This is the accessible text file for GAO report number GAO-10-636 
entitled 'Global Positioning System: Challenges in Sustaining and 
Upgrading Capabilities Persist' which was released on September 20, 
2010. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to the Subcommittee on National Security and Foreign Affairs, 
Committee on Oversight and Government Reform, House of Representatives: 

United States Government Accountability Office: 
GAO: 

September 2010: 

Global Positioning System: 

Challenges in Sustaining and Upgrading Capabilities Persist: 

GAO-10-636: 

GAO Highlights: 

Highlights of GAO-10-636, a report to the Subcommittee on National 
Security and Foreign Affairs, Committee on Oversight and Government 
Reform, House of Representatives. 

Why GAO Did This Study: 

The Global Positioning System (GPS) provides positioning, navigation, 
and timing (PNT) data to users worldwide. The U.S. Air Force, which is 
responsible for GPS acquisition, is in the process of modernizing the 
system. Last year GAO reported that it was uncertain whether the Air 
Force could acquire new satellites in time to maintain GPS service 
without interruption. GAO was asked to assess (1) the status of Air 
Force efforts to develop and deliver new GPS satellites, the 
availability of the GPS constellation, and the potential impacts on 
users if the constellation availability diminishes below its committed 
level of performance; (2) efforts to acquire the GPS ground control 
and user equipment necessary to leverage GPS satellite capabilities; 
(3) the GPS interagency requirements process; and (4) coordination of 
GPS efforts with the international PNT community. To do this, GAO 
analyzed program documentation and Air Force data on the GPS 
constellation, and interviewed officials from DOD and other agencies. 

What GAO Found: 

The Air Force continues to face challenges to launching its IIF and 
IIIA satellites as scheduled. The first IIF satellite was launched in 
May 2010—a delay of 6 additional months for an overall delay of almost 
3-½ years—and the program faces risks that could affect subsequent IIF 
satellites and launches. GPS IIIA appears to be on schedule and the 
Air Force continues to implement an approach intended to overcome the 
problems experienced with the IIF program. However, the IIIA schedule 
remains ambitious and could be affected by risks such as the program’s 
dependence on a ground system that will not be completed until after 
the first IIIA launch. The GPS constellation availability has 
improved, but in the longer term, a delay in the launch of the GPS 
IIIA satellites could still reduce the size of the constellation to 
fewer than 24 operational satellites—the number that the U.S. 
government commits to-—which might not meet the needs of some GPS 
users. 

Multiyear delays in the development of GPS ground control systems are 
extensive. In addition, although the Air Force has taken steps to 
enable quicker procurement of military GPS user equipment, there are 
significant challenges to its implementation. This has had a 
significant impact on DOD as all three GPS segments-—space, ground 
control, and user equipment-—must be in place to take advantage of new 
capabilities, such as improved resistance to jamming and greater 
accuracy. DOD has taken some steps to better coordinate all GPS 
segments. These steps involve laying out criteria and establishing 
visibility over a spectrum of procurement efforts. But they do not go 
as far as GAO recommended last year in terms of establishing a single 
authority responsible for ensuring that all GPS segments are 
synchronized to the maximum extent practicable. Such an authority is 
warranted given the extent of delays, problems with synchronizing all 
GPS segments, and importance of new capabilities to military 
operations. As a result, GAO reiterates the need to implement its 
prior recommendation. 

The GPS interagency requirements process, which is co-chaired by 
officials from DOD and DOT, remains relatively untested and civil 
agencies continue to find the process confusing. This year GAO found 
that a lack of comprehensive guidance on the GPS interagency 
requirements process is a key source of this confusion and has 
contributed to other problems, such as disagreement about and 
inconsistent implementation of the process. In addition, GAO found 
that the interagency requirements process relies on individual 
agencies to identify their own requirements rather than identifying 
PNT needs across agencies. 

The Department of State continues to be engaged internationally in 
pursuit of civil signal interoperability and military signal 
compatibility, and has not identified any new concerns in these 
efforts since GAO’s 2009 report. Challenges remain for the United 
States in ensuring that GPS is compatible with other new, potentially 
competing global space-based PNT systems. 

What GAO Recommends: 

GAO recommends that the Department of Defense (DOD) and the Department 
of Transportation (DOT) develop comprehensive guidance for the GPS 
interagency requirements process. DOD did not concur with the 
recommendation, citing actions under way. DOT generally agreed to 
consider it. GAO believes the recommendation remains valid. 

View [hyperlink, http://www.gao.gov/products/GAO-10-636] or key 
components. For more information, contact Cristina Chaplain at (202) 
512-4841 or chaplainc@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

The Air Force Continues to Face Challenges to Launching Its Satellites 
as Scheduled, Which Could Affect the Availability of the Baseline GPS 
Constellation: 

Exploitation of New Satellite Capabilities Delayed Further Because of 
Ground Control and User Equipment Delays and Acquisition Challenges: 

The GPS Interagency Requirements Process Is Relatively Untested and 
Lacks Detailed Guidance: 

Coordination of GPS Activities with the International Community 
Continues, and Some Challenges Have Been Addressed: 

Conclusions: 

Recommendation for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: GAO Assessment of GPS IIIA Prime Contractor Schedule 
Management Processes: 

Appendix III: Comments from the Department of Defense: 

Appendix IV: GAO Contact and Staff Acknowledgments: 

Tables: 

Table 1: GPS Satellite and Ground Control Segment Modernization: 

Table 2: Delays in Delivery of New GPS Ground Segment Capabilities: 

Table 3: Status of Completion of Interagency Requirements Process Key 
Steps for Requirements Initiated after the Development of the GPS 
Interagency Requirements Process: 

Table 4: Schedules and Their Descriptions: 

Table 5: Extent to Which Each Project Schedule Met Best Practices: 

Table 6: Antenna Element Schedule Analysis Details: 

Table 7: Bus Schedule Analysis Details: 

Table 8: General Dynamics Schedule Analysis Details: 

Table 9: Navigation Unit Panel Schedule Analysis Details: 

Table 10: Launch Operations Schedule Analysis Details: 

Figures: 

Figure 1: GPS Operational System: 

Figure 2: National Space-Based PNT Organization Structure: 

Figure 3: Comparison of Predicted Size of GPS Constellation (at the 95 
Percent Confidence Level) Based on Reliability Data and Launch 
Schedules as of March 2009 and December 2009: 

Figure 4: Predicted Size of GPS Constellation (at the 95 Percent 
Confidence Level) Based on a 2-Year GPS III Launch Delay and 
Reliability Data and Launch Schedules as of March 2009 and December 
2009: 

Figure 5: Predicted Size of GPS Constellation (at the 95 Percent 
Confidence Level) Based on a 1-Year GPS III Launch Delay and Current 
Management and Power Management Reliability Data and Launch Schedules 
as of December 2009: 

Figure 6: Predicted Size of GPS Constellation (at the 95 Percent 
Confidence Level) Based on a 2-Year GPS III Launch Delay and Current 
Management and Power Management Reliability Data and Launch Schedules 
as of December 2009: 

Abbreviations: 

CAM: Control Account Manager: 

CWBS: Contractor Work Breakdown Structure: 

DASS: Distress Alerting Satellite System: 

DOD: Department of Defense: 

DOT: Department of Transportation: 

EELV: Evolved Expendable Launch Vehicle: 

EVM: earned value management: 

FAA: Federal Aviation Administration: 

FNET: Finish No Earlier Than: 

FOUO: For Official Use Only: 

GPS: Global Positioning System: 

IFOR: Interagency Forum for Operational Requirements: 

IMP: Integrated Master Plan: 

IRP: Interagency Requirements Plan: 

JCIDS: Joint Capabilities Integration and Development System: 

JROC: Joint Requirements Oversight Council: 

L1C: fourth civil signal: 

L2C: second civil signal: 

L5: third civil signal: 

M-code: Military Code: 

NASA: National Aeronautics and Space Administration: 

NSPD-39: National Security Presidential Directive No. 39: 

OCS: Operational Control Segment: 

OCX: Next Generation Control Segment: 

PNT: positioning, navigation, and timing: 

SAASM: Selective Availability Anti-Spoofing Module: 

SLR: Satellite Laser Ranging: 

SNET: Start No Earlier Than: 

SOW: Statement of Work: 

SVN-49: satellite vehicle number 49: 

WBS: Work Breakdown Structure: 

[End of section] 

United States Government Accountability Office:
Washington, DC 20548: 

September 15, 2010: 

The Honorable John F. Tierney: 
Chairman: 
The Honorable Jeff Flake: 
Ranking Member: 
Subcommittee on National Security and Foreign Affairs: 
Committee on Oversight and Government Reform: 
House of Representatives: 

The Global Positioning System (GPS)--a space-based satellite system 
that provides positioning, navigation, and timing (PNT) data to users 
worldwide--has become essential to U.S. national security and a key 
component in economic growth, transportation safety, homeland 
security, and critical national infrastructure in the United States 
and abroad. The Department of Defense (DOD) develops and operates GPS, 
and an interdepartmental committee--co-chaired by DOD and the 
Department of Transportation (DOT)--manages the U.S. space-based PNT 
infrastructure, which includes GPS. The U.S. Air Force, which is 
responsible for GPS acquisition, is in the process of modernizing GPS 
to enhance its performance, accuracy, and integrity. Effective 
modernization depends on aligned delivery of new capabilities from 
satellites, the ground control segment, and user equipment. 

In April 2009, we reported on a range of issues related to GPS, 
[Footnote 1] including the development of satellites, ground control, 
and user equipment necessary to leverage GPS capabilities and the 
coordination among federal agencies and other organizations to ensure 
that GPS missions can be accomplished. We reported that it was 
uncertain whether the Air Force would be able to acquire new 
satellites in time to maintain current GPS service without 
interruption, and that some military operations and some civilian 
users could be adversely affected. In addition, we reported that 
military users faced a potential delay in utilizing new GPS 
capabilities because of poor synchronization of the development of the 
satellites with development of the ground control and user equipment. 
We also reported that DOD and civil agencies involved in ensuring that 
GPS can serve communities beyond the military took prudent steps to 
manage GPS requirements and coordinate among the many organizations 
involved with GPS, but we identified challenges in ensuring that 
civilian requirements can be met. Finally, we identified challenges in 
ensuring that GPS was compatible with other new, potentially competing 
global space-based PNT systems. 

In our prior report, we recommended that the Secretary of Defense 
appoint a single authority to oversee the development of GPS, 
including DOD space, ground control, and user equipment assets, to 
ensure that the program is well executed and resourced and that 
potential disruptions are minimized. Furthermore, we specified that 
the appointee should have the authority to ensure that all GPS 
segments are synchronized to the maximum extent practicable. DOD 
concurred with this recommendation. In concurring with our 
recommendation, DOD asserted that the Assistant Secretary of Defense 
for Networks and Information Integration has authority and 
responsibility for all aspects of GPS, and that the Air Force is the 
single acquisition agent responsible for synchronizing GPS segments. 
In addition, after our 2009 report, DOD created the Space and 
Intelligence Office within the Office of the Under Secretary of 
Defense for Acquisition, Technology and Logistics to ensure that all 
three segments of GPS stay synchronized in the development and 
acquisition processes. However, that office does not have authority 
over all user equipment. We also recommended that if weaknesses are 
found the Secretaries of Defense and Transportation should address 
civil agency concerns for developing requirements, improve 
collaboration and decision making, and strengthen civil agency 
participation. Both DOD and DOT concurred with this recommendation. 
DOD noted that it would seek ways to improve civil agency 
understanding of the DOD requirements process and would work to 
strengthen civil agency participation. DOT indicated that it would 
work with DOD to review the process and improve civil agency 
participation. 

In light of our previous findings and the importance of GPS, you asked 
that we review the program this year. In response, we assessed (1) the 
status of the Air Force's efforts to develop and deliver new GPS 
satellites, the availability of the GPS constellation, and the 
potential impacts on users if the constellation availability 
diminishes below its committed level of performance; (2) efforts to 
acquire the GPS ground control and user equipment necessary to 
leverage GPS satellite capabilities; (3) the GPS interagency 
requirements process; and (4) coordination of GPS efforts with the 
international PNT community. 

To assess the status of DOD's efforts to develop and deliver new GPS 
satellites, including the recently developed GPS IIF satellites and 
the GPS IIIA satellites that are under development, we interviewed DOD 
officials who manage and oversee the GPS program; reviewed and 
analyzed program plans and documentation related to cost, 
requirements, program direction, acquisition schedules, and launch 
schedules; and reviewed some of the GPS IIIA space vehicle development 
schedules and compared them with relevant best practices. To assess 
the availability of the GPS constellation, we conducted our own 
analysis based on GPS reliability data provided by the Air Force and 
assessed the implications of potential schedule delays. To assess 
potential impacts on users if the constellation availability 
diminishes below its committed level of performance, we obtained 
information from all military services and key civil agencies and 
departments. To assess the progress of efforts to acquire the GPS 
ground control and user equipment, we interviewed officials who manage 
and oversee these acquisitions; reviewed documentation regarding the 
delivery of capabilities and equipment; and assessed the level of 
synchronization among satellites, ground systems, and user equipment. 
To assess the GPS interagency requirements process, we reviewed policy 
and guidance on the GPS interagency requirements process, identified 
the status of civil requirements, analyzed documents, and interviewed 
DOD officials from offices that manage and oversee the GPS program and 
officials from DOT and other civil departments and agencies. To assess 
coordination efforts with the international global PNT community, we 
interviewed officials at the Department of State and at the GPS Wing. 
Our work is based on the most current information available as of 
April 16, 2010. Additional information on our scope and methodology is 
in appendix I. We conducted this performance audit from July 2009 to 
September 2010 in accordance with generally accepted government 
auditing standards. Those standards require that we plan and perform 
the audit to obtain sufficient, appropriate evidence to provide a 
reasonable basis for our findings and conclusions based on our audit 
objectives. We believe that the evidence obtained provides a 
reasonable basis for our findings and conclusions based on our audit 
objectives. 

Background: 

GPS is a global PNT network consisting of space, ground control, and 
user equipment segments that support the broadcasts of military and 
civil GPS signals. Each of these signals includes positioning and 
timing information, which enables users with GPS receivers to 
determine their position, velocity, and time 24 hours a day, in all 
weather, worldwide. 

GPS began operations with a full constellation of satellites in 1995. 
Over time, GPS has become vital to military operations and a 
ubiquitous infrastructure underpinning major sections of the economy, 
including telecommunications, electrical power distribution, banking 
and finance, transportation, environmental and natural resources 
management, agriculture, and emergency services. GPS is used by all 
branches of the military to guide troop movements, integrate logistics 
support, enable components underlying battlespace situational 
awareness, and synchronize communications networks. In addition, U.S. 
and allied munitions are guided to their targets by GPS signals and 
GPS is used to locate military personnel in distress. 

Civil agencies, commercial firms, and individuals use GPS and GPS 
augmentations[Footnote 2] to accurately navigate from one point to 
another. Commercial firms use GPS and GPS augmentations to route their 
vehicles, as do maritime industries and mass transit systems. In 
addition to navigation, civil departments and agencies and commercial 
firms use GPS and GPS augmentations to provide high-accuracy, three- 
dimensional positioning information in real time for use in surveying 
and mapping and other location-based services. The aviation community 
worldwide uses GPS and GPS augmentations to increase the safety and 
efficiency of flight. GPS and GPS augmentations are also used by the 
agricultural community for precision farming, including farm planning, 
field mapping, soil sampling, tractor guidance, and crop scouting; the 
natural resources management community uses GPS for wildfire 
management and firefighting, pesticide and herbicide control, and 
watershed and other natural resources asset management. GPS is 
increasingly important to earth observation, which includes 
operational roles in weather prediction, the measurement of sea level 
change, monitoring of ocean circulation, and mitigation of hazards 
caused by earthquakes and volcanoes. GPS helps companies and 
governments place satellites in precise orbits, and at correct 
altitudes, and helps monitor satellite constellation orbits. The 
precise time that GPS broadcasts is crucial to economic activities 
worldwide, including communication systems, electrical power grids, 
and financial networks. 

GPS System Description: 

GPS operations consist of three segments--the space segment, the 
ground control segment, and the user equipment segment. All segments 
are needed to take full advantage of GPS capabilities. (See figure 1.) 

Figure 1: GPS Operational System: 

[Refer to PDF for image: illustration] 

Space segment: 

Ground control segment: 
Master Control Station; 
Ground antenna; 
Monitor station. 

User segment: 
Handheld; 
Recreation; 
Aviation; 
Maritime; 
Ground navigation; 
Mapping and surveying. 

Sources: GAO; Copyright © Corel Corp. All rights reserved (map); Art 
Explosion. 

[End of figure] 

The GPS space segment is a constellation of satellites that move in 
six orbital planes approximately 12,500 miles above the earth. GPS 
satellites broadcast encrypted military signals and unencrypted civil 
signals. The baseline constellation consists of satellites occupying 
24 orbital slots--4 slots in each of the six orbital planes. However, 
because the U.S. government commits to at least a 95 percent 
probability of maintaining this baseline constellation of 24 
satellites, the typical size of the constellation is somewhat larger. 
Moreover in recent years, because numerous satellites have exceeded 
their design life, the constellation has grown to 31 active satellites 
of various generations. However, DOD predicts that over the next 
several years many of the older satellites in the constellation will 
reach the end of their operational life faster than they will be 
replenished, thus decreasing the size of the constellation from its 
current level, reducing satellite availability, and potentially 
reducing the accuracy of the GPS service. 

