This is the accessible text file for GAO report number GAO-05-946 
entitled 'Army Corps Of Engineers: Improved Planning and Financial 
Management Should Replace Reliance on Reprogramming Actions to Manage 
Project Funds' which was released on September 29, 2005. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Subcommittee on Energy and Water Development, Committee on 
Appropriations, House of Representatives: 

September 2005: 

Army Corps Of Engineers: 

Improved Planning and Financial Management Should Replace Reliance on 
Reprogramming Actions to Manage Project Funds: 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-05-946]  

GAO Highlights: 

Highlights of GAO-05-946, a report to Subcommittee on Energy and Water 
Development, Committee on Appropriations, House of Representatives: 

Why GAO Did This Study: 

In recent years, the Army Corps of Engineers (Corps) has had more work 
to accomplish than funds available. The Congress has supported the 
Corps' need to reprogram funds to complete projects. Reprogramming 
allows the Corps to move funds from projects that can not use available 
funds to those that can. However, concerns have been expressed about 
whether the Corps reprogrammed funds in accordance with applicable 
guidance. 

GAO determined for fiscal years 2003 and 2004 (1) the amount of funds 
reprogrammed; (2) if the Corps followed reprogramming guidance; (3) why 
the Corps reprogrammed funds; and (4) how effective the Corps’ 
reprogramming strategy was in managing funds. 

What GAO Found: 

In fiscal years 2003 and 2004, the Corps reprogrammed funds over 7,000 
times and moved over $2.1 billion among projects within the 
investigations and construction appropriations. Moreover, funds were 
moved in and/or out of nearly two thirds of the projects within these 
appropriation accounts. Comparable data for the operation and 
maintenance appropriation could not be provided by the Corps. 

GAO reviewed a random sample of 271 general investigation, construction 
general, and operation and maintenance projects and found that the 
Corps generally reprogrammed funds in accordance with its guidance. 
However, in eight cases, the Corps’ reprogramming actions did not 
comply with the guidance because it either exceeded established 
reprogramming thresholds and/or did not provide the appropriate 
notification to the Congress. Although in most cases the Corps 
reprogrammed funds according to its guidance, this guidance is written 
in such a way that most reprogramming actions do not count as 
reprogramming actions toward the congressional notification thresholds, 
thereby diminishing the Congress’ knowledge and oversight of how the 
Corps spends appropriated funds. 

In many cases, the Corps reprogrammed funds from projects that 
experienced unforeseen delays to projects that could make use of 
additional funds. On the other hand, reprogramming actions were 
conducted that were inconsistent with the Corps’ reprogramming 
guidance, such as to achieve a Corps goal that all projects carry no 
funds into the next fiscal year. Some of these movements were as small 
as 6 and 7 cents. Corps guidance states that small reprogramming 
actions are inconsistent with sound project management and increase its 
administrative burden. Funds were also moved into projects that had a 
reported “need” and then were subsequently removed because they were 
suddenly “excess”– sometimes on the same day or within a few days or 
weeks. Such movements appear to serve little useful purpose and create 
an administrative burden for the Corps because of the time and effort 
needed to accomplish these movements. 

The Corps has come to rely on reprogramming as its primary method to 
manage project funds. The use of reprogramming is no longer used as a 
tool when emergencies and unforeseen circumstances occur but instead 
has become the regular, recurring financial management practice. 
Finally, the use of numerous reprogramming actions to manage project 
funds, without a set of formal Corps-wide priorities, has resulted in 
an uncoordinated movement of funds between projects, with little 
consideration to pending needs or long-term planning. 

What GAO Recommends: 

GAO made five recommendations to help the Corps reduce its reliance on 
reprogramming actions, institute a financial planning and priority 
process for managing project funds, and work with congressional 
committees to develop meaningful reprogramming guidance. 
In its comments on the draft report, the Department of Defense 
concurred with all but one recommendation. It did not concur with the 
need to allot funds to projects periodically during the year. GAO still 
believes that this recommendation is needed because project changes 
occur throughout the year. 

www.gao.gov/cgi-bin/getrpt?GAO-05-946. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Anu Mittal at (202) 512-
4852 or mittala@gao.gov. 

