B-296483, Rand & Jones Enterprises Company, Inc., August 4, 2005
Decision
Matter of: Rand & Jones Enterprises Company, Inc.
Robert
J. Symon, Esq., Spriggs & Hollingsworth, for the protester.
Kenneth
B. MacKenzie, Esq., and Phillipa L. Anderson, Esq., Department of
Veterans Affairs, and John W. Klein and Kenneth Dodds, Small Business
Administration, for the agencies.
Guy R. Pietrovito, Esq., and James A. Spangenberg, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Agency lacked a reasonable basis to cancel a request for proposals (RFP) after disclosure of the offerors’ proposed prices where the RFP provided only for a price competition and did not contain technical evaluation factors, the agency intends to issue an invitation for bids for this same requirement, and there is no basis to find the government or the integrity of the procurement system would be prejudiced if the RFP were not cancelled.
DECISION
Rand & Jones
Enterprises Company, Inc. protests the cancellation of request for proposals
(RFP) No. 10N3-215-04, issued by the Department of Veterans Affairs (VA) for construction
services at the agency’s
The RFP, issued
The RFP incorporated the standard “Instructions to
Offerors--Competitive Acquisition” clause of Federal Acquisition Regulation
(FAR) sect. 52.215-1 that informed offerors that the agency would award a contract
to the responsible offeror whose proposal represented the best value to the
government considering the factors and subfactors identified in the
solicitation. No technical or non-price
related evaluation factors were identified in the solicitation.
The RFP also contained the standard “Notification of
Competition Limited to Eligible 8(a) Concerns” clause of FAR sect. 52.219-18,
which informed offerors that the solicitation was set aside for small business
concerns certified by the Small Business Administration (SBA) for participation
in SBA’s section 8(a) program.[1] VA did not, however, offer the procurement to
the SBA for award under the section 8(a) program as was required by SBA’s
regulations, and therefore the competition was not in fact set aside for
section 8(a) concerns.[2] SBA Report at 2.
On September 2, the contracting officer was notified
by VA’s Acquisition Assistance Division that the RFP did not provide any
technical evaluation factors.
Thereafter, the RFP was amended to require the submission of a bid
bond. The agency did not, however, amend
the solicitation to provide any technical evaluation factors.
On September 14, VA received proposals from four
firms, including Rand & Jones and Arrow Construction/BKC, Inc. VA publicly opened the proposals and
disclosed the firms’ proposed prices.[3] Arrow was the apparent low offeror for the
base CLIN. However, Arrow notified the
agency that it had made a mistake in its offered price, and requested either an
upward price adjustment or the withdrawal of its offer.
The contracting officer forwarded Arrow’s request to VA’s Acquisition Program
Management Division, which informed the contracting officer that she could
conduct discussions with Arrow and other offerors. This VA office also again informed the
contracting officer that the solicitation did not include any technical
evaluation factors. VA then discovered
that a number of the solicitation’s construction drawings required
revisions. In addition, the proposals
expired. On
VA received revised proposals from the four firms, and
again publicly opened the proposals and disclosed the firms’ proposed
prices. Rand & Jones was found to
have proposed the lowest price for the base CLIN, for which there was
apparently available funding. Arrow,
which submitted the second lowest price for the base CLIN, protested to VA that
Rand & Jones had graduated from SBA’s section 8(a) program and was
therefore not eligible to receive award under the RFP.[4] VA forwarded Arrow’s challenge to SBA. SBA took no action in response to the
challenge. VA subsequently “withdrew”
the challenge to Rand & Jones section 8(a) eligibility.
Instead, the contracting officer cancelled the RFP
because it failed to contain any technical evaluation factors and informed the
offerors that the agency would issue an invitation for bids (IFB) for this
requirement.[5] See, e.g., Agency Report, Tab
15,
VA Letter to Arrow. This protest by Rand
& Jones of the cancellation of, and the failure to make award under, the
RFP followed.
As a general rule, in a
negotiated procurement the contracting agency need only demonstrate a
reasonable basis to cancel a solicitation after receipt of proposals,
as opposed to the “compelling reason” required to cancel an IFB where the bids
have been opened. See FAR sect.
14.404-1(a)(1); CFM Equip. Co.--Recon., B-251344.2,
See Noelke GmbH, B-278324.2,
Here, the record contains no evidence, or even
argument, that the government or the integrity of the procurement system would be
prejudiced if the RFP were not cancelled and award were made thereunder. VA’s only asserted basis for cancellation is
that the RFP did not contain evaluation factors.[6] However, where, as here, a negotiated
procurement does not provide technical evaluation factors, award is to be made
to the responsible offeror with the lowest-priced, technically acceptable
offer. See Omatech Serv. Ltd.,
B-254998, B-254998.2,
We sustain the protest.
We recommend that VA award a contract to
if Rand & Jones is found to be responsible and if there is sufficient
funding.
We also recommend that Rand & Jones be reimbursed its cost of filing and
pursuing the protest, including reasonable attorneys’ fees. 4 C.F.R. sect. 21.8(2)(1) (2005).
In accordance with 4 C.F.R. sect. 21.8(f)(1), the protester’s certified claim for
such costs, detailing the time expended and costs incurred, must be submitted
directly to the agency within 60 days after receipt of this decision.
Anthony H. Gamboa
General Counsel
[1] The procurement was also identified on the agency’s electronic business opportunities system as being set aside for a competitive section 8(a) award.
[2] SBA’s regulations provide in pertinent part that “[a]ny competition conducted without first obtaining SBA’s formal acceptance of the procurement for the 8(a) [business development] program will not considered an 8(a) competitive requirement.” 13 C.F.R. sect. 124.504(b)(1) (2005).
[3] The disclosure of offerors’ proposed prices in a negotiated procurement prior to award, as was done here by VA, is prohibited. See FAR sections 3.104-3(a), 3.104-4.
[4]
As noted above, the procurement was not in fact set aside for section 8(a)
concerns. In any event, SBA advises that
Rand & Jones was an eligible section 8(a) participant on the date that
initial offers were submitted, and would therefore have been eligible for an
award under the section 8(a) program, despite the firm’s later graduation from
the program. SBA Report at 3; see
15 U.S.C. sect. 637(a)(1)(C)(ii) (2000); 13 C.F.R. sect. 124.507(d).
[5] In response to our inquiry, VA informed us that it intends to set aside the IFB for service-disabled veteran-owned small businesses. Under FAR sect. 19.1405, an agency is permitted to set aside acquisitions exceeding the micro-purchase threshold for service-disabled veteran-owned small businesses where offers are expected from two or more service-disabled veteran-owned small businesses and award is expected to be made at a fair market price. The agency does not assert, and the record does not indicate, that this proposed service-disabled veteran-owned small business set‑aside was the reason the RFP was cancelled.
[6] The RFP also did not request technical proposals.