The GPS ground control segment comprises the Master Control Station at 
Schriever Air Force Base, Colorado; the Alternate Master Control 
Station at Vandenberg Air Force Base, California; 6 dedicated monitor 
stations; 10 National Geospatial-Intelligence Agency monitoring 
stations; and 4 ground antennas with uplink capabilities. Information 
from the monitoring stations is processed at the Master Control 
Station to determine satellite clock and orbit status. The Master 
Control Station operates the satellites and regularly updates the 
navigation messages on the satellites. Information from the Master 
Control Station is transmitted to the satellites via the ground 
antennas. The U.S. Naval Observatory Master Clock monitors the GPS 
constellation and provides timing data for the individual satellites. 
The U.S. Naval Observatory Master Clock serves as the official source 
of time for DOD and a standard of time for the entire United States. 

The GPS user equipment segment includes military and commercial GPS 
receivers. A receiver determines a user's position by calculating the 
distance from four or more satellites using the navigation message on 
the satellites to triangulate its location. Military GPS receivers are 
designed to utilize the encrypted military GPS signals that are only 
available to authorized users, including military and allied forces 
and some authorized civil agencies. Commercial receivers use the civil 
GPS signal, which is publicly available worldwide. 

GPS Modernization: 

In 2000, DOD began efforts to modernize the space, ground control, and 
user equipment segments of GPS to enhance the system's performance, 
accuracy, and integrity. Table 1 shows the modernization efforts for 
the space and ground control segments. 

Table 1: GPS Satellite and Ground Control Segment Modernization: 

Satellite evolution and capabilities: 

GPS IIA/IIR (first launch 1990/1997): 
* Broadcasts signals for military and civil users. 

GPS IIR-M (first launch 2005): 
Includes IIA and IIR capabilities, plus: 
* Second civil signal; 
* Second military signal; 
* Ability to increase signal power to improve resistance to jamming. 

GPS IIF (first launch 2010): 
Satellite evolution and capabilities: Includes IIR-M capabilities, 
plus: 
* Third civil signal for transportation safety requirements. 

GPS III (first planned launch 2014): 
Includes IIF capabilities, plus: 
* IIIA: Stronger military signal to improve jamming resistance and 
fourth civil signal that is compatible with foreign signals; 
* IIIB: Near real-time command and control via cross links; 
* IIIC: Improved antijam performance for military users. 

Ground control segment and capabilities: 

Legacy Operational Control System (various versions 1979–2007): 
* Centralized computer mainframe; 
* 1970s technology. 

Architectural Evolution Plan (came online in 2007): 
* Distributed architecture; 
* Enables upgrades to the system; 
* Controls GPS IIF satellites. 

Next Generation Control Segment (planned to come online in 2015): 
* Necessary for operation of GPS IIR-M, IIF and III satellites; 
* Service-oriented architecture; 
* Connects to broader networks. 

Source: GAO analysis based on DOD program information and discussions 
with DOD officials. 

[End of table] 

Full use of military and civil GPS signals requires a ground control 
system that can manage these signals. Newer software will upgrade the 
ground control to a service-oriented or netcentric architecture that 
can support "plug and play" features and can more easily connect to 
broader networks. To use the modernized military signal from the 
ground, military users require new user equipment, which will be 
provided by the military GPS user equipment program. 

Broader Coordinating Structure: 

The 2004 U.S. Space-Based Positioning, Navigation and Timing policy 
established a coordinating structure to bring civil and military 
departments and agencies together to form an interagency, multiuse 
approach to program planning, resource allocation, system development, 
and operations. The policy also encourages cooperation with foreign 
governments to promote the use of civil aspects of GPS and its 
augmentation services and standards with foreign governments and 
international organizations. As part of the coordinating structure, an 
executive committee advises and coordinates among U.S. government 
departments and agencies on maintaining and improving U.S. space-based 
PNT infrastructures, including GPS and related systems. The executive 
committee is co-chaired by the deputy secretaries of DOD and DOT, and 
includes members at the equivalent level from the Departments of 
State, Commerce, Homeland Security, the Interior, and Agriculture; the 
Joint Chiefs of Staff; and the National Aeronautics and Space 
Administration (NASA). Figure 2 describes the national space-based PNT 
organization structure. 

Figure 2: National Space-Based PNT Organization Structure: 

[Refer to PDF for image: organizational chart] 

Top level: 
White House. 

Second level, reporting to White House: 
National Executive Committee for Space-Based Positioning, Navigation, 
and Timing: Executive Steering Group: Co-chairs: Defense and 
Transportation; 
* Defense; 
* Transportation; 
* State; 
* Interior; 
* Agriculture; 
* Commerce; 
* Homeland Security; 
* Joint Chiefs of Staff; 
* NASA; 
* Advisory Board: Sponsor: NASA. 

Third level, reporting to National Executive Committee for Space-Based 
Positioning, Navigation, and Timing: 
National Coordination Office: Host: Commerce; 
* GPS International Work Group; Chair: state; 
* Engineering Forum; Co-chairs: Defense and Transportation; 
* Ad hoc working groups. 

Source: GAO presentation of National Executive Committee for Space-
Based Positioning, Navigation, and Timing data. 

[End of figure] 

The departments and agencies have various assigned roles and 
responsibilities. For example, the Secretary of Defense is responsible 
for the overall development, acquisition, operation, security, and 
continued modernization of GPS. The Secretary has delegated 
acquisition responsibility to the Air Force, though other DOD 
components and military services are responsible for oversight, for 
some aspects of user equipment development, and for funding some parts 
of the program. DOT has the lead responsibility for coordinating civil 
requirements from all civil departments and agencies. The Department 
of State leads negotiations with foreign governments and international 
organizations on GPS PNT matters and regarding the planning, 
operations, management, and use of GPS. 

The Air Force Continues to Face Challenges to Launching Its Satellites 
as Scheduled, Which Could Affect the Availability of the Baseline GPS 
Constellation: 

The Air Force faces challenges to launching its IIF and IIIA 
satellites as scheduled. The first IIF satellite launched May 27, 
2010, almost 3-½ years later than previously planned, and the IIF 
program appears to have resolved most outstanding technical issues. In 
addition, the program faces risks that could affect the on-orbit 
performance of some GPS satellites and subsequent IIF launches. The 
GPS IIIA program is progressing and the Air Force continues to 
implement an approach that should prevent the types of problems 
experienced on the IIF program. However, the IIIA schedule remains 
ambitious and could be affected by risks such as the program's 
dependence on a ground system that will not be completed until after 
the first IIIA launch. Meanwhile, the availability of the baseline GPS 
constellation has improved, but a delay in the launch of the GPS IIIA 
satellites could still reduce the size of the constellation to below 
its 24-satellite baseline, where it might not meet the needs of some 
GPS users. 

After Long Development Delays, the First GPS IIF Satellite Has Been 
Launched, but the Program Faces Longer-Term Challenges in Launching 
IIF Satellites as Scheduled: 

Last year, we reported that under the IIF program, the Air Force had 
difficulty successfully building GPS satellites within cost and 
schedule goals, encountered significant technical problems that 
threatened its delivery schedule, and faced challenges with a 
different contractor for the IIF program.[Footnote 3] These problems 
were compounded by an acquisition strategy that relaxed oversight and 
quality inspections as well as multiple contractor mergers and moves 
and the addition of new requirements late in the development cycle. As 
a result, the IIF program had overrun its original cost estimate of 
$729 million by about $870 million and the launch of the first IIF 
satellite had been delayed to November 2009--almost 3 years late. 

Since our last review, launch of the first IIF satellite was postponed 
an additional 6 months--for an overall delay of almost 3-½ years--to 
May 2010. The first IIF satellite launched May 27, 2010, and the 
program appears to have resolved outstanding technical issues. The 
satellite was delivered to Cape Canaveral Air Force Station, Florida, 
in February 2010 to undergo final testing and preparations for launch. 
The GPS Wing[Footnote 4] attributes recent launch delays to launch 
vehicle and pad availability issues, but the late discovery of some 
technical issues also contributed to the launch delay. According to 
the GPS Wing, the technical issues were a result of inadequate 
oversight of the contractor earlier in the acquisition. To prevent an 
even longer launch delay, the program shipped the second IIF satellite 
to Cape Canaveral Air Force Station and conducted extensive system-
level end-to-end tests. This enabled the program to take the time to 
address some technical issues on the first satellite while reducing 
risk using the second satellite--GPS Wing officials reported that it 
saved them approximately 60 days of schedule time. 

On-Orbit Performance of IIF Satellites Remains Uncertain: 

Although the first IIF satellite has launched, it is uncertain how the 
IIF satellites will perform on orbit and it is unclear how well 
positioned the program is to address any on-orbit problems without 
significantly affecting the IIF schedule. Only after the first 
satellite of a new generation, like IIF, has been launched and months 
of on-orbit tests have been conducted can a thorough understanding of 
its performance be obtained. Previously, the GPS Wing had planned to 
mitigate the risk of potential IIF performance issues by launching 
some satellites of the prior generation, the IIR-Ms, after the first 
IIF launch. Space programs in the past have used this practice to 
reduce risk in case there were on-orbit problems with the new 
generation of satellites. However, when the delivery of the IIF 
satellites was continually delayed, the Air Force launched the 
remaining IIR-M satellites to eliminate the Air Force's dependence on 
the launch vehicle that was used for previous generations of GPS 
satellites. 

Two GPS Wing officials expressed concern that the GPS program is now 
in a riskier position than it has been for many years because it does 
not have any IIR-M satellites in inventory and ready to launch. In 
fact, the current IIF production and launch schedules indicate that 
there is little margin to address any potential on-orbit performance 
issues. Within little over a year after the first IIF launch, three 
additional IIF satellites are scheduled to launch and six--half of all 
IIF satellites--are scheduled to have completed production. If 
problems are identified during on-orbit testing of the first 
satellite, the satellites already in production will have to be 
retrofitted to correct the deficiencies, which could result in delays 
in launching some IIF satellites. 

Competition for Launch Resources Could Affect IIF Launch Schedule: 

Adding to these challenges, the need to compete for limited launch 
resources has increased across national security space programs and is 
likely to affect the Air Force's ability to launch GPS IIF as planned. 
Until recently, the Air Force made use of four launch facilities on 
the East Coast and three on the West Coast to launch its national 
security space satellites. However, the Air Force now plans to launch 
most national security satellites, including the GPS IIF and IIIA, 
using one of two Evolved Expendable Launch Vehicle (EELV) rocket 
types--Delta IV or Atlas V. EELV launches are conducted from two 
launch facilities on the East Coast and two on the West Coast. With 
this transition to relying on the EELV, the Air Force has reduced its 
launch facilities from seven to four. The East Coast launch facilities 
are in greatest demand, particularly the Atlas V's facility SLC-41. 
Not only does the Air Force plan to launch several high-priority 
satellites, including four IIF satellites, from that facility over the 
next 2 fiscal years, but NASA also plans to use it for the launch of 
two extremely time-sensitive missions within that same time period. 
However, historically no more than four satellites have been launched 
from the SLC-41 facility in a single year, yet eight launches are 
planned for that facility in fiscal year 2011. Air Force officials 
stated that they are taking steps to improve their capability to 
launch more satellites per year on the EELV than in the past. 

The Air Force has acknowledged that it will be challenged to achieve 
its desired launch plans in the near future and is taking some steps 
to address this challenge. For example, the Air Force designed the GPS 
IIF satellites to be dual integrated--meaning they can fly on either 
the Delta IV or Atlas V launch vehicle--which gives the Air Force more 
flexibility than if it had relied on only one type of launch vehicle. 
The GPS program in particular plans to request funding to study the 
possibility of launching GPS satellites on the West Coast, which has 
the potential of offering a broader array of launch options. However, 
some of the potential solutions to these launch challenges, such as 
launching GPS satellites from the West Coast, are long-term solutions. 
Therefore, despite these efforts, the high demand for limited launch 
resources will likely affect the GPS program's ability to achieve its 
planned launches in the near future. 

The GPS IIIA Program Has Adopted Several Best Practices but Faces 
Challenges to Launching Its Satellites on Schedule: 

Last year, we reported that the Air Force structured the new GPS IIIA 
program to prevent mistakes made on the IIF program but that the IIIA 
schedule was optimistic. To avoid repeating past problems, the program 
was taking measures to maintain stable requirements, use mature 
technologies, and provide more contractor oversight. However, we also 
reported that the Air Force would be challenged to deliver IIIA on 
time because its satellite development schedule was optimistic given 
the program's late start, past trends in space acquisitions, and 
challenges facing the new contractor. For example, the GPS IIIA 
schedule from contract award to first satellite launch is 72 months. 
We found that that time period was 3 years shorter than the schedule 
the Air Force had achieved under its IIF program as well as shorter 
than most other major space programs we have reviewed. Furthermore, we 
questioned the reliability of the GPS IIIA schedule because we found 
that it did not fully meet best practices. 

Since our prior report, we found that the GPS IIIA program appears to 
have furthered its implementation of the "back to basics" approach to 
avoid repeating the mistakes of GPS IIF and that it has passed a key 
design milestone.[Footnote 5] More specifically, the program has 
maintained stable requirements, has used mature technologies, and is 
providing more oversight than under the IIF program. There have not 
been any changes to the program to meet increased or accelerated 
technical specifications, system performance, or requirements. All 
critical technologies were reported to be mature at program start. The 
program held multiple levels of preliminary design reviews to ensure 
that the system was ready to proceed into detailed design. The 
preliminary design reviews were completed in May 2009, and the program 
completed its critical design review in August 2010. Furthermore, GPS 
Wing officials stated that they are requiring that the contractor 
follow military standards and specifications and that the contractor 
and subcontractors use earned value management.[Footnote 6] 

Since our last review, the GPS program has also made improvements to 
its integrated master schedule. The success of any program depends in 
part on having a reliable schedule and we found the GPS IIIA schedule 
to be highly integrated and of high quality. In our recent analysis of 
the IIIA schedule, we found that processes are in place to ensure that 
all activities are captured, are of reasonable duration, and are 
assigned resources. Our analysis also shows that in general the 
program office updates the schedule on a regular basis and logical 
relationships are used to determine important dates. However, our 
analysis also revealed instances of unreasonably high total float. 
Total float represents the amount of time an activity can slip before 
it affects the project finish date and is directly related to the 
logical sequencing of activities. High levels of float may interfere 
with management's ability to properly align resources to ensure that 
critical activities are not delayed. We also found that schedule risk 
analysis is performed periodically on the schedule, but some risks may 
not be captured in the overall risk analysis because of issues at the 
individual project schedule level. Appendix II discusses our 
examination of the prime contractor's schedule management process 
against best practices criteria in more detail. 

Despite these efforts to develop a stable and successful program, the 
GPS IIIA program faces challenges to launching its satellites on 
schedule. First, the 72-month time period from contract award to first 
satellite launch is 3-½ years shorter than the schedule achieved for 
the GPS IIF program. Though the GPS IIIA program has adopted practices 
that should enable it to deliver in a quicker time frame than the GPS 
IIF program, the inherent complexities associated with the design and 
integration phases that have yet to be completed will make it 
difficult to beat the prior schedule by that order of magnitude. More 
specifically, the IIIA program is not simply replicating the IIF 
program in terms of design and production. The program is using a 
satellite bus, which although it has flown on many satellites in the 
past, has not yet been used in medium-earth orbit, an orbit that 
requires different control software and production processes, such as 
a higher level of radiation hardening. The contractor will add a new 
signal, L1C, to the satellite that has not been included on previous 
GPS satellites and will also increase the power of the military signal 
that has been used on previous satellites. These types of changes can 
increase the time it takes to complete the program because some level 
of discovery will need to be completed during design and integration 
and unanticipated technical problems that arise during these phases 
can have reverberating effects. 

Second, the time period from contract award to first satellite launch 
in the IIIA schedule appears to be compressed compared to what the 
program had previously estimated. DOD's fiscal year 2004 funding 
request reported a schedule with 84 months from contract award to 
first satellite launch, but contract award took place 3 years later 
than had been planned while the first IIIA launch was only pushed back 
by 2 years, leaving that time period a year shorter than previously 
planned--a considerable amount of time given that requirements were 
not substantially changed to accommodate the schedule change. 

Third, according to GPS Wing officials, the program is trying to 
improve the quality of the satellites by requiring that the contractor 
follow military standards and specifications. This action is a 
positive step; however, using this more rigorous approach is likely to 
pose challenges to meeting the IIIA schedule. GPS Wing officials 
stated that GPS IIIA is currently the only major space system 
acquisition that is requiring the use of military standards and 
specifications and it is shouldering much of the burden of 
transitioning to these more rigorous standards. Officials report that 
some of the standards and specifications are out of date and 
familiarity with these standards has been lost. Updating the standards 
and specifications along with developing and implementing the 
necessary training and testing to apply them takes time and creates 
cost pressure. 

