B-298494.2; B-298494.3; B-298494.4; B-298494.5; B-298494.6; B-298494.7; B-298494.8; B-298494.9; B-298494.10; B-298494.11; B-298494.12; B-298494.13; B-298494.14, Computer Sciences Corporation; Unisys Corporation; Northrop Grumman Information Technology, Inc.; IBM Business Consulting Services--Federal, May 10, 2007
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective Order. This redacted version has been approved for public release.
Matter of: Computer Sciences Corporation; Unisys Corporation; Northrop Grumman Information Technology, Inc.; IBM Business
Consulting Services--Federal
File: B-298494.2; B-298494.3; B-298494.4; B-298494.5; B-298494.6; B-298494.7; B-298494.8; B-298494.9; B-298494.10; B-298494.11; B-298494.12; B-298494.13; B-298494.14
Carl J. Peckinpaugh, Esq., and Helaine G. Elderkin, Esq., for
Computer Sciences Corporation; David S. Cohen, Esq., John J. O’Brien, Esq.,
Laurel A. Hockey, Esq., Bryan T. Bunting, Esq., Catherine K. Kroll, Esq., and
Tenley A. Carp, Esq., Cohen Mohr LLP, and E. Charles Rowan, Jr., Esq., and
Charlotte D. Young, Esq., for Unisys Corporation; William W. Thompson, Jr.,
Esq., Michael A. Branca, Esq., Lori Ann Lange, Esq., and Diane Foose, Esq.,
Peckar, Abramson, Bastianelli & Kelley, LLP, and Linda T. Maramba, Esq.,
for Northrop Grumman Information Technology, Inc.; John S. Pachter, Esq., Jonathan D. Shaffer,
Esq., Mary Pat Gregory, Esq., and Matthew L. Haws, Esq., Smith Pachter
McWhorter PLC, and Todd Hutchen, Esq., for IBM Business Consulting
Services--Federal, the protesters.
Thomas P. Barletta, Esq., Daniel C. Sauls, Esq., Paul R. Hurst,
Esq., Michael J. Navarre, Esq., and Ana Holmes Voss, Esq., Steptoe &
Johnson LLP, and James S. Kennell, Esq., for Science Applications International
Corporation; Lori A. Conlon, Esq., for Lockheed Martin Information Services,
Inc.; Kevin P. Mullen, Esq., David E. Fletcher, Esq., and Tara M. Lee, Esq.,
Cooley Godward Kronish LLP, for Electronic Data Systems Corp.; Thomas O. Mason,
Esq., Frances E. Purcell, Jr., Esq., Robert E. Korroch, Esq., and Megan E.
Burns, Esq., Williams Mullen, for Booz Allen Hamilton Inc.; and Gregory S.
Jacobs, Esq., Reed Smith LLP, for CACI, Inc.--Federal, the intervenors.
Robert R. Goff, Esq., Defense Information Systems Agency, for the
agency. Guy R. Pietrovito, Esq., and James A. Spangenberg, Esq., Office of
the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
In a negotiated procurement, an agency’s exchanges with offerors with respect to their proposed subcontracting plans were discussions, where the solicitation provided for the comparative assessment of the merits of the plans as part of the agency’s technical evaluation, a number of the offerors’ subcontracting plans were assessed as being unacceptable, and the offerors made material revisions in their plans in response to the exchanges with the agency that made them acceptable.
DECISION
Computer Sciences Corporation (CSC); Unisys Corporation; Northrop Grumman Information
Technology, Inc. (NGIT); and IBM Business Consulting Services--Federal protest
the failure of the Defense Information Systems Agency (DISA), Department of
Defense (DoD), to award “Encore II” contracts to the protesters under request
for proposals (RFP) No. HC1013-05-R-2003 for information technology services
supporting DoD and other federal agencies.
The protesters challenge the agency’s technical, past performance and
price evaluation, the conduct of exchanges with the offerors,1 and source
selection decision.
