B-296855.2, Odyssey International, Inc., November 16, 2005
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective Order. This redacted version has been approved for public release.
Decision
Matter of: Odyssey International, Inc.
Patrick
S. Hendrickson, Esq., for the protester.
Timothy
A. Sullivan, Esq., and Michael H. Payne, Esq., Payne Hackenbracht and Sullivan,
for Allied Contractors and Engineers, Inc., an intervenor.
Carrie
E. Kamler, Esq., Department of Labor, for the agency.
Charles W. Morrow, Esq., and James A. Spangenberg, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Agency improperly failed to allow correction of claimed mistake in bid, where the bidder established its mistake and its intended bid (which was still low) by clear and convincing evidence and the agency denied the requested correction because of other suspected mistakes which were unrelated to the one claimed and which the agency did not bring to the bidder’s attention, as required by Federal Acquisition Regulation sections 14.407-1, 14.407-3(g)(1)(iv), and where the evidence in the record, including hearing testimony and worksheets, does not evidence that the bidder made additional mistakes (as suspected by the agency) or that the worksheets were not in good order.
DECISION
Odyssey International, Inc. protests the Department of Labor’s (DOL) decision to deny its request for correction of a mistake in its low bid under invitation for bids (IFB) No. 051RB20036, for construction services, and the consequent rejection of its bid.
The IFB, issued on
After the agency requested the three lowest bidders to
verify their bid prices, Odyssey, on May 11, requested correction of an alleged
mistake in its bid attributed to “a dramatic posting error” in its bid
tabulation sheet. Agency Report, Tab 25,
Letter from Odyssey to DOL,
On May 19, Odyssey furnished additional evidence related to the mistake, including a compact disc (CD) containing the electronic version of the previously printed spreadsheets. Odyssey requested that it be allowed to correct its base-bid price to $7,104,600 to account for the mistake. This figure included not only the $1,000,000 shortfall on the bid tabulation sheet in recording the subcontractor’s quote, but also, consistent with the methodology employed on the original bid tabulation spreadsheet, a [DELETED] markup for profit and overhead on the increased price, an additional 1-percent markup for bond premium, and a $54 bid reduction to round off the bid.[2] Agency Report, Tab 25, Odyssey’s Request for Correction, May 11, 2005; Tab 29, Odyssey’s Supplement to Request for Correction, May 19, 2005. This would make Odyssey’s corrected bid, including the two alternates, total $7,317,216,[3] which is only $2,584 less than Allied’s $7,319,800 bid.
Upon learning that Odyssey had requested correction of its
mistake in bid, on May 12, Allied protested to the agency the propriety of
permitting Odyssey to correct its bid.
On June 21, after reviewing Odyssey’s documentation, DOL accepted
Odyssey’s corrected bid, finding that there was clear and convincing evidence
of the mistake and the intended bid.
Thus, on June 28, DOL denied Allied’s protest. Allied then filed a protest at our Office on
July 8, challenging DOL’s decision.