Lastly, it should be noted that no major satellite program undertaken 
by DOD in the past decade has met its schedule goals. The GPS IIIA 
program itself has done more than many programs in the past decade to 
position itself to meet its dates, but there are still actions that 
need to be taken across DOD to enable space programs to meet their 
schedule goals. As we testified in March 2010, these include 
strengthening the space acquisition workforce, clarifying lines of 
accountability and authority, and lengthening program manager tenures, 
among others.[Footnote 7] 

An additional challenge to launching the IIIA satellites on time is 
the GPS IIIA program's dependence on a ground control system that is 
currently in development. More specifically, the first block[Footnote 
8] of the ground system, called the Next Generation Control Segment, 
or OCX, is scheduled to be operational in fourth quarter fiscal year 
2015, over 1 year after the launch of the first GPS IIIA satellite. 
GPS Wing officials stated that a complete system-level test cannot be 
conducted until OCX is available at which point GPS IIIA can become 
part of the operational constellation and be set "healthy."[Footnote 
9] They also stated that they would prefer not to launch a second GPS 
IIIA satellite until the first IIIA satellite is set healthy, meaning 
until OCX is available, only one GPS IIIA satellite should be 
launched. Yet the planned launch dates for the GPS IIIA satellites 
reflect a rapid series of IIIA launches with five launches taking 
place within 2 years after the first IIIA launch. If OCX is late, as 
some Air Force satellite ground control systems have been, several 
IIIA satellites may not be launched as currently scheduled. In October 
2009, we reported that three of eight ground control systems were 
lagging significantly behind their satellite counterparts. Of the five 
that were not behind, some were still experiencing schedule delays; 
however, their satellite counterparts were also experiencing delays. 
[Footnote 10] 

Current GPS Constellation Availability Improves, but a Delay in GPS 
III Could Affect GPS Constellation Performance: 

To ensure that the GPS constellation can provide PNT information to 
GPS users located anywhere on the earth at almost any time of day, the 
performance standards for both (1) the standard positioning service 
provided to civil and commercial GPS users and (2) the precise 
positioning service provided to military GPS users commit the U.S. 
government to at least a 95 percent probability of maintaining a 
constellation of 24 operational GPS satellites. Last year, we reported 
that the estimated long-term probability of maintaining a 
constellation of at least 24 operational satellites would fall below 
95 percent during fiscal year 2010 and would remain below 95 percent 
until the end of fiscal year 2014, at times falling to about 80 
percent. We also reported that if a 2-year delay were to occur to the 
launch of the first and subsequent GPS III satellites, the U.S. 
government would be at a much greater risk of failing to meet this 
commitment. 

The availability of the constellation has shown considerable 
improvement since last year; the Air Force now predicts that the 
probability of maintaining a constellation of at least 24 operational 
satellites will remain above 95 percent for the foreseeable future-- 
through at least 2025, the date that the final GPS III satellite is 
expected to become operational. However, the long-term impact of a 
delay to GPS III could still reduce the guaranteed size of the 
constellation to fewer than 24 satellites, which might not meet the 
needs of some GPS users. According to the Air Force, the impact of 
such a delay could be mitigated somewhat by shutting off a second 
payload on GPS satellites to save power and thereby extend the lives 
of aging satellites. However, our analysis shows that this approach 
alone would have a limited impact on enabling the U.S. government to 
meet its commitment to a 95 percent probability of maintaining a 24-
satellite constellation--increasing the predicted size of the 
constellation (at the 95 percent confidence level) by 1 satellite. 

Constellation Availability Analysis and Its Limitations: 

The Air Force, with technical support from the Aerospace Corporation, 
calculates satellite lifetime estimates for each on-orbit and 
production (not yet launched) GPS satellite based on detailed 
reliability analysis of the satellite's primary life-limiting 
subsystems. We replicated this analysis for this review using 
parameters provided by the Air Force. The Air Force's analysis is used 
to generate a reliability function for each satellite--that is, the 
probability that the satellite will still be operational as a function 
of its time on orbit. Each satellite's reliability function is modeled 
as the product of two cumulative probability distributions--one that 
accounts for the wear out of life-limiting components and one that 
accounts for random failures. Individual satellite reliability 
functions can be combined with a launch schedule and launch success 
probabilities to predict the constellation availability--that is, the 
predicted size of the constellation as a function of time. (See 
appendix I for a more complete description of the approach used to 
generate the reliability function for each satellite and to combine 
these reliability functions into a constellation availability 
analysis.) 

While the mathematical techniques used to combine satellite 
reliability functions are straightforward, the techniques used to 
generate the reliability functions themselves have inherent 
limitations. In particular, because the reliability functions 
associated with new (unlaunched) generations of GPS satellites are 
based solely on engineering and design analysis, instead of on-orbit 
performance data, the actual reliability of these satellites may be 
very different, and reliability functions may need to be modified once 
on-orbit performance data become available. For example, while the IIA 
satellites were designed to last 7.5 years on average, they have 
actually lasted more than twice as long, and the Aerospace Corporation 
has had to adjust the reliability functions of these satellites to 
account for this difference. Moreover, satellite operators work to 
develop innovative operational tactics to maximize the useful life of 
each GPS satellite. An official with the 2nd Space Operations 
Squadron, which operates and maintains the GPS constellation, noted 
that a healthy tension exists between the acquisitions community, 
which tends to be conservative in estimating the lifetimes of the 
things it acquires, and the operations community, which continues to 
evolve new techniques and procedures for getting more life out of old 
systems. Nevertheless, the Air Force appears to have a mature process 
in place to develop, certify, and routinely update satellite 
reliability functions, and we have found no evidence to suggest that 
this process is biased toward overly conservative estimates of 
satellite lifetimes. 

Near-Term Constellation Availability Has Shown Considerable 
Improvement Since Last Year: 

Last year, we reported that because there were 31 operational GPS 
satellites of various generations, the near-term probability of 
maintaining a constellation of at least 24 operational satellites 
would remain well above 95 percent for a brief period of time, but 
because older satellites were predicted to fail faster than they were 
scheduled to be replaced, we reported that the constellation would, in 
all likelihood, decrease in size. We noted that the probability of 
maintaining a constellation of 24 operational satellites would fall to 
below 95 percent in fiscal year 2009, and to as low as 80 percent 
before recovering near the end of fiscal year 2014. This situation is 
now much improved. There are still 31 operational satellites, 30 of 
which are currently working to performance standards and available to 
GPS users. Our updated analysis, based on the most recent satellite 
reliability data, indicates that the size of the constellation is 
still expected to decline somewhat over the next several years. 
However, if the current launch schedule holds, the probability of 
maintaining a constellation of 24 satellites will remain above 95 
percent for the foreseeable future. Figure 3 compares the predicted 
size of the GPS constellation over time (at the 95 percent confidence 
level) that we calculated based on the GPS reliability data and launch 
schedule we used last year with the predicted size of the 
constellation over time that we calculated based on the latest 
available GPS reliability data and launch schedule.[Footnote 11] 

Figure 3: Comparison of Predicted Size of GPS Constellation (at the 95 
Percent Confidence Level) Based on Reliability Data and Launch 
Schedules as of March 2009 and December 2009: 

[Refer to PDF for image: multiple line graph] 

Date: October 9; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 26; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 32. 

Date: October 10; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 26. 

Date: October 11; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 22; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 26. 

Date: October 12; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 22; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 26. 

Date: October 13; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 23; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 26. 

Date: October 14; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 25. 

Date: October 15; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 23; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 24. 

Date: October 16; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 25. 

Date: October 17; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 25. 

Date: October 18; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 25. 

Date: October 19; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 25; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 25. 

Date: October 20; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 27; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 25. 

Date: October 21; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 29; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 25. 

Date: October 22; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 30; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 24. 

Date: October 23; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 30; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 24. 

Source: GAO analysis of DOD data. 

[End of figure] 

The improvement in the near-term predicted size of the constellation 
is the result of several factors, most notably the Air Force's 
assumptions regarding an increased life expectancy for some of the on-
orbit satellites. Other factors include the successful launches of the 
last two GPS-IIR-M satellites in March 2009 and August 2009 and some 
adjustments to the launch schedule. 

Our updated analysis does not include the contribution of several 
residual satellites that have been decommissioned but not yet been 
permanently disposed of. These satellites could be reactivated if 
there were an unexpectedly large number of satellite failures in the 
near future. However, the maximum size of the current constellation is 
limited to 31 operational satellites because of limitations of the 
current ground system, and none of these residual satellites is 
expected to continue operating beyond the end of fiscal year 2013. 
Consequently, while including these satellites in our analysis would 
further increase the probability of maintaining a 31-satellite 
constellation for the next few years, these residual satellites would 
have little or no impact on the size of the constellation beyond 
fiscal year 2013. 

Our updated analysis also assumes that GPS-IIR-M-20--otherwise known 
as satellite vehicle number 49 (SVN-49)--will remain operational. 
However, while this satellite is currently operational and 
broadcasting GPS signals, it has remained in an "unhealthy" status 
since it was launched in March 2009, and consequently remains 
unavailable to GPS users. The satellite remains unhealthy because of a 
small but permanent signal anomaly that could adversely affect GPS 
user equipment if it were activated without putting mitigation 
measures in place. This anomaly resulted from unexpected complications 
following the integration of a demonstration payload onto the 
satellite--a payload that broadcasts the third civil signal. The Air 
Force is examining several options to mitigate the impact of this 
anomaly, but no solution that would work for all GPS users has been 
identified. On March 26, 2010, DOT published a request seeking public 
comment on the Air Force's proposed mitigation options in the Federal 
Register.[Footnote 12] However, a final decision as to whether SVN-49 
will be set healthy is not expected to be made until June 2011. If SVN-
49 were excluded from our analysis, the impact would be to reduce the 
predicted size of the constellation by about one satellite until 
around fiscal year 2020. 

A Delay in GPS III Could Still Affect GPS Constellation Availability: 

Last year, we reported that a delay in the production and launch of 
GPS III satellites could have a big impact on the U.S. government's 
ability to meet its commitment to maintain a 24-satellite GPS 
constellation. We noted that the severity of the impact would depend 
on the length of the delay, and that, for example, a 2-year delay 
(which is less than the average delay experienced by major space 
programs over the past decade) in the production and launch of the 
first and all subsequent GPS III satellites would reduce the 
probability of maintaining a 24-satellite constellation to about 10 
percent by around fiscal year 2018. Put another way, we predicted that 
the guaranteed size of the constellation (at the 95 percent confidence 
level) would fall to about 17 satellites by that time. Our updated 
analysis based on the latest reliability data and launch schedule 
indicate that a 2-year delay in the production and launch of the GPS 
III satellites would still lead to a drop in the guaranteed size of 
the constellation (at the 95 percent confidence level) to about 18 
satellites by fiscal year 2018. See figure 4 for details. 

Figure 4: Predicted Size of GPS Constellation (at the 95 Percent 
Confidence Level) Based on a 2-Year GPS III Launch Delay and 
Reliability Data and Launch Schedules as of March 2009 and December 
2009: 

[Refer to PDF for image: multiple line graph] 

Date: October 9; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 26; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 32. 

Date: October 10; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 26. 

Date: October 11; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 22; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 26. 

Date: October 12; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 22; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 26. 

Date: October 13; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 23; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 26. 

Date: October 14; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 23; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 24. 

Date: October 15; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 21; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 22. 

Date: October 16; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 19; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 20. 

Date: October 17; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 17; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 18. 

Date: October 18; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 17; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 18. 

Date: October 19; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 19; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 19. 

Date: October 20; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 20; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 21. 

Date: October 21; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 22; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 22. 

Date: October 22; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 22. 

Date: October 23; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in March 2009: 26; 
Predicted size of constellation (95 percent confidence level) – 
parameters approved in December 2009: 21. 

Source: GAO analysis of DOD data. 

[End of figure] 

This analysis assumes that the Air Force will be able to launch all 12 
IIF satellites on schedule; a slower IIF launch rate would change the 
shape of the availability curve--reducing the amount of time that the 
guaranteed size of the constellation would remain above 24 satellites-
-but would not reduce the depth of the decline in the constellation's 
guaranteed size. Moreover, while the performance of several of the on- 
orbit satellites has been somewhat better than was expected last year, 
there has been no change to the expected lifetimes of any of the IIF, 
IIIA, IIIB or IIIC satellites. Consequently, the predicted size of the 
constellation around fiscal year 2018--at a time when the 
constellation will be predominantly made up of IIF, IIIA, and IIIB 
satellites--is about the same as last year's analysis had predicted. 
The drop-off in the predicted size of the constellation in fiscal year 
2022 is the result of changes to the approved launch schedule for the 
IIIC satellites since last year. While the Air Force still plans to 
launch the first IIIC satellite in June 2019, the scheduled launch 
dates for the rest of the IIIC satellites have been pushed back from 5 
months (for the second IIIC launch) to 28 months (for the 16th and 
final IIIC launch). 

Employment of Power Management Would Mitigate the Impact of a Delay in 
GPS III, but the Effect Would Be Small: 

Excluding random failures, the operational life of a GPS satellite 
tends to be limited by the amount of power that its solar arrays can 
produce. This power level declines over time as the solar arrays 
degrade in the space environment until eventually they cannot produce 
enough power to maintain all of the satellite's subsystems. The 
effects of this power loss can be mitigated somewhat by actively 
managing satellite subsystems--shutting them down when they are not 
needed--thereby reducing the satellite's overall consumption of power. 
The Air Force currently employs this approach--referred to as current 
management--to extend the life of GPS satellites. According to the Air 
Force, it would also be possible to significantly reduce a satellite's 
consumption of power and further extend the life of its PNT mission by 
shutting off a second payload on a GPS satellite once the satellite 
could not generate enough power to support both the missions. Shutting 
off the second payload once the satellite cannot support both missions-
-known as power management--would further mitigate the impact of a 
delay in GPS III. However, the impact is limited to increasing the 
predicted size of the constellation by about 1 satellite. For example, 
if the GPS III program were delayed by 1 year, the guaranteed size of 
the constellation (at the 95 percent confidence level) would decline 
to about 21 satellites by fiscal year 2017 if current management were 
employed and to about 22 satellites if power management were employed. 
See figure 5 for details. 

Figure 5: Predicted Size of GPS Constellation (at the 95 Percent 
Confidence Level) Based on a 1-Year GPS III Launch Delay and Current 
Management and Power Management Reliability Data and Launch Schedules 
as of December 2009: 

[Refer to PDF for image: multiple line graph] 

Date: October 9; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 32; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 32. 

Date: October 10; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 26; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 27. 

Date: October 11; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 26; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 27. 

Date: October 12; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 26; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 28. 

Date: October 13; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 26; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 27. 

Date: October 14; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 24; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 26. 

Date: October 15; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 23; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 24. 

Date: October 16; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 21; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 22. 

Date: October 17; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 21; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 22. 

Date: October 18; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 22; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 23. 

Date: October 19; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 23; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 23. 

Date: October 20; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 23; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 24. 

Date: October 21; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 23; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 24. 

Date: October 22; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 23; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 24. 

Date: October 23; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 22; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 25. 

Source: GAO analysis of DOD data. 

[End of figure] 

If the GPS III program were delayed by 2 years, the guaranteed size of 
the constellation (at the 95 percent confidence level) would decline 
to about 18 satellites by fiscal year 2018 if current management were 
employed and to about 19 satellites if power management were employed. 
See figure 6 for details. 

Figure 6: Predicted Size of GPS Constellation (at the 95 Percent 
Confidence Level) Based on a 2-Year GPS III Launch Delay and Current 
Management and Power Management Reliability Data and Launch Schedules 
as of December 2009: 

[Refer to PDF for image: multiple line graph] 

Date: October 9; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 32; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 32. 

Date: October 10; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 26; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 27. 

Date: October 11; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 26; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 27. 

Date: October 12; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 26; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 28. 

Date: October 13; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 26; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 27. 

Date: October 14; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 24; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 26. 

Date: October 15; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 22; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 24. 

Date: October 16; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 20; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 21. 

Date: October 17; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 18; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 19. 

Date: October 18; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 18; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 19. 

Date: October 19; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 19; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 20. 

Date: October 20; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 21; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 21. 

Date: October 21; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 22; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 22. 

Date: October 22; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 22; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 23. 

Date: October 23; 
Committed size of satellite constellation (95 percent confidence 
level): 24; 
Predicted size of constellation (95 percent confidence level) - 
current management parameters approved in December 2009: 21; 
Predicted size of constellation (95 percent confidence level) - power 
management parameters approved in December 2009: 23. 

Source: GAO analysis of DOD data. 

[End of figure] 

Because the second payload relies on the PNT payload, there would be 
no operational benefit to retaining the second payload and shutting 
off the PNT payload at the point where a satellite cannot support both 
missions. However, the constellation availability analysis that 
employs power management does not address whether the constellation is 
satisfying the missions supported by the second payload. Moreover, 
according to Air Force Space Command officials, power management 
should not be used as the basis for official constellation 
availability analysis, given the uncertainties associated with 
predicting a satellite's actual power usage. We agree, given the 
criticality of GPS to military and civilian users. 

Potential Effects of a Decline in the Availability of the GPS 
Constellation Appear to Be Poorly Understood but Vary Significantly 
Depending on Circumstances: 

If GPS constellation performance were to fall below the baseline 
constellation of 24 satellites, the constellation would continue to 
provide a high level of service to most users most of the time, 
although accuracy and availability could diminish in some locations 
for brief periods. Military users of GPS understand that a diminished 
constellation of fewer than 24 satellites will affect their 
operations. However, it is unclear whether military users of GPS 
understand the potential specific effects. The Army, Marine Corps, and 
Navy user representatives reported that their services had not 
conducted any studies to assess how their operations would be affected 
if the constellation were to drop below 24 satellites. Furthermore, 
while some user representatives pointed out that the effects of 
diminished constellation availability would vary depending on which 
satellites continued to be available, most did not provide very 
specific explanations of the potential effects of a decline below 
performance standards on their services' operations. For example, the 
services reported the following: 

* Air Force. The Air Force user representative stated that the Air 
Force has "a healthy concern for the ready viability, integrity, and 
availability of this system. Specific data points, analysis, and 
vulnerabilities would be classified." Any system that would possibly 
function without its full designed or optimized capability would 
naturally have some operational degradation. 

* Army. The Army user representative stated that effects largely 
depend on which satellites would remain available. If there is a 
decline just below 24 satellites, the effect would probably be 
minimal, but with each additional space vehicle lost the operational 
impact would increase. 

* Marine Corps. The Marine Corps user representative stated that 
Marines are accustomed to using GPS for PNT; therefore the loss of GPS 
would severely affect Marines' ability to navigate. Effects would vary 
depending on the situation in which a user operates. The most severely 
affected Marines would be those who use GPS in marginal but currently 
acceptable conditions, such as under foliage, in mountains, and in 
urban settings, where a smaller constellation is more likely to result 
in diminished or no service. 