The RFP provides for the award of multiple, indefinite-delivery,
indefinite-quantity contracts for a 60-month base period with five 1-year
options, under which the agency will award time-and-materials or labor-hour,
fixed-price or cost-reimbursable task or delivery orders for
technical solutions for [DoD] in support of its migration to an integrated and interoperable Global Information Grid (GIG), as well as other Federal agencies having similar Information Technology (IT) migration and integration needs. The Encore II contracts represent an ongoing expansion of [DISA’s] Defense Enterprise Information Services (DEIS) I and DEIS II contracts, and Encore follow-on contracts.
RFP amend. 12, sect. B.1.a. The
Encore II contractors will provide services, hardware, software, and associated
products to satisfy information technology activities at all operating levels in support of the functional requirements,
including command and control, intelligence and mission support, and to all
elements of the GIG.2
The RFP stated that the agency would “keep the number of
[contract] awards to a reasonable amount,” which the solicitation defined to be
six awards for this acquisition.
The RFP provided for award on a “best value” basis, and stated the
following evaluation factors, subfactors, and elements:
|
Past Performance Factor |
||
|
Element 1: Cost Control |
||
|
Element 2: Schedule |
||
|
Element 3: |
||
|
Element 4: Quality |
||
|
Element 5: Socioeconomic Goals |
||
|
Element 6: Subcontracting Management |
||
|
Element 7: Business Relations |
||
|
Element 8: Key Personnel |
||
|
Technical/Management
Approach Factor |
||
|
Technical Solutions
Subfactor |
||
|
Element 1: Overall Task Area Approach |
||
|
Element 2: Task 1 Interoperable Communications |
||
|
Element 3: Task 2 Interoperable Information Sharing |
||
|
Element 4: Task 3 Operations Support |
||
|
Element 5: Task 4 Automated Processing System |
||
|
Management Solutions
Subfactor |
||
|
Element 1: Management and Organizational Structure |
||
|
Element 2: Quality Awards, Recognition and |
||
|
Element 3: Key Personnel |
||
|
Element 4: Electronic Commerce/Electronic Business |
||
|
Element 5: Ability to Recruit, Train, Maintain and |
||
|
Element 6: Small Business Subcontracting Plan |
||
|
Element 7: Mentor-Protégé Program |
||
|
Element 8: Invoice Processing |
||
|
Cost/Price Factor |
||
RFP amend. 12, sect. M.5.2. The
past performance factor was stated to be comparatively equal in weight to the
technical/management approach factor, and each of these factors was more
important than the cost/price factor.
The subfactors and elements were stated to be comparatively equal within
each factor. Offerors were informed that
proposals “must meet or exceed all evaluation criteria to be eligible for
award.”
Detailed proposal preparation instructions were provided. With respect to the past performance factor,
offerors were requested to identify “no more than four (4) recent (completed
within the last 3 years: 2003-2005, or
work that is on-going) contracts or task orders on which [they had] performed
as either the prime contractor or subcontractor.” For each of the four prior contract or task
order efforts, the offeror was to complete a past performance data sheet and to
provide a past performance questionnaire to one of the customer points of
contact identified in the data sheet.
With regard to the small business subcontracting plan element of
the management solutions subfactor, offerors were informed that the agency
would evaluate the feasibility and comprehensiveness of the offeror’s planned
approach to meeting the subcontracting goals established by the RFP.
With respect to the cost/price factor, offerors were required to
submit fixed, loaded labor rates for the life of the contract. Offerors were informed that the “proposed
rates for the labor categories and other direct costs (ODCs) in section B would
be evaluated with respect to their completeness and reasonableness” and that
the “reasonableness of the overall price [would] be determined on the basis of
adequate price competition and by comparison with the Independent Government
Cost Estimate (IGCE).”
may evaluate cost/price realism with respect to the ability of the Offeror to meet requirements in terms of skills required, complexity of disciplines and job difficulty, if the [agency] deems such analysis necessary. The Offeror’s Cost/Price proposal may be compared to the Technical proposals to determine the Offeror’s (1) understanding of work to be performed and (2) capability and capacity to provide the required services and accomplish the required tasks . . . . Unrealistically low prices may indicate an inability to understand requirements and a high-risk approach to contract performance and the ability to attract and maintain a high-quality workforce. Accordingly, the [agency] may consider the findings of such analysis regarding an Offeror’s ability to perform and the risk of its approach. Since proposed labor rates are fixed, the price evaluation shall not be adjusted as a result of any such cost/price realism analysis.
