, the Forest Service official responsible for reviewing claimed mistakes in bid, determined:
It is my decision that since this bid is the apparent high bid, the bidder has requested permission to correct the mistake, and the Contracting Officer determined that clear and convincing evidence establishes both the existence of the mistake and the bid actually intended, you are permitted to allow the bidder to correct the mistake.
AR, exh. 5, Deputy Forest Ranger Determination (
Bighorn challenges the agency decision to correct Trapper’s bid. The agency responds that Trapper’s bid may be corrected to reflect the $22.13 bid rate because the contracting officer found clear and convincing evidence to support that an error had been made in Trapper’s bid, the manner in which it was made and Trapper’s intended bid price. In any event, the agency argues that there is no prejudice to Bighorn because Trapper’s bid is high with or without the adjustment.
An agency may allow a bidder to correct a mistake in its
bid after bid opening when the bidder presents clear and convincing evidence
that a mistake occurred, the manner in which it occurred and the intended bid
price. A & J Constr. Co., Inc.,
B‑213495,
First, we agree with the agency that there is clear and
convincing evidence that a mistake in Trapper’s bid occurred. Trapper’s bid of $522,281.10, resulting in a total
bid value of $12,326,356,241.10, was obviously an unreasonable amount.
The record shows that the agency assumed that Trapper had made a clerical error in not entering the requested WAM bid rate but instead entering the total value, that is, the intended WAM bid rate multiplied by the total estimated sawtimber stumpage covered by the prospectus, and that Trapper’s intended WAM bid rate could be ascertained by dividing Trapper’s bid as submitted by 23,601 ccf, that is, $22.13.
A clerical error that is apparent on the face of a bid may
be corrected by the contracting officer prior to award, if the contracting officer
is able to ascertain the intended bid without the benefit of advice from the
bidder. See SCA Servs. Of
Georgia, Inc., B-209151,
However here, contrary to the agency’s assumption, the $22.13
WAM bid rate was not logically ascertainable from the face of Trapper’s bid--$522,281.10
divided by 23,601 ccf equals 22.129617, not $22.13. If this mistake were simply that of inserting
the extended value on the bid form instead of the requested WAM bid rate, no
such discrepancy would be expected. In
fact, Trapper advised the agency that its intended WAM bid rate was $22.22 for
Lodgepole Pine and Other, and that Trapper intended this bid rate is confirmed
by the fact that if $22.22 were multiplied by the 23,505 ccf quantity of
Lodgepole Pine and Other, the product would equal Trapper’s actual bid of
$522.281.10. Thus, this mistake was not
a correctable clerical error apparent from the face of the bid. See Sundance Constr., Inc.,
B-182485,
Nevertheless, as indicated above, the mistake can be corrected if the bidder presents clear and convincing evidence that a mistake occurred, the manner in which it occurred and the intended bid price. A & J Constr. Co., Inc., supra. There is no evidence that $22.13 was Trapper’s intended WAM bid rate. Indeed, Trapper’s request to the agency to correct its WAM bid rate to $22.13 was not supported by worksheets or any other form of bid calculation documents. In fact, the record shows that it was not Trapper who calculated this amount, but the agency’s bid official. See AR at 3.
While the agency asserts that Trapper’s bid rate would be
higher than Bighorn’s in any case, there is no evidence in the record
supporting this assertion. In fact,
Trapper, by its own admission, did not account in the $22.22 WAM bid rate for
the 96 ccf of True Fir timber, and there is no evidence in the record
whether this failure was intentional or the result of a mistaken or erroneous
interpretation of the bid instructions, much less any indication as to how this
would have affected Trapper’s WAM bid rate.
This leaves open the possibility that Trapper may, in the exercise of its
business judgment, have found it uneconomical to harvest True Fir under the
terms of the prospectus or that its bid rate would have been more significantly
affected if it had been accounted for, such that its bid could closely approach
or be displaced by Bighorn’s bid. See
Protester’s Comments at 5 n.5. Where a
bidder fails to include a price for a contract requirement, and there is no
clear and convincing evidence of the intended bid if this price had been
included, the bidder may not be permitted to recalculate its bid to arrive at a
bid not intended before bid opening. See
Astro Quality Servs., Inc., B‑280676,
Accordingly, the agency’s decision to allow Trapper to correct its bid was not reasonable. Instead, the agency should have permitted Trapper to withdraw its bid. See id. at 4-5. We recommend that award be made to Bighorn if otherwise appropriate.[7]
The protest is sustained.
Gary L. Kepplinger
General Counsel
[1]
The WAM is the bid rate for the stumpage of various species of timber covered
by the sale. According to the
prospectus, “[t]he Forest Service shall establish bid rates by species in the
contract by multiplying each species’ minimum acceptable bid rate by the bid
increase percentage [and] [t]he bid increase percentage is the bidder’s
weighted average bid rate divided by the minimum acceptable weighted average
rate. The total amount for stumpage is the
volume of each biddable species multiplied by its bid rate.” Agency Report (AR), exh. 1, Timber
[2] A ccf is one hundred cubic feet.
[3] 23,505 ccf Lodgepole Pine and Other + 96 ccf True Fir.
[4] Trapper’s bid as entered on the bid form was an obvious error because its $522,281.10 WAM bid rate would result in a total bid of $12,326,356,241.10. AR at 5.
[5]
Actually, the bid amount, $522,281.10, divided by 23,601 ccf is $22.129617. Using $22.13 results in a total bid value of
$522,290.13 ($22.13 multiplied by 23,601 ccf).
[6] Trapper’s bid of $522,281.10 when divided by 23,505 ccf is exactly $22.22.
[7]
We considered this protest under 4 C.F.R. sect. 21.13(a) (2007) because the Forest
Service has agreed to have protests of timber sales decided by our Office. When we consider protests of sales, the
provisions of 4 C.F.R. sect. 21.8(d), pertaining to recommendations for the payment
of protest costs, do not apply. 4 C.F.R.
sect. 21.13(b). See Squires Timber Co., B-298859,