* Navy. The Navy user representative stated that there is no "one-size-
fits-all" answer, that information regarding the effects would be 
classified, and that the Navy would continue to operate even if it 
could not use GPS, although missions might take longer to accomplish 
and require additional assets. 

Civil agency officials stated that if the constellation performance 
fell below the committed level of service, their operations would be 
affected; however, the effects vary by agency. For instance, Federal 
Aviation Administration (FAA) officials stated that a constellation 
smaller than the committed 24 satellites could result in flight delays 
and increased reliance on legacy ground-based navigation and 
surveillance systems. Likewise, U.S. Coast Guard officials stated that 
they could revert back to older methods of navigation if GPS service 
were diminished, but there would be a loss of efficiency. On the other 
hand, the National Institute of Standards and Technology, within the 
Department of Commerce, relies on GPS for timing data rather than 
navigation data and may be less sensitive to decreases in the number 
of GPS satellites. Furthermore, some civil agencies rely on both GPS 
and augmentation systems. For example, FAA augmentation systems 
increase the integrity of GPS for aviation purposes. However, 
officials from a few civil agencies explained that the augmentation 
systems cannot compensate for a drop in the size of the GPS 
constellation below the committed level. 

Exploitation of New Satellite Capabilities Delayed Further Because of 
Ground Control and User Equipment Delays and Acquisition Challenges: 

GPS modernization efforts across the space, ground control, and user 
equipment segments introduce new capabilities, such as improved 
resistance to jamming and greater accuracy. For most of these new 
capabilities, all three segments need to be in place in order for 
users to benefit from the new capability. However, the development of 
GPS ground control systems has experienced years of delay and in some 
cases will delay the delivery of new capabilities to users. In 
addition, although the Air Force has taken steps to enable quicker 
procurement of military GPS user equipment, there are significant 
challenges to these systems' implementation. 

Ground Control Challenges: 

We previously reported that the Air Force had not been fully 
successful in synchronizing the acquisition and development of the 
next generation of GPS satellites with the ground control system, 
thereby delaying the ability of military and civil users to utilize 
new GPS satellite capabilities.[Footnote 13] The delay was due to 
funding shifts that were made to resolve GPS IIF satellite development 
problems. Since our last report, we found that the Air Force has faced 
technical problems and continued to experience delays in upgrading the 
capabilities of the current ground control system and that the 
delivery date of the follow-on ground system has further slipped. 

Table 2 highlights specific new capabilities for which there have been 
significant delays in the ground segments and additional delays that 
have occurred since last year's review. 

Table 2: Delays in Delivery of New GPS Ground Segment Capabilities: 

Capability enabled: Selective Availability Anti-Spoofing Module; 
Originally planned delivery date: September 2005; 
Delivery date reported by GAO in 2009: September 2009; 
Delay in months: 48; 
Current delivery date: January 2010; 
Delay in months: 52. 

Capability enabled: Second civil signal; 
Originally planned delivery date: September 2007; 
Delivery date reported by GAO in 2009: September 2012 or 2013; 
Delay in months: 60-72; 
Current delivery date: August 2015; 
Delay in months: 95. 

Capability enabled: Military Code; 
Originally planned delivery date: September 2007; 
Delivery date reported by GAO in 2009: September 2012 or 2013; 
Delay in months: 60-72; 
Current delivery date: September 2016; 
Delay in months: 108. 

Capability enabled: Third civil signal; 
Originally planned delivery date: September 2007; 
Delivery date reported by GAO in 2009: September 2012 or 2013; 
Delay in months: 60-72; 
Current delivery date: September 2016; 
Delay in months: 108. 

Capability enabled: Fourth civil signal; 
Originally planned delivery date: May 2013; 
Delivery date reported by GAO in 2009: Not previously reported on; 
Delay in months: N/A; 
Current delivery date: September 2016; 
Delay in months: 40. 

Source: GAO analysis of GPS Wing data. 

[End of table] 

Since our 2009 report, the contract for the newest ground system 
development effort--known as OCX--was awarded in February 2010, about 
10 months later than the original contract award date was to occur. To 
account for the delay and increase confidence in the schedule, the Air 
Force extended the OCX delivery schedule by adding 16 months of 
development time. As a result, key OCX capabilities associated with 
the IIIA satellites will not be operational until September 
2016[Footnote 14]--over 2 years after the first IIIA satellite launch. 
The Air Force is working on a mitigation strategy that calls for 
development of a separate effort to launch and control the first IIIA 
satellite. However, GPS Wing officials indicated that the effort will 
not enable new capabilities offered by IIIA, including a signal known 
as Military Code (M-code), which is designed to enable resistance to 
jamming, and three civil signals: the second civil signal (L2C), to 
improve the accuracy of the other signals; the third civil signal 
(L5), to be used for aviation; and the fourth civil signal (L1C), to 
offer interoperability with international global space-based PNT 
systems. 

The other delayed capability identified in table 2 is the Selective 
Availability Anti-Spoofing Module (SAASM),[Footnote 15] which will 
provide military users with improved security and information 
assurance. The ground control system software that precedes OCX 
deploys the SAASM functionality, which is a critical enabler of DOD's 
navigation warfare strategy. Although new user equipment capable of 
exploiting SAASM was delivered to the warfighters in 2004, they were 
not able to take full advantage of this capability until January 2010--
when the SAASM module was delivered as part of the ground control 
system. 

User Equipment Challenges: 

GPS has become an essential element in conducting military operations. 
GPS user equipment is incorporated into nearly every type of system 
used by DOD, including aircraft, spacecraft, ground vehicles, ships, 
and munitions. A key component of the GPS modernization is a new 
military signal--known as M-code--that will increase the jam 
resistance of the GPS military service. For military users to benefit 
from this new capability, they need to be provided with new military 
user equipment capable of receiving and processing the new military 
signal. 

In 2009, we found that the Air Force was not fully successful in 
synchronizing the acquisition and development of the next generation 
of GPS satellites with the user equipment, thereby delaying users' 
ability to benefit from M-code. While the signal was to be made 
operational by the GPS satellites and ground control system in about 
2013 (now 2016), we found that the warfighters would not be able to 
take full advantage of this new signal until about 2025--when the 
modernized user equipment is completely fielded. We also found that 
diffuse leadership was a contributing factor, given that there was no 
single authority responsible for synchronizing procurements and 
fielding of user equipment. More specifically, while the Air Force was 
responsible for developing the satellite and ground segments for GPS, 
the military services were individually responsible for procuring user 
equipment for the weapon systems they owned and operated. As such, 
there were separate budget, management, oversight, and leadership 
structures over the space, ground control, and user equipment 
segments. While there were valid reasons to segment procurement 
responsibility, DOD and GAO studies have consistently found that DOD 
has lacked the tools necessary to coordinate these procurements and 
ensure that they are synchronized to the extent that warfighters can 
take advantage of M-code and other new capabilities available to them 
through GPS satellites. 

Since our 2009 report, the Air Force has taken steps to enable quicker 
procurements of user equipment, but there are still significant 
challenges to its implementation. First, the Air Force intends to 
follow an acquisition approach that will enable the military services 
to contract separately with commercial GPS providers rather than 
develop entirely new, customized user equipment systems. To support 
this approach, the Air Force plans to develop a common module, which 
commercial providers could use, along with interface control 
documents, to produce their equipment. The Air Force's current 
expectation is that it will issue requests for proposals in February 
2011, formally initiate the military user equipment acquisition 
program in fiscal year 2012, and begin production in fiscal year 2015. 
At this time, however, the Air Force does not have approved 
requirements or an approved military user equipment acquisition 
strategy. 

Second, as a pathway to its new approach, the Air Force is working 
with three contractors to develop GPS receiver cards capable of 
receiving and processing legacy GPS signals and the new military 
signal, while incorporating a new security architecture into the 
design. However, the delivery of receiver cards from two contractors 
has slipped by about a year because of unforeseen challenges with 
software and hardware integration and antispoofing software 
development and integration. The third contractor is facing technical 
problems, the cause of which has not yet been identified, and the Air 
Force is uncertain as to when this contractor will deliver its 
receiver card. Even after the cards are developed and delivered, they 
still need to go through independent security and technology testing 
to demonstrate that the technologies are mature, which can take 9 
months to a year. Moreover, since there is still no program of record 
for the military GPS user equipment, it is difficult to forecast when 
enough military GPS user equipment will be in place to utilize the M-
code capabilities operationally. 

Third, some steps have been taken to better coordinate procurements of 
user equipment. Specifically, in January 2010, the Office of the Under 
Secretary of Defense for Acquisition, Technology and Logistics held 
its first annual GPS enterprise review. The purpose of this review, 
which will be held again in the fall of 2010, is to review the status 
of the GPS acquisition programs at one time and provide more 
visibility into how the GPS acquisitions and capabilities fit 
together. In addition, DOD recently created the Space and Intelligence 
Office within the Office of the Under Secretary for Acquisition, 
Technology and Logistics to ensure that all three segments of GPS stay 
synchronized in the development and acquisition processes. DOD has 
also documented GPS synchronization as one of its goals for the next 
15 years in its March 2010 Net-Centric Portfolio Strategic Plan, used 
in part to identify areas requiring additional focus. More 
specifically, DOD plans to ensure synchronized development and 
fielding of GPS space, ground control, and user equipment segments to 
support delivery of advanced capabilities. This includes fielding user 
equipment to all designated users starting in 2014 and almost 
completing fielding by full operational capability of the GPS III 
satellite constellation. In DOD's netcentric plan, M-code initial 
operational capability is defined as having 18 M-code satellites on 
orbit, having the control segment able to command and upload M-code 
capabilities to the satellites, and having enough military GPS user 
equipment in place across DOD to utilize M-code capabilities 
operationally. Furthermore, the Air Force has made significant changes 
to the definition of initial operational capability, which now takes 
into account all three GPS segments rather than only the satellite 
segment. 

DOD has taken some steps to coordinate GPS segments, but it is not 
likely that these will be sufficient to ensure that all GPS segments 
are synchronized to the maximum extent practicable, which we 
recommended last year. Specifically, we recommended that the Secretary 
of Defense appoint a single authority to oversee the development of 
GPS, including DOD space, ground control, and user equipment assets, 
to ensure that the program is well executed and resourced and that 
potential disruptions are minimized. The creation of the Space and 
Intelligence Office is a positive development; however, the office 
does not have authority over all user equipment. In addition, we 
recently reported that DOD program officials believe that the primary 
reason that user equipment is not optimally synchronized is a lack of 
coordination and effective oversight of the many military 
organizations that either develop user equipment or have some hand in 
the development.[Footnote 16] 

The GPS Interagency Requirements Process Is Relatively Untested and 
Lacks Detailed Guidance: 

The GPS interagency requirements process remains relatively untested 
and civil agencies continue to find the process confusing. The lack of 
detailed guidance on the process is a key source of confusion and has 
also contributed to other problems, such as disagreement and 
inconsistent implementation of the process. In addition, we found that 
the interagency requirements process relies on individual agencies to 
identify their own requirements but does not identify PNT needs across 
civil agencies. 

We previously reported that DOD and civil agencies considered the 
process for approving civil GPS requirements rigorous but relatively 
untested, and that civil agencies found the process confusing. 
[Footnote 17] We stated that prudent steps had been taken to manage 
requirements and coordinate among the many organizations involved with 
GPS. However, we reported that civil agencies had not submitted many 
requirements proposals to date. We focused on two proposals: those for 
the Distress Alerting Satellite System (DASS) and the geodetic 
requirement implemented by Satellite Laser Ranging (SLR). These 
proposals had yet to complete the initial steps in the interagency 
requirements process. In addition, we reported that civil agencies 
that had proposed GPS requirements found the requirements approval 
process confusing and time-consuming. We recommended that if 
weaknesses are found the Secretaries of Defense and Transportation 
should address civil agency concerns for developing requirements, 
improve collaboration and decision making, and strengthen civil agency 
participation. Both DOD and DOT concurred with this recommendation. 
DOD noted that it would seek ways to improve civil agency 
understanding of the DOD requirements process and would work to 
strengthen civil agency participation. DOT indicated that it would 
work with DOD to review the process and improve civil agency 
participation. 

GPS Interagency Requirements Process Remains Relatively Untested: 

In our current work, we found that the requirements process continues 
to be relatively untested and the lack of documentation of the various 
stages of the process makes it difficult to determine the extent to 
which requirements followed the GPS interagency requirements process. 
No new civil requirements have been requested since our prior report; 
while DASS and SLR have made some progress, no final decision on 
whether these requirements will be included on GPS has been made. In 
addition, there are some civil requirements that have already been 
included in the DOD requirements document for GPS III, but the extent 
to which they were evaluated via the interagency requirements process 
is unclear. 

The Interagency Forum for Operational Requirements (IFOR), which is co-
chaired by officials from DOD and DOT and includes members from 
several agencies, serves as the entry point into the process and is 
responsible for receiving and processing new operational requirements 
and for clarifying existing requirements. DOT has the lead 
responsibility for the coordination of civil requirements from all 
civil departments and agencies. Although guidance on the steps in the 
interagency requirements process describes a more complex process, 
descriptions by officials involved with the process indicate that 
there are three key steps in the requirements process with the final 
determination of whether a requirement is approved being made by DOD's 
Joint Requirements Oversight Council (JROC) in coordination with the 
DOT's Extended Positioning/Navigation Executive Committee: 

1. Civil agencies are to internally identify and validate their 
requirements and conduct cost, risk, and performance analyses. 

2. Civil requirements proposals are submitted to IFOR, which is 
composed of military and civil working groups. IFOR is then to assist 
with preparing civil requirements proposals for a GPS satellite 
capability development document. 

3. Upon IFOR recommendation, civil requirements enter the Joint 
Capabilities Integration Development System (JCIDS), the DOD process 
to validate warfighter requirements. DOD's JROC will make the final 
determination of whether a requirement will be approved for inclusion 
on GPS, which is documented in the JROC-approved capability 
development document. 

Additional details in the guidance provide more specificity regarding 
how these steps are to be implemented and describe additional steps 
that may be necessary if there are disagreements or other issues that 
require adjudication. In addition, there may be a considerable amount 
of communication with the requesting agency and revision during this 
process if IFOR or DOD determines that improvements to the 
requirements packages are necessary. 

As shown below, two requirements, DASS and SLR, formally entered the 
interagency requirements process but have not yet completed the review 
process. Two other civil requirements were included in the GPS III 
capability development document, but as is reflected in table 3, the 
lack of documentation of their review makes it difficult to determine 
the extent to which the GPS interagency requirements process was 
applied for those submissions. 

Table 3: Status of Completion of Interagency Requirements Process Key 
Steps for Requirements Initiated after the Development of the GPS 
Interagency Requirements Process: 

Civil requirement: L1C; 
Step 1: Civil agency identification, validation, and analysis: No. 
Generated via international agreement and sponsored by the White House; 
Step 2: IFOR reviews and approves for submission to DOD requirements 
process: No. No formal proposal submitted to IFOR, and IFOR did not 
conduct a formal review; 
Step 3: Requirement is reviewed and approved or rejected by JROC: Yes. 
Reviewed and approved by JROC, as reflected in GPS III capability 
development document. 

Civil requirement: Aviation/navigation integrity; 
Step 1: Civil agency identification, validation, and analysis: Yes. 
Sponsored by DOT/FAA; 
Step 2: IFOR reviews and approves for submission to DOD requirements 
process: No. Submitted to IFOR for review; no formal documentation of 
IFOR approval prior to JCIDS review; 
Step 3: Requirement is reviewed and approved or rejected by JROC: Yes. 
Reviewed and approved by JROC, as reflected in GPS III capability 
development document. 

Civil requirement: DASS; 
Step 1: Civil agency identification, validation, and analysis: Yes. 
Sponsored by the Coast Guard; 
Step 2: IFOR reviews and approves for submission to DOD requirements 
process: Yes. IFOR has reviewed requirement; 
Step 3: Requirement is reviewed and approved or rejected by JROC: No. 
Not yet submitted to JCIDS. 

Civil requirement: Geodetic requirement/SLR; 
Step 1: Civil agency identification, validation, and analysis: Yes. 
Sponsored by NASA and endorsed by other agencies; 
Step 2: IFOR reviews and approves for submission to DOD requirements 
process: No. Pending review; 
Step 3: Requirement is reviewed and approved or rejected by JROC: No. 
Not yet submitted to JCIDS. 

Source: GAO analysis based on agency information and discussions with 
agency officials. 

[End of table] 

Lack of Detailed Guidance Contributes to Confusion and Disagreement: 

Guidance for the interagency requirements process lacks sufficient 
detail in areas such as explanations of key terms, documentation 
standards, steps in the process, and funding. This lack of detail has 
contributed to a number of problems, such as confusion, disagreement 
among the agencies involved, and inconsistent implementation of the 
process. 

Three documents provide guidance specific to the interagency 
requirements process. National Security Presidential Directive No. 39 
(NSPD-39)[Footnote 18] provides high-level guidance and the GPS 
Interagency: 

Requirements Plan (IRP)[Footnote 19] and the IFOR charter[Footnote 20] 
provide more process-specific guidance. The documents do not define 
key terms, such as secondary mission requirement, civil use, and dual 
use, nor do they outline how these types of requirements should be 
treated in the interagency requirements process. As a result, 
distinctions based on informal verbal instructions appear to have 
affected how requirements have been treated in the process and could 
affect future funding decisions. 