In addition, the RFP informed offerors that the agency intended to
make award on the basis of initial proposals and without conducting
discussions.
[t]here will be no communications with Offerors after the time and date specified in the Contracting Officer’s request for final proposal revisions, except for communications regarding an Offeror’s Subcontracting Plan. Subcontracting Plan validation is not to be construed as negotiations or a reopening of negotiation[s].
DISA received 16 proposals, including those of the protesters
(CSC, Unisys, NGIT, and IBM) and the 6 awardees (Booz Allen Hamilton, Inc.
(BAH), CACI, Inc.-Federal, Electronic Data Systems Corporation (EDS), Lockheed
Martin Information Services, Inc. (LMI), Science Applications International
Corporation (SAIC), and Systems Research and Application Corporation
(SRA)). The proposals were evaluated by
the agency’s respective evaluation teams:
the past performance team (PPT) evaluated offerors’ past performance
information; the technical/management approach team (TMAT) evaluated offerors’
technical/management approach; the cost/price team evaluated offerors’ price
proposals, and the contracting officer evaluated the offerors’ general contract
information proposal. Contracting
Officer’s Statement at 25. With
respect to the past performance and technical/management approach evaluations,
the evaluators independently prepared individual, written assessments and
ratings of the proposals, which were assembled into a document presenting the
evaluators’ individual views. See,
e.g., AR, Tabs 659-74, PPT and TMAT Decision Point Documents for
Offerors. Following their individual
evaluations, the PPT and TMAT met to discuss and agree upon a consensus
evaluation and ratings for each of the proposals. Contracting Officer’s Statement at 44. Consensus evaluation reports were then
prepared for each offeror and submitted to the source selection advisory
council (SSAC). See AR, Tabs
832-47, Past Performance Consensus Reports, Tabs 848-63,
Technical/Management Approach Consensus Reports.
The offerors’ price proposals were evaluated by the agency’s
cost/price team, which reviewed the offers for completeness and reasonableness,
by comparing the offerors’ prices to each other, developing the DLCC for each
proposal, and comparing each offeror’s calculated DLCC to the IGCE. Contracting Officer’s Statement at 53.[1]
The protesters’ and awardees’ proposals received the following
overall ratings:5
|
Offeror |
Past Performance |
Tech./Mgmt.
Approach |
DLCC (in
billions) |
|
SRA |
Blue/Low Risk |
Blue/Low Risk |
$7.51 |
|
CACI |
Blue/Low Risk |
Blue/Low Risk |
$7.98 |
|
BAH |
Blue/Low Risk |
Blue/Low Risk |
$7.99 |
|
EDS |
Blue/Low Risk |
Blue/Low Risk |
$8.01 |
|
LMI |
Blue/Low Risk |
Blue/Low Risk |
$8.37 |
|
SAIC |
Blue/Low Risk |
Green/Low Risk |
$8.55 |
|
NGIT |
Blue/Low Risk |
Green/Low Risk |
$10.09 |
|
IBM |
Blue/Low Risk |
Green/Low Risk |
$10.11 |
|
CSC |
Blue/Low Risk |
Green/Moderate
Risk |
$8.69 |
|
Unisys |
Blue/Low Risk |
Yellow/Moderate
Risk |
$9.31 |
AR, Tab 831, SSAC Report, at 37.
The evaluation results were presented to the agency’s SSAC, which
accepted the evaluators’ ratings.