Allied based this protest on its review of the printed bid tabulation
spreadsheets provided by Odyssey in support of its mistake claim that Allied
had obtained from DOL. We dismissed this
protest as academic on August 3 after DOL reversed its prior position and
advised that it would now not accept Odyssey’s corrected bid because of “a
number of other serious errors, unrelated to [the] initial mistake in bid
claimed by Odyssey,” which were found in Odyssey’s spreadsheets and which
prevented the agency from determining Odyssey’s intended bid price. See Agency Corrective Action Letter,
As indicated above, as a result of Allied’s protest to our
Office, DOL found, upon further review, that Odyssey’s spreadsheets did not
establish clear and convincing evidence of the mistake and intended bid. This change in position was based on factors
not related to the particular mistake claimed by Odyssey. Specifically, DOL now found an apparent
computational error in the “General Conditions” section of the spreadsheets
because the total for this section when added was $316,293, instead of
$422,043, which was the total that appeared on both the original and the
corrected spreadsheets. DOL next points
to section 5500, “Metal Fabrications,” in the original and the corrected
spreadsheets where, instead of prices, the original worksheet said “in” and the
corrected worksheet said “in 05120.” DOL
found that these changed notations reflected a potential error because it
indicated that the metal fabrications, including the stairs, were a part of
Odyssey’s structural steel subcontractor’s quote, but that subcontractor’s
quote did not include stairs, an item for which DOL estimated the cost to be
between $60,000 and $70,000. With
respect to sections 8310, “Access Doors and Panels”; 10400, “Signage”; 10520,
“Fire Protection Specialties”; and 10810, “Toilet Accessories” on the spreadsheets,
DOL found that Odyssey had a supplier’s quote for the materials, but had not
included the cost of labor in the spreadsheets, which the government estimated
to be $17,205. Finally, DOL found that
in section 2821, “Chain Link Fences and Gates,” the original spreadsheet
contained the notation “in 03300,” but the corrected spreadsheet changed the
notation to “in 02980.” Since DOL had
estimated the item at $18,000, it found that whether Odyssey had included a
price for this item could not be determined from the changes to this notation. DOL found that the foregoing problems
indicated that Odyssey’s spreadsheets were not in good order and did not
reasonably support by clear and convincing evidence Odyssey’s claimed intended
bid price. See Agency Report,
Tab 7, Letter from DOL to Odyssey,
Odyssey maintains that DOL improperly reversed its decision to permit correction of the mistake, based on Allied’s and DOL’s misunderstanding of Odyssey’s spreadsheets.[4] Odyssey argues that DOL mistakenly concluded that the subtotal in its General Conditions section was not properly calculated because it accepted Allied’s reading of the printed spreadsheets, which did not include two rows that had been hidden to protect the confidentiality of the information, but were accessible to the agency on the CD by unhiding these rows, which would have confirmed the accuracy of the subtotal for this section reflected in the printed spreadsheets.[5] Odyssey further contends that the various revised notations on the spreadsheets did not evidence any mistakes in its bid and did not affect its bid amount. Odyssey complains that the agency improperly denied correction for reasons not related to the mistake that was claimed without providing Odyssey with an opportunity to respond to these issues.
A bidder who seeks upward correction of its bid price
prior to award must submit clear and convincing evidence that a mistake was
made, the manner in which the mistake occurred, and the intended price. Federal Acquisition Regulation (FAR)
sect. 14.407-3(a). Workpapers, including
records of computer generated software spreadsheets/workpapers (hardcopy printouts,
computer disks, tapes or other software media), may constitute clear and
convincing evidence if they are in good order, and indicate the intended bid
price, and there is no contravening evidence.
Holmes Mech., Inc., B-281417,
Here, the agency acknowledges, and we agree, that Odyssey’s documentation establishes by clear and convincing evidence that Odyssey made a $1,000,000 error in transcribing its structural steel subcontractor’s quote in section 5120 of its spreadsheets. There is also no dispute that when this error is corrected and the markups and rounding are taken into account that Odyssey’s corrected bid would be $7,317,216.[6] The only dispute concerns the sufficiency of the spreadsheets as evidence of the intended bid because of additional alleged mistakes, other than those claimed by Odyssey, that DOL suspected were made in the other areas of the spreadsheets, which in DOL’s view meant that Odyssey’s spreadsheets were not in good order so as to establish by clear and convincing evidence its intended bid price.
In our view, DOL did not act reasonably in determining
that Odyssey’s spreadsheets were not in good order and did not provide clear
and convincing evidence of Odyssey’s intended bid. DOL’s reversal of its initial decision
permitting Odyssey to upwardly correct the bid was based upon what DOL regarded
as possible additional mistakes in the spreadsheets beyond the one Odyssey
claimed. Under FAR sect. 14.407‑1,
in cases of apparent mistakes and in cases where the contracting officer has
reason to believe that a mistake may have been made, the contracting officer is
required to request from the bidder a verification of the bid, calling
attention to the suspected mistakes.