* Secondary mission requirements. A secondary mission requirement, 
sometimes called a secondary payload, is a requirement that does not 
directly support the primary GPS mission to provide PNT information. 
The guidance does not define the term nor does it indicate whether or 
how a secondary mission requirement should be evaluated via the 
interagency requirements process. DASS is considered to be a secondary 
mission requirement, and Coast Guard officials involved with the DASS 
program report that its review was delayed for several years because 
of uncertainty regarding how secondary mission requirements should be 
treated in the interagency process. According to those officials, when 
the DASS requirement was submitted to IFOR in 2003, the Coast Guard 
was told that DASS should not be reviewed via this process because it 
was a secondary mission requirement and that it should instead be 
submitted directly to DOD's JCIDS requirements process. After several 
years of delay, the Coast Guard was informed that DASS should be 
reviewed by IFOR after all. IFOR ultimately accepted the requirement 
for review in 2008. 

* Civil and dual use. According to officials involved with the 
interagency requirements process, requirements that are identified by 
the civil community are considered initially to be "civil unique" and 
may later be determined to have military utility and identified as 
"dual use." However, the guidance does not define the terms, nor does 
it state how civil unique or dual-use requirements are to be treated 
in the process. Even though the guidance does not distinguish between 
these two terms, some agencies involved in the process have indicated 
that whether a requirement is considered to be civil unique or dual 
use should determine how the requirement is funded. For example, NASA 
contends that SLR should be considered dual use and that DOD should 
therefore partially cover the costs of SLR. According to NASA, both 
the civil community and the military would benefit from SLR because it 
would improve GPS accuracy. However, some DOD officials disagree. They 
stated that there are no military requirements for SLR and that it is 
therefore not a dual-use requirement, implying that it should be 
funded solely by NASA. 

In addition, the guidance provides some information regarding what 
types of documents should be submitted, but it lacks specificity, 
resulting in confusion and disagreement among the military and civil 
agencies involved. The IRP states that cost, risks and performance 
trades, and other information will be submitted in order to defend 
requirements' feasibility, affordability, and best value for the 
government. However, the guidance documents do not specify the type, 
level of detail, or formatting requirements for submissions to IFOR. 

* There has been a disconnect between the Coast Guard's understanding 
of documentation needs and DOD's documentation expectations. To remedy 
this, some Coast Guard officials involved with submitting the DASS 
requirement stated that a list of required reports and their format 
should be provided to civil agencies. These officials said that they 
provided IFOR with assessments of six alternatives, but they were told 
by DOD officials that the analyses were not adequate. In addition, 
although guidance does not indicate that documents should be submitted 
using the JCIDS format, Coast Guard officials indicated that some of 
the studies they provided in support of the DASS requirement 
submission were not accepted because they did not use that format. 

* Similarly, NASA officials have expressed frustration with the lack 
of clear and consistent guidance on documentation standards. While 
NASA officials stated that since 2007 they have provided all the 
documentation and analyses on SLR requested by IFOR, DOD officials 
stated that SLR has not been fully developed as a requirement. 

The guidance also does not explain in detail the steps in the 
interagency requirements process. For example, the guidance lacks 
detail about formal approvals needed to proceed to the next step in 
the process and about standards regarding what is to take place during 
each phase of the process. This has resulted in confusion about next 
steps for agencies that have submitted requirements and it may also 
have contributed to inconsistent implementation of the process. 

* Approval requirements. There is limited information in the guidance 
on what formal approvals are required, how they are to be documented, 
and few details as to when and how these approvals relate to one 
another. As a result, civil agency officials have indicated that they 
find it difficult to know when a requirement has been approved to move 
to the next step in the process or whether it has received final 
approval. In the case of SLR, in 2007, IFOR released a memo 
recommending that SLR be included in the GPS III capability 
development document. However, after some concerns about SLR were 
identified within DOD that approval was de facto rescinded. SLR is 
again pending IFOR review and approval. Similarly, there appears to be 
some confusion about the ultimate fate of some requirements that have 
already been included in a capability development document. For 
example, some of the aviation-related requirements were included in 
the GPS III capability development document for later increments of 
GPS III, which are important to meeting the needs of FAA's Next 
Generation Air Transportation System program, a satellite-based air 
traffic management system that is under development and is expected to 
increase the safety and enhance the capacity of the air transport 
system. However, some DOD officials report that this capability 
development document will be treated as the one for GPS IIIA and that 
requirements not included on GPS IIIA will have to be submitted 
through JCIDS again on the capability development documents for either 
the GPS IIIB or GPS IIIC. 

* Phases of the process. The guidance lacks details about specific 
phases of the interagency requirements process, which may have 
contributed to inconsistent implementation. For example, the guidance 
regarding the initial step in the interagency requirements process 
states, among other things, that civil agencies are to internally 
identify and validate their requirements. However, the requirement for 
L1C never went through this phase of the process. Instead, the request 
resulted from an international agreement and was submitted by the 
White House. In addition, expertise and experience with requirements 
and their identification and validation processes vary greatly across 
government agencies. DOT and DOD officials report that some agencies 
have documented, disciplined requirements processes. However, while 
other agencies represent vital GPS applications and users, they have 
limited experience with requirements processes because they do not 
typically acquire systems to fulfill their missions. Although it may 
not be realistic to expect civil agencies to have requirements 
processes that are as rigorous as DOD's, more detailed guidance on 
expectations regarding standards for identification and validation of 
requirements could help ensure that there is more consistency in the 
first stage of the process. 

Lastly, the guidance does not include criteria for funding decisions 
beyond indicating that sponsoring agencies must pay for their 
requirements. More specifically, the lack of details in guidance 
regarding the required timing of funding commitments has caused 
confusion. The process for considering civil GPS requirements is 
intended to maintain fiscal discipline by ensuring that only critical 
needs are funded and developed. Our past work has shown that 
requirement add-ons cause cost and schedule growth.[Footnote 21] 
Guidance requires that the agency proposing the requirement pay the 
costs associated with adding it to the GPS satellites, thereby forcing 
agencies to separate their wants from needs. IFOR has requested that 
sponsoring agencies commit to fund a requirement when the requirement 
proposal is submitted. For example, IFOR requested that the Coast 
Guard provide a funding commitment for DASS before the requirement 
enters the JCIDS process. However, information regarding when a 
funding commitment is required is not included in guidance on the 
interagency requirements process. 

Approach to Identify Civil Requirements Does Not Identify PNT Needs 
Across Agencies: 

The interagency requirements process relies on individual agencies to 
identify their own requirements but does not identify PNT needs across 
civil agencies. For example, the DASS requirement is a secondary 
mission requirement to support a search and rescue system rather than 
a performance requirement specific to PNT. While such requirements may 
fulfill important needs, they do not reflect civil community 
requirements for PNT capabilities. Yet there are considerable 
challenges to identifying needs across agencies. For example, civil 
agencies have different roles, missions, and priorities ranging from 
providing leadership related to food, agriculture, and natural 
resources to providing the safest, most efficient aerospace system in 
the world. The civil PNT Executive Committee Co-chair pointed out that 
most civil agencies have not identified PNT requirements for their 
agencies, which poses a considerable challenge to identifying these 
requirements across agencies. These challenges have resulted in an 
approach that is agency specific and not coordinated rather than a 
coordinated national approach to identifying PNT needs. 

While there is no standardized process for identifying requirements 
across civil agencies, we found that two efforts under way are 
attempting to contribute to the development of a coordinated national 
approach to identifying PNT requirements. First, DOT officials stated 
that they are working with civil agencies to identify PNT requirements 
that represent their stakeholder needs with respect to accuracy, 
availability, coverage, and integrity. This information would serve as 
input for the 2010 Federal Radionavigation Plan, a document that 
reflects official U.S. radionavigation policy, which covers 
radionavigation systems, including GPS. Second, DOD's National 
Security Space Office has been working with civil agencies to develop 
a national PNT architecture to address capability gaps and provide a 
framework for evaluating and recommending new requirements. 

Coordination of GPS Activities with the International Community 
Continues, and Some Challenges Have Been Addressed: 

Last year, we reported that the State Department has engaged other 
planned global navigation satellite system providers bilaterally and 
multilaterally in pursuit of compatibility with GPS signals and 
services and interoperability with civil GPS signals and service. The 
United States has made joint statements of cooperation with several 
countries and an executive agreement with the European Community, 
although according to State Department officials, this agreement has 
not yet been ratified by all European Union members.[Footnote 22] 
Additionally, State Department officials reported that they believe 
they lack dedicated technical expertise to monitor international 
activities. State Department officials stated that they would like DOD 
and civil agencies to dedicate funding and staff positions to 
international activities accompanied by a sustained level of senior 
management support and understanding of the importance of these 
activities. Furthermore, U.S. firms had raised a concern to the 
Department of Commerce about the lack of information from the European 
Commission relating to the process for obtaining licenses to sell 
equipment that is compatible with Galileo, a space-based global 
navigation satellite system being developed by the European Union. 
However, according to the executive agreement with the European 
Community, subject to applicable export controls, the United States 
and the European Community are to make sufficient information publicly 
available to ensure equal opportunity for persons who seek to use 
these signals, manufacture equipment to use these signals, or provide 
value-added services that use these signals. 

State Department officials said that they had no new issues or 
concerns to add to what we reported in April 2009. State Department 
officials also stated that they continue to engage other planned 
global navigation satellite system providers bilaterally and 
multilaterally in pursuit of interoperability with civil GPS signals 
and compatibility with GPS military signals. According to the 
officials we spoke with, there have been no changes in the number or 
status of cooperative agreements between the United States and other 
countries since April 2009. Furthermore, the State Department reported 
that the current number of DOD technical experts needed for 
international discussions about foreign global navigation satellite 
systems is now sufficient. 

Additionally, U.S. GPS industry representatives we met with remain 
concerned about the lack of information from the European Commission. 
In July 2009, the Office of the U.S. Trade Representative reported to 
Congress that industry representatives were concerned about (1) the 
lack of information on how to secure licenses to sell products, 
protect intellectual property rights, or both; (2) access to signal 
test equipment for Galileo's publicly available service; and (3) the 
lack of information on the three other Galileo PNT services--service 
for safety-of-life applications, an encrypted signal for government 
users, and an encrypted service intended for commercial users. 
[Footnote 23] However, according to State Department officials, in 
spring 2010, the European Commission helped address the first two of 
these concerns when it published an updated technical document that 
includes information on the process for licensing intellectual 
property rights related to Galileo. State Department officials said 
that the U.S. government is seeking additional clarification on 
Galileo's newly established intellectual property licensing scheme, 
which if it is obtained, should address the first concern. State 
Department officials explained that the updated technical document 
addresses the second concern, regarding access to signal test 
equipment for Galileo's publicly available service, and that the U.S. 
government will no longer need to pursue the issue. 

Conclusions: 

Conditions have improved for the near-term size and availability of 
the GPS constellation. While DOD has strengthened acquisition 
practices for GPS and made concerted efforts to maximize the life of 
GPS satellites, it still faces many of the same challenges we 
identified last year, as well as new ones we identified this year. For 
example, the GPS IIIA program has complex and difficult work ahead as 
it undertakes assembly, integration, and test efforts, and its 
schedule may leave little margin to address challenges that may arise. 
Such issues could affect the Air Force's ability to launch satellites 
on time, which in turn may affect future GPS constellation 
availability. Furthermore, because of continued delays with ground 
control systems and the challenges the Air Force is encountering with 
enabling quicker procurement of military GPS user equipment, new 
capabilities may not be delivered to the warfighters when DOD needs 
them. To better align key decisions and capability deliveries, DOD is 
now looking more broadly across the GPS enterprise. However, it 
remains to be seen whether these actions go far enough to synchronize 
all GPS segments to the maximum extent practicable. For example, while 
DOD's new Space and Intelligence Office will help ensure that the 
development and acquisition of all GPS segments are synchronized, this 
office does not have authority over all military user equipment 
development. Consequently, we reiterate our recommendation from our 
April 2009 report that the Secretary of Defense appoint a single 
authority to oversee the development of GPS, including DOD space, 
ground control, and user equipment assets, to ensure that the program 
is well executed and resourced and that potential disruptions are 
minimized. Furthermore, we specified that the appointee should have 
the authority to ensure that all GPS segments are synchronized to the 
maximum extent practicable, and should coordinate with the existing 
PNT infrastructure to assess and minimize potential service 
disruptions should the satellite constellation decrease in size for an 
extended period of time. Regarding the GPS interagency requirements 
process, there is still a great deal of confusion about how civil 
agencies should submit and pay for their requirements. Moreover, this 
year we found that a lack of comprehensive guidance on the GPS 
interagency requirements process is a key source of this confusion. 
Taking steps to clarify the process, documentation requirements, and 
definitions of key terms would help alleviate this confusion. 

Recommendation for Executive Action: 

We recommend that the Secretaries of Defense and Transportation, whose 
departments co-chair the National Executive Committee for Space-Based 
Positioning, Navigation, and Timing, develop more comprehensive 
guidance for the GPS interagency requirements process, including an 
explanation of key terms, documentation expectations, process steps, 
requirements approval, and funding commitments. 

Agency Comments and Our Evaluation: 

We provided a draft of this report to the Secretaries of Defense, 
Commerce, Energy, Homeland Security, State, and Transportation and the 
Administrator of the National Aeronautics and Space Administration for 
comment. DOD provided written comments on a draft of this report that 
are reprinted in appendix III. DOT provided oral comments on a draft 
of this report. 

In written comments, DOD did not concur with our recommendation that 
the Secretary of Defense and the Secretary of Transportation develop 
comprehensive guidance for the GPS interagency requirements process, 
including an explanation of key terms, documentation expectations, 
process steps, requirements approval, and funding commitments. DOD 
stated that the actions being taken by IFOR to clarify existing 
guidance, ranging from the new IFOR charter (signed in May 2010) to a 
directed review of the IRP, meet the needs being recommended by the 
report. DOT generally agreed to consider our recommendation. 

The IFOR charter, which was updated on May 26, 2010, includes some 
notable improvements compared to previous guidance, but it does not 
address all of the shortcomings we identified. In particular, the 
revised guidance provides more clarity regarding what documentation 
should be provided with requirements proposal submissions; IFOR's role 
in approving or rejecting proposed new requirements; and expectations 
regarding funding commitments, including the timing of commitments. In 
addition, the guidance states that requirements will be classified as 
operational requirements or additional payloads; however, it does not 
explain what the implications of those classifications are in terms of 
how the requirements will be treated in the interagency requirements 
process. The guidance also does not include definitions of civil 
unique and dual-use requirements, yet there are ongoing deliberations 
regarding whether SLR is a dual-use requirement. The revised guidance 
also lacks information on the type of detail, level of detail, and 
formatting structure for documentation required with requirements 
proposal submissions. Lastly, the guidance does not specify how IFOR 
approvals are to be documented and lacks specificity regarding at what 
stage a requirement is officially approved for inclusion on GPS 
satellites. Given that there is still confusion about how civil 
agencies should submit and pay for their requirements, we believe our 
recommendation remains valid that the Secretaries of Defense and 
Transportation, who are responsible for leading interagency 
coordination, should provide more comprehensive guidance. 

DOD's written comments noted that DOD concurred with a "For Official 
Use Only" (FOUO) designation for our report, which was its status 
while in draft. We subsequently worked with DOD to identify and revise 
specific areas of the report containing FOUO information, and DOD has 
confirmed that this version of the report is acceptable for public 
release. 

We received technical comments from the Departments of Commerce, 
Energy, State, and Transportation and the National Aeronautics and 
Space Administration, which have been incorporated where appropriate. 

As agreed with your offices, unless you publicly announce the contents 
of this report earlier, we plan no further distribution until 7 days 
from the report date. At that time, we will send copies of this report 
to the appropriate congressional committees; the Secretaries of 
Defense, Commerce, Energy, Homeland Security, State, and 
Transportation; the Administrator of the National Aeronautics and 
Space Administration; and other interested parties. The report also 
will be available at no charge on the GAO Web site at [hyperlink, 
http://www.gao.gov]. 

If you have any questions about this report or need additional 
information, please contact me at (202) 512-4841 or chaplainc@gao.gov. 
Contact points for our Offices of Congressional Relations and Public 
Affairs may be found on the last page of this report. The major 
contributors to this report are listed in appendix IV. 

Signed by: 

Cristina T. Chaplain: 
Director: 
Acquisition and Sourcing Management: 

[End of section] 

Appendix I: Scope and Methodology: 

In order to assess the status of the U.S. Air Force's efforts to 
develop and deliver new Global Positioning System (GPS) satellites, 
the availability of the GPS constellation, and the potential impacts 
on users if the constellation availability diminishes below its 
committed level of performance, we performed several tasks. Our work 
is based on the most current information available as of April 16, 
2010. 

To assess the status of the Department of Defense's (DOD) efforts to 
develop and deliver new GPS satellites, we reviewed and analyzed 
current program plans and documentation related to cost, requirements, 
program direction, and acquisition and launch schedules. We also 
interviewed officials from the Office of the Assistant Secretary of 
Defense, Networks and Information Integration; the Office of the Under 
Secretary of Defense for Acquisition, Technology and Logistics; the 
Office of the Joint Chiefs of Staff; U.S. Strategic Command; the Air 
Force Space Command; the Air Force Space and Missile Systems Center's 
GPS Wing; the Air Force's 2nd Space Operations Squadron; and the Air 
Staff. In addition, to assess the reliability of the GPS IIIA space 
vehicle integrated master schedule, we reviewed 5 of 20 supporting 
project schedules and compared those schedules with relevant best 
practices as identified in our Cost Estimating and Assessment Guide. 
[Footnote 24] The review period for the 5 schedules was from May 2008 
to July 2009. These 5 schedules were selected because they make up the 
bulk of the work and they are most critical to the production of the 
GPS IIIA space vehicle. This analysis revealed the extent to which the 
schedules reflected key estimating practices that are fundamental to 
having a reliable schedule. In conducting this analysis, we 
interviewed GPS Wing officials and contractor representatives to 
discuss their use of best practices in creating the program's current 
schedules. 