The small business subcontracting plans of a majority of the
offerors were found to be “unacceptable” by the agency for various reasons,
including the proposal of less than the required small business subcontracting
goals and/or the failure to identify the dollar values associated with proposed
goal percentages. See Agency
Legal Memorandum at 9; AR, Tabs 675-704, Small and Disadvantaged Business
Utilization Specialist (SADBUS) and
In response to the agency’s questions and requests, it received
additional information from the highest rated offerors with respect to their
past performance, quality awards, small business subcontracting plans, and
general contract information proposals.
With respect to the small business subcontracting plans, the agency
found that the awardees’ plans had become acceptable. Agency Legal Memorandum at 9. With respect to the quality awards, the
offerors’ responses resulted in increased ratings for six offerors, including
three awardees, under the quality awards element of the management solutions
subfactor, which resulted in a higher management solutions subfactor rating for
two offerors (CSC and CACI), although these offerors’ higher subfactor rating
did not result in a higher technical/management factor rating. Contracting Officer’s Statement at 66.
The SSAC provided a detailed briefing to the SSA that described
the consensus evaluation and price evaluation conclusions of the evaluators and
the SSAC. This briefing identified each
offeror’s evaluated strengths and weaknesses under each factor, subfactor, and
element. The briefing also informed the
SSA of the agency’s exchanges with the offerors. See AR, Tab 788, SSA Decision
Briefing, at 190. The SSAC recommended
that the SSA select the proposals of BAH, CACI, EDS, LMI, SAIC, and SRA for
award on the basis that “[t]hese offerors [were] capable of providing . . .
superior IT products and services to meet future task order requirements in a
timely and cost-effective manner.”
The SSA conducted a price/technical tradeoff analysis, in which
she concluded that the offers of BAH, CACI, EDS, LMI, SAIC, and SRA reflected
the best value to the agency.
Specifically, the SSA noted that BAH, CACI, EDS, LMI, and SRA had submitted
the five highest technically-rated offers with the lowest DLCCs. With respect to SAIC, the SSA found:
SAIC was the next lowest evaluated DLCC price, and they received the same overall Technical/Management Approach rating of Green as CSC, IBM, [another offeror], and NGIT. Within the Technical/Management Approach [factor], CSC and [the other offeror] were rated Medium Risk, while NGIT and IBM were rated Low Risk. However, CSC, IBM, [the other offeror] and NGIT had evaluated DLCCs that were more than the evaluated DLCC for SAIC. In addition, IBM and NGIT have evaluated DLCCs that were higher than the IGCE. I conclude that the risk rating for CSC and [the other offeror] along with the cost differential between CSC, IBM, [the other offeror], NGIT and SAIC is significant enough to preclude award to CSC, IBM, [the other offeror] and NGIT.
AR, Tab 894x, Source Selection Decision, at 29-30. Awards were made to BAH, CACI, EDS, LMI,
SAIC, and SRA, and, after debriefings, these protests followed.
CSC, Unisys, NGIT, and IBM protest that the exchanges between DISA
and the offerors with the 10 highest rated proposals constituted discussions
and that these discussions were not meaningful, as required by the FAR.7 DISA and the intervenors contend that the
agency’s exchanges were clarifications.
FAR sect. 15.306 describes a range of exchanges that may take place
between an agency and an offeror during negotiated procurements.
Clarifications are “limited exchanges” between the agency and offerors
that may allow offerors to clarify certain aspects of proposals or to resolve
minor or clerical mistakes. FAR
sect. 15.306(a)(2).
Discussions, on the other hand, occur when an agency indicates to an
offeror significant weaknesses, deficiencies, and other aspects of its proposal
that could be altered or explained to materially enhance the proposal’s
potential for award or to obtain information from the offeror that is necessary
to determine the proposal’s acceptability.
See FAR sect. 15.306(d)(3); Nu-Way, Inc., B-296435.5, B‑296435.10,
Here, the record shows that the majority of the small business
subcontracting plans submitted by the offerors were found to be unacceptable by
the agency, and that, as a result of the agency’s exchanges on this subject
with the 10 highest rated offerors (including the awardees), those firms
revised their proposals, such that the proposals became acceptable.