[End of section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

The Corps Reprogrammed Significant Amounts of Funds among Hundreds of 
Projects: 

The Corps Followed Internal Guidance That Allowed Extensive 
Reprogrammings Without Congressional Notification: 

The Corps Reprogrammed Funds for Various Reasons: 

The Corps' Reprogramming Activities Resulted in Inefficient Management 
of Funds: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendixes: 

Appendix I: Scope and Methodology: 

Appendix II: Reprogramming Guidance Used by the Corps: 

Appendix III: Projects with Reprogrammings That Did Not Follow Corps 
Guidance: 

Fund Movements Conducted under ER 11-2-201 (October 1, 2002, to May 26, 
2004): 

Fund Movements Conducted under Guidance Based on the Direction Provided 
in the House Report 108-554 (May 27 to September 30, 2004): 

Appendix IV: Comments from the Department of Defense: 

Appendix V: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Staff Acknowledgments: 

Tables: 

Table 1: Fiscal Years 2003 and 2004 Appropriations: 

Table 2: Projects Where the Corps Failed to Follow Reprogramming 
Guidance: 

Figure: 

Figure 1: Reprogramming Categories during Fiscal Years 2003 and 2004: 

Letter September 16, 2005: 

The Honorable David L. Hobson: 
Chairman, Subcommittee on Energy and Water Development: 
Committee on Appropriations: 
House of Representatives: 

The Honorable Peter J. Visclosky: 
Ranking Minority Member: 
Subcommittee on Energy and Water Development: 
Committee on Appropriations: 
House of Representatives: 

Each year, the Congress provides funding to the U. S. Army Corps of 
Engineers (Corps) for hundreds of investigations, construction, and 
operation and maintenance projects for the nation's water 
resources.[Footnote 1] During fiscal year 2004, the Corps' budget for 
these types of projects was more than $3.8 billion. The conference 
report accompanying the bill that appropriates the funds includes a 
specific amount of funding for each project, in effect providing the 
Corps with direction for accomplishing water resource projects. 
However, the Corps may reprogram funds among the projects. 
Reprogramming is generally defined as the movement of funds among 
projects within an appropriation account and is permitted to provide 
agencies with the flexibility needed to manage appropriated funds. 

The authority to reprogram funds in and out of projects is implicit in 
an agency's responsibility to manage its funds, and it has evolved 
largely in the form of informal nonstatutory agreements between 
agencies and their congressional oversight committees. Although an 
agency's ability to reprogram funds may be restricted by statute, more 
frequently congressional guidance on the extent and nature of an 
agency's reprogramming authority is provided in committee reports that 
accompany appropriation bills. In the case of the Corps, the agency had 
developed internal reprogramming guidance, based on previous 
congressional direction, in 1995 that was in effect until May 2004. At 
that time, the Corps received reprogramming direction from both the 
Senate and the House Appropriations Committees. Starting on May 27, 
2004, the Corps' reprogramming procedures were based on direction that 
was subsequently included in the House of Representatives report on the 
fiscal year 2005 appropriations bill. The Corps' reprogramming guidance-
both before and after May 27, 2004-required notifying the Congress of 
the Corps' intention to move funds when reprogrammings exceeded 
specific thresholds. The thresholds vary by type of project and are set 
as a specific dollar amount and/or a percentage of project funding. The 
May 27, 2004, guidance was somewhat more restrictive, although still 
permitting the Corps to have considerable flexibility in reprogramming 
funds between projects. 

In this context, for fiscal years 2003 and 2004, we determined (1) how 
much funding the Corps moved within its Civil Works appropriations, (2) 
the extent to which the Corps followed applicable guidance in moving 
funds between projects, (3) the reasons for Corps' reprogramming 
actions during fiscal years 2003 and 2004, and (4) how effective the 
Corps' reprogramming strategy was in managing appropriated funds. In 
conducting our work, we reviewed the Corps' overall reprogramming 
activity within the investigations, construction, and operation and 
maintenance appropriations during fiscal years 2003 and 2004.[Footnote 
2] We selected a random sample of 271 investigations, construction, and 
operation and maintenance projects from these 2 years and reviewed each 
reprogramming activity, determined why funds were reprogrammed, and 
whether funds were reprogrammed in accordance with the guidance in 
effect at the time. We also held discussions with program and project 
managers to obtain further details about the projects included in our 
sample and about the advantages and disadvantages of the Corps' use of 
reprogramming to manage project funds. We conducted our review from 
December 2004 through June 2005 in accordance with generally accepted 
government auditing standards, which included an assessment of data 
reliability and internal controls. Appendix I contains a more detailed 
discussion of our scope and methodology. 

Results in Brief: 

In fiscal years 2003 and 2004, the Corps conducted thousands of 
reprogramming actions and moved billions of dollars among its civil 
works projects. Specifically, in fiscal years 2003 and 2004, the Corps 
reprogrammed funds over 7,000 times and moved over $2.1 billion among 
investigations and construction projects; the Corps could not provide 
agency wide data for reprogramming actions for operation and 
maintenance projects.[Footnote 3] During fiscal years 2003 and 2004, 
more than 60 percent of the over 1,500 investigations and construction 
projects had funds reprogrammed. In both years, the Corps reprogrammed 
over 56 percent of the total funds appropriated for the investigations 
and construction accounts. 

Although the Corps generally followed its reprogramming guidance, the 
guidance has been developed in such a way that it permits extensive 
movements of funds without congressional notification. As a result, the 
Corps was able to move billions of dollars among hundreds of projects 
without congressional knowledge and oversight. For 263 of the 271 
randomly selected projects we reviewed, the Corps reprogrammed funds in 
fiscal years 2003 and 2004 in accordance with its reprogramming 
guidance. For the 8 projects where the Corps' reprogramming actions did 
not comply with the guidance, the Corps had exceeded the thresholds 
established for reprogramming but did not provide the appropriate 
notifications to the Congress. Even though the Corps moved funds 
according to its guidance, the guidance had been developed in such a 
way that most movements of funds did not count toward congressional 
notification thresholds. For example, for investigations and 
construction projects, the Corps categorized all reprogrammings of 
funds out of a project as "revocations" which, according to its 
guidance, did not count toward congressional notification thresholds. 
Consequently, the Corps could move most or all of the funds out of a 
project without having to notify the Congress. Similarly, if funds were 
returned to the same project at a later date, the Corps did not 
consider these movements as reprogrammings that counted toward 
congressional notification thresholds. Except for the period from May 
27, 2004, to September 30, 2004, when different guidance was in effect, 
only those movements of funds into a project that were specifically 
labeled by the Corps as "reprogrammings" counted toward the 
congressional notification threshold. This category was seldom used 
and, according to Corps officials, when used, was generally limited to 
amounts that were less than the congressional notification threshold. 
As a result, only about 16 percent of investigations and construction 
reprogramming actions prior to May 27, 2004, were categorized as Corps-
defined "reprogrammings" that counted toward the threshold for 
congressional notification. We believe that all actions should have 
counted toward the congressional notification thresholds, because when 
the Corps moves funds that create a major deviation from the funding 
direction the Congress provided for these projects, the Congress should 
be informed of the changes and the reason for the changes no matter how 
the Corps chooses to categorize the movement. 