To assess the availability of the GPS constellation, we did the 
following: 

* Interviewed officials from the Air Force Space and Missile Systems 
Center GPS Wing, the Air Force Space Command, the Air Force's 2nd 
Space Operations Squadron, and the Department of Energy's National 
Nuclear Security Administration. To assess the risks that a delay in 
the acquisition and fielding of GPS III satellites could result in the 
U.S. government failing to meet its commitment to a 95 percent 
probability of maintaining a constellation of 24 operational GPS 
satellites, we obtained information from the Air Force predicting the 
reliability of 79 GPS satellites--each of the 32 operational (on-
orbit) satellites, 44 future GPS satellites, and 3 residual 
satellites--as a function of their time on orbit. Each satellite's 
total reliability function defines the probability that the satellite 
will still be operational (or in sufficient working order to be made 
operational) at a given time in the future. This reliability function 
is generated from the product of two cumulative reliability functions--
a wear out reliability function governed by the cumulative normal 
distribution and a random reliability function governed by the 
cumulative Weibull distribution.[Footnote 25] The reliability function 
for a specific satellite is defined by a set of four parameters--two 
that define the cumulative normal distribution and two that define the 
cumulative Weibull distribution. 

* Obtained two sets of reliability parameters for each of the 79 
satellites. One set of parameters describes the reliability of the 
satellites based on the "current management" approach--the Air Force's 
efforts to actively manage satellite subsystems to reduce a 
satellite's overall consumption of power. The second set of parameters 
assumed use of a power management approach--shutting off the 
satellite's second payload once the satellite is not expected to be 
capable of generating enough power to support both the positioning, 
navigation, and timing (PNT) mission and the set of missions supported 
by the second payload. For each of the 44 unlaunched satellites, we 
also obtained a parameter defining its probability of successful 
launch and its scheduled launch date. The 44 unlaunched satellites 
include 12 IIF satellites, 8 IIIA satellites, 8 IIIB satellites, and 
16 IIIC satellites; launch of the final IIIC satellite is scheduled 
for July 2025. Using this information, we generated overall 
reliability functions for each of the 32 operational, 44 unlaunched, 
and 3 residual satellites GPS satellites. We discussed with Air Force 
and Aerospace Corporation representatives, in general terms, how each 
satellite's normal and Weibull parameters were calculated. However, we 
did not analyze any of the data used to calculate these parameters. 

* Developed a Monte Carlo simulation[Footnote 26] using the 
reliability function for each of the 32 operational and 44 unlaunched 
GPS satellites to predict the probability that at least a given number 
of satellites would be operational as a function of time, based on the 
GPS launch schedule approved in December 2009.[Footnote 27] We 
conducted several runs of our simulation--each run consisting of 
10,000 trials--and generated curves depicting the predicted size of 
the GPS constellation at the 95 percent confidence level as a function 
of time. During last year's review, we compared the results for a 24-
satellite constellation with a similar Monte Carlo simulation that the 
Aerospace Corporation had performed for the Air Force, and confirmed 
that our simulation produced results that are very similar.[Footnote 
28] We compared our results with the results for the predicted size of 
the GPS constellation over time (at the 95 percent confidence level) 
that we had calculated last year using the GPS reliability data and 
launch schedule approved in March 2009. We then used our Monte Carlo 
simulation model to examine the impact of a 2-year delay in the launch 
of all GPS III satellites. We moved each GPS III launch date back by 2 
years. We then reran the model and calculated a new curve for the size 
of the operational constellation as a function of time. 

To assess the military services' understanding of the potential 
impacts on users if the constellation availability diminishes below 
its committed level of performance, we asked Air Force, Army, Marine 
Corps, and Navy military service user representatives to provide 
formal studies and analyses regarding this issue. However, because 
most military service representatives stated that their services had 
not conducted formal studies and analyses on this issue, we also 
obtained written responses to questions regarding this issue from the 
military service representatives. In addition, to describe civil 
departments' and agencies' understanding of the potential impacts on 
users if the constellation availability diminishes below its committed 
level of performance, we obtained written responses to questions 
regarding this issue from civil departments and agencies involved with 
the GPS interagency requirements process, including the National 
Aeronautics and Space Administration; the Department of 
Transportation, including the Federal Aviation Administration; the 
Department of Commerce, including the National Oceanic and Atmospheric 
Administration and the National Institute of Standards and Technology; 
and the Department of Homeland Security, including the U.S. Coast 
Guard. 

To assess the progress of efforts to acquire the GPS ground control 
and user equipment, we interviewed officials who manage and oversee 
these acquisitions, including officials from the Office of the 
Assistant Secretary of Defense, Networks and Information Integration; 
the Office of the Under Secretary of Defense for Acquisition, 
Technology and Logistics; the Office of the Joint Chiefs of Staff; 
U.S. Strategic Command; the Air Force Space Command; the Air Force 
Space and Missile Systems Center's GPS Wing; the Air Force's 2nd Space 
Operations Squadron; and the Air Staff. We reviewed recent 
documentation regarding the delivery of capabilities and equipment and 
assessed the level of synchronization among satellites, ground 
systems, and user equipment. Our work is based on the most current 
information available as of April 16, 2010. 

To assess the GPS interagency requirements process, we (1) reviewed 
and analyzed guidance on the process and documents related to the 
status of civil requirements and (2) interviewed officials from the 
National Aeronautics and Space Administration; the Department of 
Transportation, including the Federal Aviation Administration; the 
Department of Commerce, including the National Oceanic and Atmospheric 
Administration and the National Institute of Standards and Technology; 
the Coast Guard; the Office of the Assistant Secretary of Defense, 
Networks and Information Integration; the National Security Space 
Office; the Air Force Space Command; the Interagency Forum for 
Operational Requirements; and the National Coordination Office for 
Space-Based Positioning, Navigation, and Timing. Our work is based on 
the most current information available as of March 10, 2010. 

To assess GPS coordination efforts with the international global PNT 
community, we interviewed officials at the Department of State and the 
Air Force Space and Missile Systems Center's GPS Wing and some 
industry representatives. We also reviewed a July 2009 report to 
Congress from the Office of the U.S. Trade Representative. Our work is 
based on the most current information available as of March 2, 2010. 

We conducted this performance audit from July 2009 to September 2010 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

[End of section] 

Appendix II: GAO Assessment of GPS IIIA Prime Contractor Schedule 
Management Processes: 

Our research has identified nine practices associated with effective 
schedule estimating[Footnote 29]: (1) capturing all activities, (2) 
sequencing all activities, (3) assigning resources to all activities, 
(4) establishing the duration of all activities, (5) integrating 
schedule activities horizontally and vertically, (6) establishing the 
critical path for all activities, (7) identifying float[Footnote 30] 
between activities, (8) conducting a schedule risk analysis, and (9) 
updating the schedule using logic and durations to determine the dates. 

The GPS IIIA space vehicle integrated master schedule consists of a 
master schedule with 20 embedded project schedules representing 
individual integrated product teams. We selected 5 of these project 
schedules for review because they make up the bulk of the work and 
they are most critical to the production of the GPS IIIA space 
vehicle. Specifically, we selected the Antenna Element, Bus, General 
Dynamics, Navigation Unit Panel, and Launch Operations project 
schedules and assessed them against the nine best practices for 
schedule development (see table 4). The review period for the 5 
schedules was from May 2008 to July 2009. 

Table 4: Schedules and Their Descriptions: 

Schedule name: Antenna Element; 
Description: Represents the subcontractor integration effort for the 
antenna element program that ensures the development, testing, and 
qualification of the following antennas: navigation L-band (long-
frequency wave used in civil signals) antennas; the legacy ultra high-
frequency crosslink antenna; and telemetry, tracking, and control 
antennas. 

Schedule name: Bus; 
Description: Represents the Lockheed Martin integration effort for the 
design, development, fabrication, assembly, testing, and qualification 
of the space vehicle bus and subsystems and units. 

Schedule name: General Dynamics; 
Description: Represents General Dynamic's effort as a subcontractor on 
the communications portion. 

Schedule name: Launch Operations; 
Description: Represents the Lockheed Martin integration effort to 
assess all facilities, communications, timelines, transportation, test 
equipment, plans, and other capabilities for a successful launch 
campaign. 

Schedule name: Navigation Unit Panel; 
Description: Represents the Lockheed Martin integration effort of 
International Telephone and Telegraph subcontractor work (Mission Data 
Unit time keeping, panel, program engineering, test equipment, and 
transmitter subschedules). 

Source: GAO analysis of Air Force GPS IIIA schedule data. 

[End of table] 

A well-defined schedule helps to identify the amount of human capital 
and fiscal resources that are needed to execute the program, and thus 
is an important contribution to a reliable cost estimate. Our research 
has identified a range of best practices associated with effective 
schedule estimating.[Footnote 31] These practices are as follows: 

* Capturing all activities: The schedule should reflect all activities 
(steps, events, outcomes, etc.) as defined in the program's work 
breakdown structure, including activities to be performed by both the 
government and its contractors. 

* Sequencing all activities: The schedule should be planned so that it 
can meet the program's critical dates. To meet this objective, 
activities need to be logically sequenced in the order that they are 
to be carried out. In particular, activities that must finish prior to 
the start of other activities (i.e., predecessor activities) and 
activities that cannot begin until other activities are completed 
(i.e., successor activities) should be identified. By doing so, 
interdependencies among activities that collectively lead to the 
accomplishment of events or milestones can be established and used as 
a basis for guiding work and measuring progress. 

* Assigning resources to all activities: The schedule should 
realistically reflect what resources (i.e., labor, material, and 
overhead) are needed to do the work, whether all required resources 
will be available when they are needed, and whether any funding or 
time constraints exist. 

* Establishing the duration of all activities: The schedule should 
reflect how long each activity will take to execute. In determining 
the duration of each activity, the same rationale, data, and 
assumptions used for cost estimating should be used for schedule 
estimating. Further, these durations should be as short as possible 
and they should have specific start and end dates. Excessively long 
periods needed to execute an activity should prompt further 
decomposition of the activity so that shorter execution durations will 
result. 

* Integrating schedule activities horizontally and vertically: The 
schedule should be horizontally integrated, meaning that it should 
link the products and outcomes associated with already sequenced 
activities. These links are commonly referred to as handoffs and serve 
to verify that activities are arranged in the right order to achieve 
aggregated products or outcomes. The schedule should also be 
vertically integrated, meaning that traceability exists among varying 
levels of activities and supporting tasks and subtasks. Such mapping 
or alignment among levels enables different groups to work to the same 
master schedule. 

* Establishing the critical path for all activities: Using scheduling 
software the critical path--the longest duration path through the 
sequenced list of activities--should be identified. The establishment 
of a program's critical path is necessary for examining the effects of 
any activity slipping along this path. Potential problems that may 
occur on or near the critical path should also be identified and 
reflected in the scheduling of time for high-risk activities. 

* Identifying float between activities: The schedule should identify 
float--the time that a predecessor activity can slip before the delay 
affects successor activities--so that schedule flexibility can be 
determined. As a general rule, activities along the critical path have 
the least amount of float. 

* Conducting a schedule risk analysis: A schedule risk analysis uses a 
good critical path method schedule and data about project schedule 
risks as well as Monte Carlo simulation (statistical) techniques to 
predict the level of confidence in meeting a program's completion 
date, the amount of time needed for a level of confidence, and the 
identification of high-priority risks. This analysis focuses not only 
on critical path activities but also on other schedule paths that may 
become critical. A schedule/cost risk assessment recognizes the 
interrelationship between schedule and cost and captures the risk that 
schedule durations and cost estimates may vary because of, among other 
things, limited data, optimistic estimating, technical challenges, 
lack of qualified personnel, and other external factors. As a result, 
the baseline schedule should include a buffer or a reserve of extra 
time. Schedule reserve for contingencies should be calculated by 
performing a schedule risk analysis. As a general rule, the reserve 
should be held by the project manager and applied as needed to those 
activities that take longer than scheduled because of the identified 
risks. Reserves of time should not be apportioned in advance to any 
specific activity since the risks that will actually occur and the 
magnitude of their impact is not known. 

* Updating the schedule using logic and durations to determine the 
dates: The schedule should use logic and durations in order to reflect 
realistic start and completion dates for program activities. The 
schedule should be continually monitored to determine when forecasted 
completion dates differ from the planned dates, which can be used to 
determine whether schedule variances will affect downstream work. 
Maintaining the integrity of the schedule logic is not only necessary 
to reflect true status, but is also required before conducting a 
schedule risk analysis. The schedule should avoid logic overrides and 
artificial constraint dates that are chosen to create a certain result 
on paper. To ensure that the schedule is properly updated, individuals 
trained in critical path method scheduling should be responsible for 
updating the schedule. 

Table 5 presents the findings for the five project schedules for each 
best practice, along with an overall score for the integrated master 
schedule on each best practice. Tables 6 through 10 provide details on 
the individual project schedule assessments. All durations are given 
in working time, that is, there are 5 working days per week, 22 
working days per month, and 260 working days per year. 

Table 5: Extent to Which Each Project Schedule Met Best Practices: 

Best practice: 1. Capturing all activities; 
Overall assessment (met, substantially met, partially met, minimally 
met, not met)[A]: Met; 
Antenna: Met; 
Bus: Met; 
General Dynamics: Met; 
Navigation unit panel: Substantially met; 
Launch operations: Met. 

Best practice: 2. Sequencing all activities; 
Overall assessment (met, substantially met, partially met, minimally 
met, not met)[A]: Substantially met; 
Antenna: Substantially met; 
Bus: Substantially met; 
General Dynamics: Partially met; 
Navigation unit panel: Partially met; 
Launch operations: Substantially met. 

Best practice: 3. Assigning resources to all activities; 
Overall assessment (met, substantially met, partially met, minimally 
met, not met)[A]: Met; 
Antenna: Met; 
Bus: Met; 
General Dynamics: Met; 
Navigation unit panel: Met; 
Launch operations: Substantially met. 

Best practice: 4. Establishing the duration of all activities; 
Overall assessment (met, substantially met, partially met, minimally 
met, not met)[A]: Substantially met; 
Antenna: Substantially met; 
Bus: Substantially met; 
General Dynamics: Substantially met; 
Navigation unit panel: Substantially met; 
Launch operations: Substantially met. 

Best practice: 5. Integrating schedule activities horizontally and 
vertically; 
Overall assessment (met, substantially met, partially met, minimally 
met, not met)[A]: Substantially met; 
Antenna: Substantially met; 
Bus: Substantially met; 
General Dynamics: Substantially met; 
Navigation unit panel: Substantially met; 
Launch operations: Substantially met. 

Best practice: 6. Establishing the critical path for all activities; 
Overall assessment (met, substantially met, partially met, minimally 
met, not met)[A]: Substantially met; 
Antenna: Substantially met; 
Bus: Met; 
General Dynamics: Substantially met; 
Navigation unit panel: Substantially met; 
Launch operations: Met. 

Best practice: 7. Identifying float between activities; 
Overall assessment (met, substantially met, partially met, minimally 
met, not met)[A]: Partially met; 
Antenna: Partially met; 
Bus: Partially met; 
General Dynamics: Partially met; 
Navigation unit panel: Partially met; 
Launch operations: Partially met. 

Best practice: 8. Conducting a schedule risk analysis; 
Overall assessment (met, substantially met, partially met, minimally 
met, not met)[A]: Met; 
Antenna: Met; 
Bus: Met; 
General Dynamics: Met; 
Navigation unit panel: Partially met; 
Launch operations: Substantially met. 

Best practice: 9. Updating the schedule using logic and durations to 
determine dates; 
Overall assessment (met, substantially met, partially met, minimally 
met, not met)[A]: Met; 
Antenna: Substantially met; 
Bus: Substantially met; 
General Dynamics: Met; 
Navigation unit panel: Met; 
Launch operations: Met. 

Source: GAO analysis of Air Force GPS IIIA schedule data. 

[A] Based on our analysis of the schedules and discussions with the 
GPS IIIA contractor, we rated each schedule against our five-point 
criteria and assigned a corresponding score using the evidence 
provided to support our ratings: met = 5, substantially met = 4, 
partially met =3, minimally met = 2, and not met = 1. Met--DOD 
provided complete evidence that satisfies the entire criterion. 
Substantially met--DOD provided evidence that satisfies more than half 
of the criterion. Partially met--DOD provided evidence that satisfies 
about half of the criterion. Minimally met--DOD provided evidence that 
satisfies less than half of the criterion. Not met--DOD provided no 
evidence that satisfies any part of the criterion. 

[End of table] 

Table 6: Antenna Element Schedule Analysis Details: 

Best practice: 1.Capturing all activities; 
Criterion met? Met; 
GAO analysis: Activities in the GPS IIIA integrated master schedule 
are mapped to Integrated Master Plan (IMP), Statement of Work (SOW), 
Contractor Work Breakdown Structure (CWBS), and Control Account 
Manager (CAM) custom fields. The activities in the Antenna schedule 
are mapped to 18 different SOW numbers. CAMs are involved in 
developing the schedule and revising activities within the schedule as 
necessary. 

Best practice: 2. Sequencing all activities; 
Criterion met? Substantially met; 
GAO analysis: Our analysis shows that none of the 554 remaining 
activities have missing logic. Of those remaining activities that have 
predecessor and successor logic, only 3 activities are "open-ended," 
that is, 3 activities are missing logic that would determine their 
start dates. Because their start dates are not determined by logic, 
these 3 open-ended activities may inhibit the power of the schedule to 
calculate a critical path and important downstream dates. We found 
that the schedule uses many constraints, particularly Start No Earlier 
Than (SNET) constraints. There are 71 remaining activities (13 
percent) with SNET constraints. Program schedule officials stated that 
the SNET constraints are used to manage resources and to schedule 
procurement tasks to start once funding is available. However, 
constraining an activity's start date prevents managers from 
accomplishing work as soon as possible and consumes flexibility early 
in the project. Moreover, scheduling a procurement activity with a 
constrained date does not guarantee that the item will arrive on that 
date in reality. Of the remaining activities, 35 activities (6 
percent) are linked to their successor activities with lags. Lags are 
often used to put activities on a specific date or to insert a buffer 
for risk; however, these lags persist even when predecessor activities 
are delayed (that is, when the buffer should be consumed). 