DISA does not disagree that a majority of the offerors, with whom
exchanges were conducted regarding their subcontracting plans, revised their
plans to become acceptable. The agency
contends, however, citing a number of decisions of our Office, that exchanges
regarding the acceptability of a required small business subcontracting
plan--even the submission of a revised plan--relate to an offeror’s
responsibility and therefore are not discussions. See General Dynamics-Ordnance &
Tactical Sys., Inc., B-295987, B-295987.2,
It is true that in each of the cases cited by DISA we found that
exchanges concerning an offeror’s small business subcontracting plan were not
discussions because those plans were only evaluated as part of the agency’s
responsibility determination. See,
e.g., General Dynamics-Ordnance & Tactical Sys., Inc., supra,
at 10 (“A request for, or providing of, information that relates to
offeror responsibility, rather than proposal evaluation, does not constitute
discussions and thus does not trigger the requirement to hold discussions with
other competitive range offerors. ”) (footnote omitted). However, in each of these cases, unlike the
RFP at issue here, the solicitation did not include a technical evaluation
factor under which the comparative merits of offerors’ small business
subcontracting plans would be considered to determine which proposal
represented the best value to the government and thus entitled to award. Thus, under the circumstances of each of
these cases, the assessment of offerors’ small business subcontracting plans
could only be done as part of the agency’s responsibility determination.
In contrast, the RFP here provided for a comparative assessment of
the offerors’ small business subcontracting plans as part of the agency’s
technical evaluation to determine which proposal represented the best value to
the government.8 See
RFP amend. 12, sect. M.5.2.a.(2)(ii)(6) (“For large businesses, the Government
will evaluate the feasibility and comprehensiveness of the Offeror’s planned
approach to meeting the established subcontracting goals of . . . .”). In accordance with this evaluation scheme,
the agency’s TMAT performed a comparative evaluation of the offerors’ proposed
small business subcontracting plans that were provided as part of the offerors’
technical/management approach proposals, assigning strengths and weaknesses for
each proposal. See, e.g.,
AR, Tab 881, SSAC Evaluation Report, app. 4, Technical/Management Approach
Factor Evaluation, at 103 (SRA’s proposal was evaluated as exceeding the small
business subcontracting plan requirements, with a number of strengths,
including that the firm had committed to exceeding the small business goal); see
also id. at 189, 212 ([Deleted]’s and [Deleted]’s proposals were
evaluated as exceeding the small business subcontracting plan requirements,
with a number of strengths and no weaknesses).
In contrast, [Deleted]’s proposed small business subcontracting plan was
evaluated as failing to satisfy the solicitation requirements and a number of
weaknesses were assigned, including that the proposal did not adequately
address how the firm would meet small business goals.
More akin to the circumstances of this procurement than the cases
cited by DISA are our decisions in Fritz Cos., Inc., B-246736 et al.,
May 13, 1992, 92-1 CPD para. 443, aff’d, Daniel F. Young--Recon., B‑246736.4,
July 30, 1992, 92-2 CPD para. 62. The
solicitation at issue in the Fritz case required the submission of small
business and small disadvantaged business subcontracting plans and informed
offerors that these plans could become the determining factor in the award
decision if offers were found to be essentially equal. In Fritz, we found that, despite the
agency’s characterization that award had been made on the basis of initial
proposals, the agency had actually conducted discussions with the awardee,
where the agency selected the awardee’s proposal on the basis of its superior
subcontracting plan but after the awardee had been provided with an opportunity
to revise its plan, which we found to be a material revision to the awardee’s
proposal.
DISA also contends that these exchanges do not constitute
discussions because they relate only to the small business subcontracting plan
that was submitted as part of the general contract information proposal and not
to the plan that was submitted as part of the technical/management approach
proposal. DISA and the intervenors
argue that the solicitation informed offerors that the small business subcontracting
plans submitted with the firms’ general contract information proposals would
not be considered in the agency’s technical evaluation, and that the RFP
informed offerors that the agency would not conduct discussions with regard to
the small business subcontracting plans.