Since DOL suspected other mistakes in Odyssey’s bid than the one Odyssey
was requesting to correct, consistent with FAR sect. 14.407-1, it should have
requested further verification of Odyssey’s bid price, and called Odyssey’s
attention to the suspected mistakes in its spreadsheets. In this regard, FAR sect. 14.407‑3(g)(1)(iv)
provides that to ensure that the bidder will be put on notice of mistakes
suspected by the contracting officer, the bidder should be advised as
appropriate “of any other information, proper for disclosure, that leads the
contracting officer to believe that there is a mistake in bid.” See Enco Dredging, B‑284107,
Based on our review of the record, including the spreadsheets, the CD, and the hearing testimony from the individual responsible for preparing Odyssey’s bid, we find that none of the items referenced by DOL (or all these items in total) as indicating a possible mistake beyond that claimed by Odyssey provides a valid basis for denying Odyssey’s correction request.
Specifically, the record confirms that Odyssey’s
spreadsheets on the CD contained hidden rows that included prices of [DELETED]
for a contract administrator and [DELETED] for a safety officer that, when added
to the other rows in the General Conditions section, equal the $422,043
subtotal in the spreadsheets. Although
Odyssey printed the spreadsheets that it provided to DOL in support of the
mistake correction claim without these rows being visible, it furnished DOL the
CD that contained the complete spreadsheet, which was completely accessible to
the agency by manipulating certain commands in the spreadsheet program.[7]
While DOL does not dispute, and we have confirmed, that the correct total of the General Conditions section can be discerned from the spreadsheet on the CD once the rows are unhidden, it contends that the protester’s spreadsheets still should not be accepted as reliable proof of its intended bid because the spreadsheets were printed on May 11 (after bid opening) and the spreadsheet on the CD reflects that it was created on May 19.
However, the fact that bid worksheets were generated by a
computer does not preclude them from constituting valid evidence to support a
request for bid correction, even where a worksheet on a computer was not
printed until after bid opening. See
Holmes Mech., Inc., supra, at 2 n.1, 4. The key consideration is whether or not the
submissions are clear and convincing evidence of the mistake and intended bid;
the manipulation of the mistake in bid rules may occur just as easily when a
bidder has prepared its worksheets without the use of a computer.
Instead, the spreadsheet preparer testified that the spreadsheets,
including the complete spreadsheet with unhidden columns, were printed on the
day after bid opening, and that these spreadsheets were what Odyssey utilized
prior to bid opening to calculate the bid, and that the printed date of May 11
appearing on the spreadsheets is controlled by the computer’s software
programs, and not the user. He further
testified that although a printed copy of the complete spreadsheet was not
furnished to the agency with its request for correction on May 11 because he did
not believe this hidden information was necessary to support the claimed error,
he printed a complete copy for his files on this date. See VT at
Given the preparer’s unrebutted and credible testimony
that the spreadsheet, as represented on the CD that had been provided to the
agency in support of its mistake claim, was what Odyssey utilized prior to
opening to calculate its bid on his computer, we find the spreadsheets and CD
are reliable and constitute clear and convincing evidence of Odyssey’s intended
bid.[8] See Cooper Constr., Inc., B‑285880,
The other alleged mistakes in the spreadsheets that the agency now references also were not brought to Odyssey’s attention as required. In each of these cases, Odyssey has provided credible and unrebutted explanations as to why they did not evidence mistakes. Moreover, none of these alleged mistakes involved apparent errors in the computation of the bid as discerned from the spreadsheets.
Specifically, the notation changes Odyssey made to the
corrected spreadsheet did not involve changes in bid price. Indeed, the preparer testified that the typed
inscriptions that appear in the various notes were his personal notes denoting
where unpriced work items were covered in the bid and did not have any impact
on the scope of work to be provided under the contract or the price to be
charged the government. The preparer
testified that the notation “in” was made to denote that a particular line item
was included in the contract in terms of cost and scope. He testified that he continued to complete
the notes after bid opening because time constraints prior to bid opening did
not permit him to fully complete the notes.