Best practice: 3. Assigning resources to all activities; 
Criterion met? Met; 
GAO analysis: We found the schedule to be sufficiently resource 
loaded. There are 53 resources listed in the schedule; two are 
specifically applied to the Antenna schedule activities with no 
evidence of overallocation. GPS Wing officials also indicated that the 
CAMs use the schedule along with other tools to review and plan for 
resource usage. 

Best practice: 4. Establishing the duration of all activities; 
Criterion met? Substantially met; 
GAO analysis: The durations of the majority of remaining activities 
meet best practices. However, several activities have longer-than-
expected[A] durations. For example, 28 remaining activities have 
durations over 200 days. Several of these activities are long-lead 
item procurement activities that may need alternative ways to monitor 
their progress. GPS Wing officials stated that CAMs review and monitor 
activity durations. 

Best practice: 5. Integrating schedule activities horizontally and 
vertically; 
Criterion met? Substantially met; 
GAO analysis: Our analysis of the schedule concludes that vertical 
traceability--that is, the ability to consistently trace Work 
Breakdown Structure (WBS) elements between detailed, intermediate, and 
master schedules--is demonstrated because the overall GPS IIIA 
integrated master schedule is made up of individual subschedules like 
the Antenna schedule. However, issues with reliance on date 
constraints and the use of lags keep this detailed schedule from being 
fully compliant with the requirement of horizontal traceability--that 
is, the overall ability of the schedule to depict relationships 
between different program elements and product handoffs. 

Best practice: 6. Establishing the critical path for all activities; 
Criterion met? Substantially met; 
GAO analysis: We discussed with GPS Wing officials how the critical 
path is calculated in the Antenna schedule. The Antenna critical path 
contains a 20-day margin for risk, which is considered a good practice 
as this represents an acknowledgment of inherent risk within the 
schedule. However, our analysis also shows that there are lags of 130 
days and 40 days in the critical path, and the first activity of the 
path starts with an unjustified SNET constraint. The critical path 
should determine the project completion date by computation using the 
logical relations between predecessor activities and their durations 
rather than artificial constraints. 

Best practice: 7. Identifying realistic total float; 
Criterion met? Partially met; 
GAO analysis: There are 31 activities with over 400 days of total 
float, and 211 activities with from 200 to 399 days of total float. In 
other words, according to the schedule, 242 activities could be 
delayed by 9 to 18 months and not delay the final activity in the 
Antenna schedule. Activities with such large float values indicate 
some lack of completeness in the schedule logic. 

Best practice: 8. Conducting a schedule risk analysis; 
Criterion met? Met; 
GAO analysis: GPS Wing officials provided evidence of a risk analysis 
being done on the entire integrated master schedule. The program uses 
traditional risk ranges of minimum, most likely, and high, which are 
applied to activity durations. The ranges are applied to triangular 
distributions before Monte Carlo simulations. In the Antenna schedule, 
we found 421 activities that have reasonable risk ranges for their 
durations that follow the guidance provided by the program. Note that 
there is no need to put risk ranges on every detail task to have a 
successful risk analysis. GPS Wing officials told us that risk 
analysis is run on the schedule monthly. 

Best practice: 9. Updating the schedule using logic and durations to 
determine the dates; 
Criterion met? Substantially met; 
GAO analysis: There are only seven instances of out-of-sequence logic--
that is, actual progress being recorded on successor activities even 
though the predecessor activities are not complete. This is a common 
occurrence in scheduling, as reality often overrides planned logic. 
However, some of the schedule logic appears to have been initially 
incorrect as some of the successor activities have started almost 2 
years early. Some of these successors are in other detailed schedules 
and cannot be moved by the Antenna schedule. 

Source: GAO analysis of Air Force GPS IIIA Antenna element schedule 
data. 

[A] The Defense Contract Management Agency recommends keeping 
individual task durations to less than 2 calendar months (or 44 
working days). The shorter the duration of the tasks in the schedule, 
the more often the CAMs are compelled to update completed work, which 
more accurately reflects the actual status of the tasks. When task 
durations are very long, management insight into the actual status is 
decreased. 

[End of table] 

Table 7: Bus Schedule Analysis Details: 

Best practice: 1. Capturing all activities; 
Criterion met? Met; 
GAO analysis: Activities in the GPS IIIA integrated master schedule 
are mapped to IMP, SOW, CWBS, and CAM custom fields. There are 100 out 
of the remaining 2,082 activities that do not have SOW numbers, but 
these are mostly zero-duration milestones, and one is a general delay 
task. CAMs are involved in developing the schedule and revise 
activities within the schedule as necessary. 

Best practice: 2. Sequencing all activities; 
Criterion met? Substantially met; 
GAO analysis: Our analysis shows that none of the 2,082 remaining 
activities have missing logic. Of those remaining activities that have 
predecessor and successor logic, only 5 activities are "open-ended"--
that is, 5 activities are missing logic from their finish dates that 
would determine the start dates of their successors. Because their 
finish dates do not link to the start dates of successor activities, 
these 5 open-ended activities will not affect the start dates of any 
successors if they are delayed. In addition, these open-ended 
activities can create artificially large total float values, which may 
affect management's ability to effectively allocate resources. We 
found that the schedule uses many constraints, particularly SNET 
constraints. There are 270 remaining activities (13 percent) with 
constraints, 269 of which are SNET constraints. Program schedule 
officials stated that the SNET constraints are used to manage 
resources and to schedule procurement tasks to start once funding is 
available. However, constraining an activity's start date prevents 
managers from accomplishing work as soon as possible and consumes 
flexibility early in the project. Moreover, scheduling a procurement 
activity with a constrained date does not guarantee that the item will 
arrive on that date in reality. Of the remaining activities, 63 
activities (3 percent) are linked to their successor activities with 
lags. Lags are often used to put activities on a specific date or to 
insert a buffer for risk; however, these lags persist even when 
predecessor activities are delayed (that is, when the buffer should be 
consumed). 

Best practice: 3. Assigning resources to all activities; 
Criterion met? Met; 
GAO analysis: We found the schedule to be sufficiently resource 
loaded. There are 14 main resources listed in the Bus schedule that 
have been used in over 2,000 activity assignments. There is no 
evidence of overallocation. GPS Wing officials also indicated that the 
CAMs use the schedule along with other tools to review and plan for 
resource usage. 

Best practice: 4. Establishing the duration of all activities; 
Criterion met? Substantially met; 
GAO analysis: The durations of the majority of remaining activities 
meet best practices. However, several activities have longer-than-
expected durations. For example, 7 remaining activities have durations 
over 400 days, and 106 have durations from 200 to 400 days. The 
longest duration is that of the battery cell life test, which takes 7-
½ years. It will be difficult to update such an activity unless the 
activity is split up into more manageable parts. GPS Wing officials 
stated that CAMs review and monitor activity durations. 

Best practice: 5. Integrating schedule activities horizontally and 
vertically; 
Criterion met? Substantially met; 
GAO analysis: Our analysis of the schedule concludes that vertical 
traceability--that is, the ability to consistently trace WBS elements 
between detailed, intermediate, and master schedules--is demonstrated 
because the overall GPS IIIA integrated master schedule is made up of 
individual subschedules like the Bus schedule. However, issues with 
reliance on date constraints and the use of lags keep this detailed 
schedule from being fully compliant with the requirement of horizontal 
traceability--that is, the overall ability of the schedule to depict 
relationships between different program elements and product handoffs. 

Best practice: 6. Establishing the critical path for all activities; 
Criterion met? Met; 
GAO analysis: We discussed with GPS Wing officials how the critical 
path is calculated in the Bus schedule. Only six activities in the Bus 
schedule are on the critical path and hence determine the date for 
SV01 Satellite Delivery. This is a consequence of a highly integrated 
master schedule with 20 component schedules. 

Best practice: 7. Identifying realistic total float; 
Criterion met? Partially met; 
GAO analysis: There are 50 activities with over 600 days of total 
float, and 303 activities with from 300 to 600 days of total float. In 
other words, according to the schedule, 353 activities could be 
delayed by 14 to 27 months and not delay the final activity in the Bus 
schedule. These high float values are due to incomplete logic and 
reliance on constraints instead of logic and durations to drive this 
schedule. Activities with such large float values indicate some lack 
of completeness in the schedule logic. 

Best practice: 8. Conducting a schedule risk analysis; 
Criterion met? Met; 
GAO analysis: GPS Wing officials provided evidence of a risk analysis 
being done on the entire integrated master schedule. In the Bus 
schedule, we found 1,109 activities that have reasonable risk ranges 
about their durations. Note that there is no need to put risk ranges 
on every detail task to have a successful risk analysis. These ranges 
are mostly percentages around the durations and are right-skewed to 
convey a higher probability of running longer than running shorter--a 
common technique in risk analysis. GPS Wing officials told us that 
risk analysis is run on the schedule monthly. 

Best practice: 9. Updating the schedule using logic and durations to 
determine the dates; 
Criterion met? Substantially met; 
GAO analysis: There are 13 instances of out-of-sequence logic--that 
is, actual progress being recorded on successor activities even though 
the predecessor activities are not complete. This is a common 
occurrence in scheduling, as reality often overrides planned logic. 
However, some of the schedule logic shows successors that were 
completed in earlier years, which should be corrected. Without 
complete, up-to-date logic, the critical path and important dates 
downstream may be incorrect. 

Source: GAO analysis of Air Force GPS IIIA Bus schedule data. 

[End of table] 

Table 8: General Dynamics Schedule Analysis Details: 

Best practice: 1. Capturing all activities; 

Criterion met? Met; 
GAO analysis: Activities in the GPS IIIA integrated master schedule 
are mapped to IMP, SOW, CWBS, and CAM custom fields. There are 15 out 
of the remaining 1,922 activities that do not have SOW numbers. CAMs 
are involved in developing the schedule and revise activities within 
the schedule as necessary. 

Best practice: 2. Sequencing all activities; 
Criterion met? Partially met; 
GAO analysis: Our analysis shows that 43 of the 1,922 remaining 
activities (2 percent) are "open-ended." Of these, 42 activities are 
missing logic from their finish dates that would determine the start 
dates of their successors. Because their finish dates do not link to 
the start dates of successor activities, these 42 open-ended 
activities will not affect the start dates of any successors if they 
are delayed. In addition, these open-ended activities can create 
artificially large total float values, which may affect management's 
ability to effectively allocate resources. We found that the schedule 
uses many constraints, particularly SNET constraints. There are 416 
remaining 1,922 activities (22 percent) with constraints, 382 of which 
are SNET constraints. Program schedule officials stated that the SNET 
constraints are used to manage resources and to schedule procurement 
tasks to start once funding is available. However, constraining an 
activity's start date prevents managers from accomplishing work as 
soon as possible and consumes flexibility early in the project. 
Moreover, scheduling a procurement activity with a constrained date 
does not guarantee that the item will arrive on that date in reality. 
The 416 constraints within the schedule include 27 Finish No Earlier 
Than (FNET) constraints. Each FNET constraint needs to be examined and 
justified, as such constraints prevent an activity from finishing 
earlier if predecessor activities allow it. Of the remaining 
activities, 167 activities (9 percent) are linked to their successor 
activities with lags. Lags are often used to put activities on a 
specific date or to insert a buffer for risk; however, these lags 
persist even when predecessor activities are delayed (that is, when 
the buffer should be consumed). 

Best practice: 3. Assigning resources to all activities; 
Criterion met? Met; 
GAO analysis: We found the schedule to be sufficiently resource 
loaded. There are 92 resources listed in the General Dynamics schedule 
that are named, costed, and assigned to activities. GPS Wing officials 
also indicated that the CAMs use the schedule along with other tools 
to review and plan for resource usage. 

Best practice: 4. Establishing the duration of all activities; 
Criterion met? Substantially met; 
GAO analysis: The durations of the majority of remaining activities 
meet best practices. However, several activities have longer-than-
expected durations (i.e., durations of no more than 2 months). For 
example, 26 remaining activities have durations from 300 to 780 days, 
and 102 have durations from 100 to 300 days. There are 10 activities 
with durations greater than 700 days, all of which appear to be level-
of-effort activities. However, these durations are fixed, so that if 
the activities that they support take more or less time, the level of 
effort does not change durations as it should. 

Best practice: 5. Integrating schedule activities horizontally and 
vertically; 
Criterion met? Substantially met; 
GAO analysis: Our analysis of the schedule concludes that vertical 
traceability--that is, the ability to consistently trace WBS elements 
between detailed, intermediate, and master schedules--is demonstrated 
because the overall GPS IIIA integrated master schedule is made up of 
individual subschedules like the General Dynamics schedule. However, 
issues with reliance on date constraints and the use of lags keep this 
detailed schedule from being fully compliant with the requirement of 
horizontal traceability--that is, the overall ability of the schedule 
to depict relationships between different program elements and product 
handoffs. 

Best practice: 6. Establishing the critical path for all activities; 
Criterion met? Substantially met; 
GAO analysis: We discussed with GPS Wing officials how the critical 
path is calculated in the General Dynamics schedule. Our analysis of 
the critical path shows that while it is determined by predecessor 
logic and durations rather than constraints, it includes two 
unexplained lags of 77 total days. It is not clear why the program 
should choose to delay the start of the lagged activities that occur 
on the critical path by a total of 15 weeks. 

Best practice: 7. Identifying realistic total float; 
Criterion met? Partially met; 
GAO analysis: There are 1,079 remaining activities (56 percent) with 
100 or more days of total float, 25 of which have from 700 to 771 days 
of total float. In other words, according to the schedule, 25 
activities could be delayed by almost 32 months and not delay the 
final activity in the General Dynamics schedule. These high float 
values are due to incomplete logic and reliance on constraints instead 
of logic and durations to drive this schedule. Activities with such 
large float values indicate some lack of completeness in the schedule 
logic. 

Best practice: 8. Conducting a schedule risk analysis; 
Criterion met? Met; 
GAO analysis: GPS Wing officials provided evidence of a risk analysis 
being done on the entire integrated master schedule. The program uses 
traditional risk ranges of minimum, most likely, and high, which are 
applied to activity durations. The ranges are applied to triangular 
distributions before Monte Carlo simulations are run. In the General 
Dynamics schedule, we found 1,758 activities that have reasonable risk 
ranges about their durations. These ranges are mostly percentages 
around the durations and are right-skewed to convey a higher 
probability of running longer than running shorter--a common technique 
in risk analysis. GPS Wing officials told us that risk analysis is run 
on the schedule monthly. 

Best practice: 9. Updating the schedule using logic and durations to 
determine the dates; 
Criterion met? Met; 
GAO analysis: Our analysis shows that there are no instances of out-of-
sequence logic--that is, actual progress being recorded on successor 
activities even though the predecessor activities are not complete. 
Our analysis found no instances of actual dates in the future or dates 
in the past that are not marked as "actual." 

Source: GAO analysis of Air Force GPS IIIA General Dynamics schedule 
data. 

[End of table] 

Table 9: Navigation Unit Panel Schedule Analysis Details: 

Best practice: 1. Capturing all activities; 
Criterion met? Substantially met; 
GAO analysis: Activities in the GPS IIIA integrated master schedule 
are designed to be mapped to IMP, SOW, CWBS, and CAM information. CAMs 
are involved in developing the schedule and revise activities within 
the schedule as necessary. However, officials stated that while the 
Panel schedule was verified by the prime contractor to fully support 
the SOW, the SOW data were inadvertently overwritten with other data. 
Senior schedulers are currently in the process of repopulating the SOW 
information in the Panel schedule. 

Best practice: 2. Sequencing all activities; 
Criterion met? Partially met; 
GAO analysis: Our analysis shows that 9 of the 126 remaining 
activities (7 percent) are "open-ended." These 9 open-ended activities 
are missing logic from their finish dates that would determine the 
start dates of their successors. Because their finish dates do not 
link to the start dates of successor activities, these 9 open-ended 
activities will not affect the start dates of any successors if they 
are delayed. In addition, these open-ended activities can create 
artificially large total float values, which may affect management's 
ability to effectively allocate resources. Considering that there are 
only 95 remaining detail activities (the other 31 remaining activities 
are milestones), this means that nearly 10 percent of the remaining 
work activities are not properly linked. We found the schedule uses 
many constraints, particularly SNET constraints. There are 12 SNET 
constraints placed on activities within the schedule, of which 11 
activities are imported from other schedules within the integrated 
master schedule. These 11 activities would presumably have their dates 
established in their own schedules by logic and duration, and 
therefore should not need constraining in the Panel schedule. There 
are 15 activities with lags to their successor activities. Lags are 
often used to put activities on a specific date or to insert a buffer 
for risk; however, these lags persist even when predecessor activities 
are delayed (that is, when the buffer should be consumed). 

Best practice: 3. Assigning resources to all activities; 
Criterion met? Met; 
GAO analysis: We found the schedule to be sufficiently resource 
loaded. There are 18 resources listed in the Panel schedule, several 
of which have been applied extensively to the schedule. GPS Wing 
officials also indicated that the CAMs use the schedule along with 
other tools to review and plan for resource usage. 

Best practice: 4. Establishing the duration of all activities; 
Criterion met? Substantially met; 
GAO analysis: The durations of the majority of remaining activities 
meet best practices. However, several activities have longer-than-
expected durations (i.e., durations of no more than 2 months). For 
example, 13 remaining activities have durations from 200 to 540 days, 
and 13 have durations from 45 to 199 days. It will be difficult to 
update long, non-level-of-effort activities unless the activities are 
split up into more manageable parts. GPS Wing officials stated that 
CAMs review and monitor activity durations. 