See RFP amend. 12, sect. L.3.c.
DISA also states in this regard that offerors’ revisions to their small
business subcontracting plans were not provided to the agency’s TMAT and
therefore did not affect the firms’ technical/management approach factor
evaluations. See Agency Legal
Memorandum at 15.
We do not agree that the solicitation provided that offerors’
small business subcontracting plans (and more specifically their promises to
satisfy or exceed the small business subcontracting goals) would not be
evaluated by the agency in its consideration of the firms’ proposals under the
technical/management approach factor.
Rather, as noted above, the RFP specifically stated that the firms’
promises to satisfy the solicitation’s mandatory subcontracting goals would be
considered under this factor.9 See RFP amend. 12, sect.
M.5.2.a.(2)(ii)(6). In fact, these
promises were specifically considered by the TMAT, the SSAC, and the SSA in
their consideration of the relative merits of the firms’ technical/management
approach proposals. See, e.g.,
AR, Tab 894x, Source Selection Decision, at 15, where the SSA recognized that
SAIC had committed to exceeding the small business subcontracting goals.
We also find no merit to the agency’s and intervenors’ argument
that the RFP’s statement that the agency did not intend to conduct discussions
with offerors with respect to their small business subcontracting plans
resolves whether the actual exchanges provided were discussions or
clarifications. As noted above, we look
at the actions of the parties to determine whether discussions have been held,
and thus neither an agency’s characterization of its exchanges nor its stated
intention not to conduct discussions is determinative of whether the exchanges
are in fact discussions or clarifications. See Gulf Copper Ship Repair, Inc.,
supra; Raytheon Co., B-261959.3,
Finally, we do not find dispositive that the agency chose to
not share the offerors’ responses concerning their small business
subcontracting plans with the TMAT. The
fact remains that a majority of the 10 highest rated offerors had submitted
subcontracting plans that were determined to be unacceptable and that these
firms were provided with an opportunity to revise these plans (including
proposing new subcontracting goals or providing additional information to
establish that the firms would satisfy or exceed these goals). Following these actions, the firms’ plans
were determined to be acceptable, and this information was shared with both the
SSAC and the SSA, who presumably considered the TMAT’s, the SADBUS’s/PCR’s and
contracting officer’s assessment of the firms’ subcontracting plans, and the
results of the firms’ discussion responses.10
In conclusion, we find that the agency’s exchanges with the
offerors, which allowed a majority of the highest rated offerors to revise
their proposals in a material way, were not clarifications but were
discussions. As noted above, when an
agency conducts discussions with one offeror, it must conduct discussions with
all other offerors whose proposals are in the competitive range, and those
discussions must be meaningful; that is, the discussions must identify
deficiencies and significant weaknesses in each offeror’s proposal. See Spherix, Inc., supra,
at 13-14. Here, the record establishes
that the protesters were prejudiced, because, although the agency conducted
discussions with CSC, NGIT, and IBM concerning their subcontracting plans, the
discussions with the protesters were not meaningful, given that there were a
number of significant weaknesses identified in each of the protesters’
proposals, and considered by the SSA in her selection decision, which the
protesters were never given an opportunity to address, but which could have been
altered or explained to materially enhance the proposals’ potential for
award. See, e.g., AR, Tab
894x, Source Selection Decision, at 19-21, 24, and 27-28 (identifying numerous
weaknesses in the protesters’ proposals).
Because we sustain the protests on the basis of the agency’s
failure to afford the protesters meaningful discussions, we do not address the
protesters’ challenges to the agency’s evaluation and source selection
decision, given our recommendation below that the agency open the competition to
conduct discussions with offerors whose proposals are found to be in the
competitive range. However, as the
agency proceeds with its corrective action, it may want to be mindful of the
other issues raised by protesters, including the significant concerns raised by
the protesters with respect to the agency’s past performance evaluation, which
found no discriminators in the evaluation of the protesters’ and awardees’
proposals, and with respect to price realism, given that the record does not
evidence that a price realism analysis was performed.
The protests are sustained.
We recommend that the agency establish a competitive range and
conduct meaningful discussions with offerors whose proposals are found to be
within the competitive range, obtain and evaluate revised proposals, and make a
new source selection decision. We also
recommend that the agency reimburse the protesters for their reasonable costs
of filing and pursuing the protests. Bid
Protest Regulations, 4 C.F.R. sect. 21.8(d)(1) (2007). The protesters’ certified claims for costs,
detailing time expended and costs incurred, must be submitted directly to the
agency within 60 days of receiving this decision. 4 C.F.R. sect. 21.8(f)(1).
Gary L. Kepplinger
General Counsel
1 The Federal Acquisition Regulation (FAR) provides for a
range of “exchanges” with offerors after the receipt of proposals, including
clarifications, communications, and discussions. FAR sect. 15.306.
2 Offerors were informed that the following could not be
obtained under the Encore II contracts:
point to point circuits; transmission (voice/data/video) and network management in support of the [Defense Information System Network]; and standalone hardware purchase and/or maintenance and standalone software purchase and/or maintenance.
RFP amend. 12, sect. C.1.3.
3 The total
DLCC for each proposal is calculated by first computing an annual price by
totaling the annual labor costs with the estimated ODCs with mark-up and
profit. A discount factor (identified in
the RFP) for each year is applied to the total annual price to arrive at a
discounted price for each contract year; the discounted annual prices are then
added to compute the proposal’s evaluated total DLCC. RFP amend. 12, sect. M.5.2.b.(4).
[1] The proposed price of one offeror (not a party to this protest) was found to be unreasonable.
5 The
awardees and protesters are identified in descending order from the highest
non-price evaluation rating (SRA) to the lowest non-price factor rating
(Unisys). The proposals of 11 offerors
received higher non-price factor ratings than Unisys.
6 [Deleted]’s
plan actually states that the firm’s proposed subcontracting to small business
concerns goal would be 24 percent of the total subcontracted work value, and
not of the total contract task order dollars.
See [Deleted] Subcontracting Plan, attach. A, Goals for
Individual Subcontracting Plan, at 1.
7 Unisys,
which did not have any exchanges with the agency, also complains that it was
treated unequally. Unisys Protest at
24-25.
8 Traditional
responsibility factors may be comparatively evaluated in a negotiated
procurement as part of agency’s technical evaluation and not as a matter of the
offeror’s responsibility. See Medical
Info. Servs., B-287824,
9 Accepting
the agency’s argument distinguishing between the subcontracting plans submitted
in the offerors’ technical/management proposals and general contracting
information proposals would mean that offerors could submit different and
inconsistent plans. For example, an
offeror could promise to exceed the subcontracting goals in its
technical/management proposal and receive evaluation credit for doing so, yet
propose goals that were merely acceptable in its plan submitted in its general
contracting information proposals. (The
plan submitted with the offerors’ general contracting information proposals were
incorporated by the agency into the contracts awarded under the
solicitation.) Or as presented here, an
offeror’s small business subcontracting plan could be determined to be
acceptable in the agency’s technical evaluation, but the firm’s plan in the general
contract information proposal could be found unacceptable because the plan
failed to satisfy the RFP’s mandatory goals.
Such an inconsistency in an offeror’s subcontracting plan could not
reasonably be ignored by the agency in its evaluation of proposals. See TRW, Inc., B-254045.2, Jan.
10, 1994, 94-1 CPD para. 18 at 11 (agency improperly failed to resolve through
negotiations its evaluated negative concerns with the awardee’s technical
proposal, caused by its apparent inconsistency with the cost proposal).
10 Although
the record does not document exactly what was provided to the SSA with respect
to the exchanges with the offerors, the record does evidence that the SSA was
informed by the SSAC of the areas (including the small business subcontracting
plans) that were the subject of the exchanges.
See AR, Tab 788, SSA Decision Briefing, at 190.