With respect to the change from “in” to “in section 5120,” the preparer
indicated that this note was completed merely to remind himself and the project
manager to further negotiate metal fabrication costs with the structural steel
contractor. With respect to section
3300, the preparer testified that the area where the change was made was simply
to recognize that prior to submitting the bid a change had occurred in terms of
where these costs were being covered. See
VT at
Moreover, the concern that Odyssey may not have included
certain labor costs because its costs did not match the government estimate is
not the type of mistake for which correction would be permitted under the FAR
mistake-in-bid procedures.[9] The FAR permits correction of a mistake only
where it can be demonstrated that the bidder intended a bid other than the one
submitted--that is, where the mistake is attributable to something other than
the bidder’s exercise of its business judgment.
Reynosa Constr., Inc., B-278364,
In sum, close scrutiny of the evidence in the record establishes by clear and convincing evidence both that Odyssey made a mistake as well as its intended bid, which will remain low after correction of the mistake. Consequently, we find that DOL should not have denied Odyssey’s request for correction.
We recommend that DOL permit Odyssey to correct its mistake in bid, and award the contract to that firm, if otherwise appropriate. We also recommend that the protester be reimbursed the reasonable costs of filing and pursuing the protest, including attorney’s fees. 4 C.F.R. sect. 21.8(d)(1) (2005). The protester should submit its certified claim for such costs, detailing the time expended and the costs incurred, directly to the contracting agency within 60 days after receipt of this decision.
The protest is sustained.
Anthony H. Gamboa
General Counsel
[1]
The spreadsheets were prepared on a Microsoft Excel spreadsheet program. Because it is a feature of this program, the
dates appearing on the spreadsheets are the dates they were printed for
submission to the agency. See
Hearing Video Transcript (VT) at
[2]
The preparer of the spreadsheets testified that the original bid price was
rounded downward by $54 from $6,034,054--the base bid as indicated on Odyssey’s
bid calculation spreadsheet--to $6,034,000 to make submitting the bid easier
for the bid handler. See VT at
[3] $7,104,600 + $212,616 = $7,317,216.
[4]
Odyssey argues that DOL should not have released the spreadsheets to Allied
because the information was proprietary/confidential information, and that we
should find that the agency’s improper release of the information precludes the
agency from using the information to reverse its decision allowing correction
of its bid. Since we sustain the protest
and recommend award based on Odyssey’s corrected price, we need not resolve
whether these spreadsheets should have been provided to Allied. However, we do note that the protester did
not mark the submitted spreadsheets as confidential or proprietary as should
generally be done where a firm believes that information should not be
disclosed by the agency. See Litton
Applied Tech., B-227090, 227156,
[5] The Microsoft Excel software permits columns and rows on spreadsheets to be hidden and “unhidden.”
[6]
The computer-generated spreadsheets here contained the same markups that can be
easily used to calculate the effect of the mistake and determine the intended
bid but for the mistake. Where such
spreadsheets are in good order they can constitute clear and convincing
evidence of the intended bid. Roy
Anderson Corp., B-292555, B-292555.2,
[7]
The preparer of the spreadsheet indicated that he hid the safety officer and
contract administration rows to protect the confidentiality of the information,
given that the General Conditions section was not the basis for the mistake
that it was requesting to correct and that the missing rows were included on
the CD. See VT at
[8] Although Allied questions the electronic version of the spreadsheet on the submitted CD because the [DELETED] for the Safety Officer figure is in a blank row above the row for the Safety Officer, we are not troubled by this because the complete sheet was printed in the proper form on May 11 when Odyssey initially requested to correct its bid.
[9]
With respect to the agency’s concern that certain labor costs were not included
for sections 8310, 10400, 10520, and 10810, the bid preparer testified that
these labor costs were in fact included in section 8110, where $14,000 in labor
costs were included, and that Odyssey’s bidding strategy often requires
including labor cost in other sections, where, as was the case here,
installation prices for all material items from subcontractors are not
generally available. See VT at