Best practice: 5. Integrating schedule activities horizontally and 
vertically; 
Criterion met? Substantially met; 
GAO analysis: Our analysis of the schedule concludes that vertical 
traceability--that is, the ability to consistently trace WBS elements 
between detailed, intermediate, and master schedules--is demonstrated 
because the overall GPS IIIA integrated master schedule is made up of 
individual subschedules like the Panel schedule. However, issues with 
reliance on date constraints and the use of lags keep this detailed 
schedule from being fully compliant with the requirement of horizontal 
traceability--that is, the overall ability of the schedule to depict 
relationships between different program elements and product handoffs. 

Best practice: 6. Establishing the critical path for all activities; 
Criterion met? Substantially met; 
GAO analysis: We discussed with GPS Wing officials how the critical 
path is calculated in the Panel schedule. Our analysis of the critical 
path shows that while it is determined by predecessor logic and 
durations rather than constraints, it includes two unexplained lags of 
26 total days. While these are not large lags, it is not clear why the 
program should choose to delay the start of events on the critical 
path by over 5 weeks. 

Best practice: 7. Identifying realistic total float; 
Criterion met? Partially met; 
GAO analysis: There are 31 activities within the schedule with 400 or 
more days of total float, 18 of which have more than 1,000 days of 
total float. In other words, according to the schedule, 31 activities 
could be delayed by more than 1-½ years and not delay the final 
activity in the Panel schedule. These high float values are due to 
incomplete logic and reliance on constraints instead of logic and 
durations to drive this schedule. 

Best practice: 8. Conducting a schedule risk analysis; 
Criterion met? Partially met; 
GAO analysis: GPS Wing officials provided evidence of a risk analysis 
being done on the entire integrated master schedule. However, our 
analysis of the Panel schedule reveals that only two short tasks have 
meaningful risk ranges. No other tasks within the schedule have risk 
ranges. Therefore, the Panel schedule is not fully contributing to the 
overall integrated master schedule risk analysis. Our analysis 
indicates that some activities, by their descriptive names alone, seem 
probable candidates for risk analysis. These include activities such 
as "Test Flight ...," "Test on ...," "Verify ...," "Assembly ...," and 
"Final Functional Test ...." Without conducting a comprehensive 
schedule risk analysis, decision makers will not know in advance which 
risks might delay the project, what a safe completion date might be 
for the current plan, and how much contingency reserve of time may be 
needed to achieve a successful completion date. 

Best practice: 9. Updating the schedule using logic and durations to 
determine the dates; 
Criterion met? Met; 
GAO analysis: Our analysis shows that there is only one instance of 
out-of-sequence logic--that is, actual progress being recorded on 
successor activities even though the predecessor is not complete. This 
is a common occurrence in scheduling, as reality often overrides 
planned logic. Our analysis found no instances of actual dates in the 
future or dates in the past that are not marked as "actual." 

Source: GAO analysis of Air Force GPS IIIA Navigation Unit Panel 
schedule data. 

[End of table] 

Table 10: Launch Operations Schedule Analysis Details: 

Best practice: 1. Capturing all activities; 
Criterion met? Met; 
GAO analysis: Activities in the GPS IIIA integrated master schedule 
are designed to be mapped to IMP, SOW, CWBS, and CAM information. CAMs 
are involved in developing the schedule and revise activities within 
the schedule as necessary. All 382 remaining detail activities are 
assigned to one of nine SOW numbers within the schedule. 

Best practice: 2. Sequencing all activities; 
Criterion met? Partially met; 
GAO analysis: Our analysis shows that only 1 of the 497 remaining 
activities is "open-ended." This open-ended activity is missing logic 
that would determine its start date. Because its start date is not 
determined by logic, this open-ended activity may inhibit the power of 
the schedule to calculate a critical path and important downstream 
dates. We found that the schedule uses many constraints, particularly 
SNET constraints. There are 57 SNET constraints placed on activities 
within the schedule. Program schedule officials stated that the SNET 
constraints are used to manage resources and to schedule procurement 
tasks to start once funding is available. However, constraining an 
activity's start date prevents managers from accomplishing work as 
soon as possible and consumes flexibility early in the project. 
Moreover, scheduling a procurement activity with a constrained date 
does not guarantee that the item will arrive on that date in reality. 
There are 14 activities with lags to their successor activities. Some 
lags are extremely long, ranging from 540 to 850 days. Lags are often 
used to put activities on a specific date or to insert a buffer for 
risk; however, these lags persist even when predecessor activities are 
delayed (that is, when the buffer should be consumed). Extremely long 
lags are usually used to force successor tasks to occur on specific 
dates. 

Best practice: 3. Assigning resources to all activities; 
Criterion met? Substantially met; 
GAO analysis: We found only one resource in the schedule, which was 
assigned to 272 of 382 detail activities. GPS Wing officials indicated 
that the CAMs use the schedule along with other tools to review and 
plan for resource usage. 

Best practice: 4. Establishing the duration of all activities; 
Criterion met? Substantially met; 
GAO analysis: The durations of the majority of remaining activities 
meet best practices. However, several activities have longer-than-
expected durations (i.e., durations of no more than 2 months). For 
example, 34 remaining activities have durations from 45 to 99 days, 
and 5 have durations from 200 to 281 days. It will be difficult to 
update long, non-level-of-effort activities unless the activities are 
split up into more manageable parts. GPS Wing officials stated that 
CAMs review and monitor activity durations. 

Best practice: 5. Integrating schedule activities horizontally and 
vertically; 
Criterion met? Substantially met; 
GAO analysis: Our analysis of the schedule concludes that vertical 
traceability--that is, the ability to consistently trace WBS elements 
between detailed, intermediate, and master schedules--is demonstrated 
because the overall GPS IIIA integrated master schedule is made up of 
individual subschedules like the Launch operations schedule. However, 
issues with reliance on date constraints and the use of lags keep this 
detailed schedule from being fully compliant with the requirement of 
horizontal traceability--that is, the overall ability of the schedule 
to depict relationships between different program elements and product 
handoffs. 

Best practice: 6. Establishing the critical path for all activities; 
Criterion met? Met; 
GAO analysis: We discussed with GPS Wing officials how the critical 
path is calculated in the Launch schedule. The critical path in the 
Launch schedule is less than 90 days. It begins with an external 
activity, which is the result of extensive linkage between schedules 
in the GPS IIIA integrated master schedule. 

Best practice: 7. Identifying realistic total float; 
Criterion met? Partially met; 
GAO analysis: There are 111 activities within the schedule with 200 or 
more days of total float, 33 of which have from 500 to 900 days of 
total float. In other words, according to the schedule, 33 activities 
could be delayed by over 22 months and not delay the final activity in 
the Launch schedule. These high float values are due to incomplete 
logic and reliance on constraints instead of logic and durations to 
drive this schedule. 

Best practice: 8. Conducting a schedule risk analysis; 
Criterion met? Substantially met; 
GAO analysis: GPS Wing officials provided evidence of a risk analysis 
being done on the entire integrated master schedule. Our analysis of 
the Launch schedule shows that 271 of 382 detail activities have risk 
applied to them. However, all 271 activities have the same risk 
applied to their durations. Therefore, it is difficult to determine 
whether the Launch schedule is fully or meaningfully contributing to 
the overall integrated master schedule risk analysis. Without 
conducting a comprehensive schedule risk analysis, decision makers 
will not know in advance which risks might delay the project, what a 
safe completion date might be for the current plan, and how much 
contingency reserve of time may be needed to achieve a successful 
completion date. 

Best practice: 9. Updating the schedule using logic and durations to 
determine the dates; 
Criterion met? Met; 
GAO analysis: Our analysis shows that there are only two instances of 
out-of-sequence logic--that is, actual progress being recorded on 
successor activities even though the predecessor activities are not 
complete. This is a common occurrence in scheduling, as reality often 
overrides planned logic. Our analysis found no instances of actual 
dates in the future or dates in the past that are not marked as 
"actual." 

Source: GAO analysis of Air Force GPS IIIA Launch Operations schedule 
data. 

[End of table] 

[End of section] 

Appendix III: Comments from the Department of Defense: 

Office Of The Assistant Secretary Of Defense: 
Networks And Information Integration: 
6000 Defense Pentagon: 
Washington, DC 20301-6000: 

July 26, 2010: 

Ms. Christina Chaplain: 
Director, Acquisition and Sourcing Management: 
U.S. Government Accountability Office (GAO): 
441 G Street, NW: 
Washington, DC 20548: 

Dear Ms. Chaplain: 

This is the Department of Defense (DoD) response to the GAO draft 
report, GAO-10-636, "Global Positioning System: Challenges in 
Sustaining and Upgrading Capabilities Persist," dated May 28, 2010 
(GAO Code 120847). 

The Department non-concurs with the recommendation that the Secretary 
of Defense and Secretary of Transportation develop comprehensive 
guidance for the GPS interagency requirements process. The actions 
being taken by the Interagency Forum for Operational Requirements 
(IFOR) to clarify existing guidance, ranging from the new IFOR Charter 
(signed May 2010) to a directed review of the GPS Interagency
Requirements Plan (IRP), meet the needs being recommended by the 
report. The Department also concurs with the "For Official Use Only" 
designation of the subject report, with limited public release. [Note: 
FOUO designation was removed during subsequent review and discussion 
(see p. 40)] 

Since its inception over 30 years ago, GPS has become one of the most 
widely used systems in the world for military and civilian 
Positioning, Navigation and Timing (PNT) purposes and sets the example 
for other nations seeking to provide similar services. GPS enables 
national security and economic infrastructures, which enhances 
efficiency and improves safety and effectiveness of virtually all 
operations. GPS is the cornerstone of our National PNT Architecture, 
around which future PNT services will evolve. The DoD accepts its 
responsibility with respect to GPS and is committed to maintaining and 
improving the services it provides. In that regard, the Department 
seeks support from Congress to maintain stability of GPS funding, 
enabling synchronized modernization of GPS space, ground control, and 
user equipment that is now underway. 

The staff point of contact for this review is Mr. Raymond Swider. He 
can be reached at raymond.swider@osd.mil or (703) 607-1122. 

Signed by: 

Dr. Ronald Jost: 
Deputy Assistant Secretary of Defense (C3, Space & Spectrum) 

[End of section] 

Appendix IV: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Cristina Chaplain (202) 512-4841 or chaplainc@gao.gov: 

Staff Acknowledgments: 

In addition to the contact named above, key contributors to this 
report were Art Gallegos, Assistant Director; Greg Campbell; Tisha 
Derricotte; Steven Hernandez; Laura Holliday; Jason Lee; Sigrid 
McGinty; Karen Richey; Jay Tallon; Hai Tran; Alyssa Weir; and Rebecca 
Wilson. 

[End of section] 

Footnotes: 

[1] GAO, Global Positioning System: Significant Challenges in 
Sustaining and Upgrading Widely Used Capabilities, [hyperlink, 
http://www.gao.gov/products/GAO-09-325] (Washington, D.C.: Apr. 30, 
2009). 

[2] GPS is augmented by ground-based or space-based navigation aids 
that are maintained by individual departments and agencies to provide 
users with improvements to the GPS navigation signal in terms of 
accuracy, availability, and integrity needs. 

[3] [hyperlink, http://www.gao.gov/products/GAO-09-325]. 

[4] On July 31, 2004, the Air Force GPS program office became the GPS 
Wing, when the Air Force's Space and Missile Systems Center 
reorganized and renamed its organizations to mirror the traditional 
Air Force structure. 

[5] The "back to basics" policy was instituted by the Air Force in 
2007 to direct space programs to adopt acquisition practices such as 
incremental introduction of new technologies to constellations of 
satellites and stabilization of requirements early in the acquisition 
process. 

[6] Earned value management (EVM) is a program management tool that 
integrates the technical, cost, and schedule parameters of a contract. 
During the planning phase, an integrated baseline is developed by time-
phasing budget resources for defined work. As work is performed and 
measured against the baseline, the corresponding budget value is 
"earned." Using this earned value metric, cost and schedule variances 
can be determined and analyzed. EVM provides significant benefits to 
both the government and the contractor. 

[7] GAO, Space Acquisitions: DOD Poised to Enhance Space Capabilities, 
but Persistent Challenges Remain in Developing Space Systems, 
[hyperlink, http://www.gao.gov/products/GAO-10-447T] (Washington, 
D.C.: Mar. 10, 2010). 

[8] A block, or increment, delivers a capability in a discrete, value- 
added increment. Capability increments are based on a balance of 
capability, delivery timeline, technology maturity, risk, and budget. 

[9] The navigation message broadcast by each GPS satellite contains 
data that enable GPS receivers to determine whether that satellite 
should be used to calculate a user's position. If these data indicate 
that the satellite can be used, then the satellite is considered 
healthy. During on-orbit checkout and later during routine 
maintenance, the navigation message is changed to indicate that the 
satellite is unhealthy and should not be used. 

[10] GAO, Defense Acquisitions: Challenges in Aligning Space System 
Components, [hyperlink, http://www.gao.gov/products/GAO-10-55] 
(Washington, D.C.: Oct. 29, 2009). 

[11] In [hyperlink, http://www.gao.gov/products/GAO-09-325], we 
presented our analysis somewhat differently. We showed the probability 
of maintaining a constellation of at least 24 GPS satellites as a 
function of time. For this report, we used the same underlying data to 
present the predicted size of the constellation--at the 95 percent 
confidence level--as a function of time. We believe that this 
presentation of the data better depicts the impact of our 
constellation availability analysis. In figs. 3 through 6, the 
analysis shows the guaranteed size of the GPS constellation (at the 95 
percent confidence level) under various assumptions, and makes clear 
that even under worst-case assumptions, there is a high probability 
that the constellation will remain above about 17 satellites. 

[12] 75 Fed. Reg. 14,658 (Mar. 26, 2010). 

[13] [hyperlink, http://www.gao.gov/products/GAO-09-325]. 

[14] The Air Force plans to develop OCX in blocks. Block I, to be 
delivered in August 2015, will command and control the IIIA satellites 
and enable the second civil signal. Block II, to be delivered in 
September 2016, will enable the third civil signal, the Military Code, 
and the fourth civil signal. 

[15] Antispoofing is a process of encrypting one of the codes 
broadcast by the satellites. This prevents an enemy from predicting 
the code sequence and using that prediction to generate a code that 
could be used to deceive a GPS set. The set would believe the 
deception code to be real and could falsely calculate its position. 

[16] [hyperlink, http://www.gao.gov/products/GAO-10-55]. 

[17] [hyperlink, http://www.gao.gov/products/GAO-09-325]. 

[18] White House, U.S. Space-Based Positioning, Navigation, and Timing 
Policy, NSPD-39 (Dec. 8, 2004). NSPD-39 is the national space-based 
positioning, navigation, and timing policy. 

[19] Department of Defense, Joint Staff, Interagency Requirements Plan 
(Revised June 2007). The IRP outlines the 2001 interagency 
requirements process. The process was revised and approved in 2007 by 
JROC as requested by the National Executive Committee for Space-Based 
Positioning, Navigation, and Timing. 

[20] Air Force Space Command and Department of Transportation, The 
Interagency Forum for Operational Requirements (IFOR) Charter (June 
11, 2001). The IFOR charter was approved in 2001 to outline roles, 
responsibilities, and relationships. The IFOR charter was approved by 
both DOD and DOT. 

[21] GAO, Military Space Operations: Common Problems and Their Effects 
on Satellite and Related Acquisitions, [hyperlink, 
http://www.gao.gov/products/GAO-03-825R] (Washington, D.C.: June 2, 
2003). 

[22] Agreement on the Promotion, Provision and Use of Galileo and GPS 
Satellite-Based Navigation Systems and Related Applications, U.S.- 
E.C., June 2004. The European Union replaced and succeeded the 
European Community on December 1, 2009. Treaty of Lisbon amending the 
Treaty on European Union and the Treaty Establishing the European 
Community, December 17, 2007, O.J. (C 306) 1 (2007). 

[23] Office of the U.S. Trade Representative, "USTR Report to Congress 
on U.S. Equipment Industry Access to the Galileo Program and Markets" 
(statement before Congress, July 2009). 

[24] GAO, GAO Cost Estimating and Assessment Guide: Best Practices for 
Developing and Managing Capital Program Costs, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: March 2009). 

[25] The Weibull distribution is a common two-parameter continuous 
probability distribution; it is used to model the random failures of 
GPS satellites. 

[26] Monte Carlo simulation refers to a computer-based analysis that 
uses probability distributions for key variables, selects random 
values from each of the distributions simultaneously, and repeats the 
random selection over and over. Rather than presenting a single 
outcome--such as the mostly likely or average scenario--Monte Carlo 
simulations produce a distribution of outcomes that reflect the 
probability distributions of modeled uncertain variables. 

[27] Our Monte Carlo simulation also included the reliability 
functions for each of the three residual satellites; however, we 
excluded these satellites from our primary analysis. We did, however, 
run an excursion to demonstrate what the effect of including these 
residual satellites would be on the predicted size of the 
constellation. 

[28] Last year we reported our results differently--as the probability 
of maintaining a constellation of at least 24 satellites--instead of 
the size of the constellation at the 95 percent confidence level. 
However, the underlying data generated by our Monte Carlo simulation 
can present the information in either way. 

[29] [hyperlink, http://www.gao.gov/products/GAO-09-3SP]. 

[30] Float is the amount of time an activity can slip before affecting 
the critical path, which is the longest duration path through the 
sequenced list of activities. 

[31] [hyperlink, http://www.gao.gov/products/GAO-09-3SP]. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: