B-297452, SERAPH Inc., January 12, 2006
Decision
Dale
Yeager for the protester.
Daniel
J. Donohue, Esq., and Elizabeth M. Gill, Esq., Wickwire Gavin, PC, for CACI
Premiere Technology, Inc., an intervenor.
Audrey
Roh, Esq., Department of Homeland Security, United States Coast Guard, for the
agency.
Peter D. Verchinski, Esq., and John M. Melody, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Alleged misevaluation of two proposed personnel under “relevant past experience/proposed personnel” factor as lacking relevant experience did not competitively prejudice protester, and thus does not provide basis for sustaining protest, where contemporaneous evaluation record shows that protester’s proposal was not downgraded based on evaluation of the two personnel, and that proposal ultimately was eliminated from consideration for award based on evaluated deficiencies under different factor, which protester does not question.
DECISION
SERAPH Inc. protests the award of a contract to CACI Premiere Technology, Inc. under request for proposals (RFP) No. HSCG23095-R-DOT097, issued by the Department of Homeland Security, United States Coast Guard, for support services assisting the Coast Guard in developing and implementing capabilities to detect, identify, interdict and detain terrorist threats in the maritime domain. SERAPH primarily argues that the Coast Guard improperly evaluated the experience of two of its proposed key personnel.
On
The Coast Guard received 15 proposals. In evaluating SERAPH’s proposal under the first
factor, relevant past experience/proposed personnel, the technical evaluation
team (TET) assigned SERAPH an overall rating of green, which represented low
risk.[1] The report explained that SERAPH’s proposed
staff appears to meet or exceed the experience needed to conduct the training,
but also stated that SERAPH’s chemical, biological, radiological, nuclear and
explosives (CBRNE) specialist did not appear to have much experience in the
CBRNE field, Agency Report (AR), Technical Evaluation Report, Tab 8, at 7, and
that the boat specialist SERAPH proposed “has more of a boarding/close quarters
combat background than that of a boat specialist.”
The agency made an initial determination that 11 of the proposals--including SERAPH’s--had no chance of being selected for award based on their technical ratings and prices. The proposals that remained in consideration, unlike SERAPH’s, received green or higher ratings under each of the technical evaluation factors. The Coast Guard then made a final price/technical tradeoff among the remaining four proposals, selecting CACI’s proposal on the basis that it was the highest rated of all proposals received, and the lowest priced among the remaining proposals.
SERAPH principally argues that the agency’s determination that two of its proposed personnel had limited relevant experience was unreasonable. [2]
Our Office will not sustain a protest unless the protester
demonstrates a reasonable possibility that it was prejudiced by the agency’s
actions, that is, unless the protester demonstrates that, but for the agency’s
actions, it would have had a substantial chance of receiving the award. McDonald‑Bradley, B‑270126,
We find that SERAPH was not prejudiced by the alleged
improper evaluation of its two key personnel since, even if we agreed with
SERAPH, it would not be in line for award.
More specifically, the contemporaneous evaluation record shows that SERAPH’s
proposal was not selected for award due to the agency’s evaluation conclusion that
the proposal represented a moderate risk under the understanding of work evaluation
factor, and not because the agency determined that SERAPH’s proposed personnel
had inadequate experience. In this
regard, the agency specifically stated in the competitive award memorandum that
SERAPH’s proposed staff has the experience and training necessary to perform
the contract. AR, Tab 9, at 15. While the memorandum includes the comments (stated
above) concerning the two proposed personnel, the agency nevertheless concluded
that “the noted risks are not significant to warrant an overall elevated risk
rating.”
The record shows that it was SERAPH’s inadequately written
plan to perform the work that led to the elimination of its proposal from the
competition. The agency found that the
discussion of the required work in SERAPH’s proposal was not sufficiently
defined to allow the agency to determine whether SERAPH fully understood the requirement. The competitive award memorandum specifically
concluded that this deficiency--represented by a moderate risk rating under the
understanding of the work factor--resulted in SERAPH’s proposal no longer being
considered for award. AR, Tab 9, at
25. The protester has not challenged the
agency’s finding of this deficiency. Given
that SERAPH’s proposal was eliminated from the competition on this basis, and
not due to the agency’s view of the adequacy of SERAPH’s proposed personnel’s
experience, it is clear that the alleged misevaluation of the firm’s proposed
personnel had no effect on the award decision.
Accordingly, SERAPH was not prejudiced by the alleged improper
evaluation. See generally Northport
Handling, Inc., B-274615,
The protest is denied.
Anthony H. Gamboa
General Counsel
[1] Possible ratings under the technical factors were blue, green, yellow, and red, in descending order of technical ability. Separate risk ratings of low, moderate, or high also were assigned under each technical factor.
[2] SERAPH also argues that CACI had an impermissible organizational conflict of interest (OCI) arising from its alleged participation in the preparation of the solicitation. However, the agency responds that CACI had no role in the preparation of the solicitation, and SERAPH has provided no evidence establishing that the agency’s representations are incorrect; unsupported statements do not provide a basis for sustaining a protest. SERAPH further asserts that the award was improper because the award amount exceeded the stated ceiling price of $7,180,800. SERAPH misunderstands the solicitation. In fact, the $7,180,800 amount was the ceiling price only for the T&M CLINs; there was no ceiling price for the fixed-price CLINs.