The Corps reprogrammed funds for a variety of reasons, some which 
appear to be inconsistent with the Corps' internal reprogramming 
guidance. The Corps' guidance states that reprogramming to address 
unforeseen events is a valid use of reprogramming and increases the 
efficiency of the entire program. In many cases, the Corps reprogrammed 
funds from projects that were experiencing unforeseen delays to 
projects that could make use of additional funds. Similarly, in other 
cases, funds were moved into projects that experienced unexpected 
costs, such as a lock failure on a waterway. In these cases, funds had 
to be moved from one project to another because the Corps allocated all 
available funds to projects at the beginning of the year and did not 
keep any funds aside for unexpected project contingencies. On the other 
hand, large numbers of reprogrammings were also conducted for reasons 
that were inconsistent with the Corps' internal reprogramming guidance. 
For example, to achieve a Corps goal that all projects carry no funds 
into the next fiscal year, even though Corps funds are "no year" funds 
and remain available to the Corps until spent, about 23 percent of all 
movements occurred during the last month of the fiscal year. Some of 
these movements were as small as 6 and 7 cents. Such movements appear 
to serve little useful purpose and create an administrative burden for 
the Corps. Corps guidance states that small reprogrammings are 
inconsistent with sound project management, cause additional accounting 
and paperwork efforts at all levels, and increase the risk of errors. 

The Corps' financial management practice of conducting thousands of 
reprogrammings resulted in movements of funds that were not necessary 
and reflected poor planning and an absence of Corps-wide priorities for 
projects. Corps reprogramming guidance discourages the temporary 
movement of funds and considers such actions to be inconsistent with 
sound project management practices. In addition, Corps reprogramming 
guidance states that only funds surplus to current year requirements 
should be a source for reprogramming. However, the Corps uses a "just-
in-time" reprogramming strategy under which it moves funds from 
projects that currently have available funds to projects with an 
immediate need, regardless of the donor projects' future needs or the 
relative priority of the projects receiving the funds. As a result, 
funds were removed from projects without considering their near-term 
funding requirements, such as projects with impending studies. Funds 
were also moved into projects that reportedly had a "need" and then 
were subsequently removed because they were "excess"--sometimes on the 
same day or within a few days or weeks. For example, in fiscal year 
2004, the Corps revoked 7 percent of the funds from every construction 
project--a total of $154.6 million--regardless of whether the funds 
were needed on the project or not. These funds were moved primarily to 
provide funds for "national requirements projects" (projects to which 
Corps headquarters management had promised to restore funds moved in 
prior years). Of the funds revoked and moved to the national 
requirements projects, $38.8 million was eventually moved to other 
projects because some of the national requirements projects had no need 
for these funds. One national requirements project--New York and New 
Jersey Harbor--received nearly $24.9 million. All of those funds, plus 
an additional $10.3 million were not needed on the project and were 
subsequently moved to other projects. 

We are making recommendations that the Secretary of Defense direct the 
Commanding General and Chief of Engineers of the U.S. Army Corps of 
Engineers to eliminate the use of excessive reprogramming actions and 
to provide better financial management of project funds. In commenting 
on a draft of this report, the Department of Defense stated that it was 
a constructive report and concurred with all but one of our 
recommendations. Regarding our recommendation that the Corps develop a 
financial planning and management system for the investigations, 
construction, and operation and maintenance appropriations that changes 
the way the Corps allocates funds from an annual basis to a more 
frequent basis and reflects actual schedule and project performance, 
the department said that it is important that the Corps continue to 
allocate all funds provided by the Congress for each project and that 
any deviation from that amount would not reflect the intent of the 
Congress. The department also said that withholding funds from the 
initial allocation would add administrative burden, increase 
uncertainty in execution, and would not aid in scheduling and schedule 
review. 

We disagree with the department because from the time the Corps submits 
its budget estimates until the appropriation is received, changes may 
have occurred and projects may not need the amount of funds included in 
the conference report or may need additional funds. Our recommendation 
would allow the Corps to make these known changes before allocating all 
funds to a project. Currently, the Corps makes such changes through 
reprogramming actions. Our recommendation would merely serve to 
streamline the process. This would eliminate the administrative burden 
of making project funding allocations that the Corps already knows it 
is going to reallocate through reprogramming actions. 

Background: 

The Corps' Civil Works program is responsible for investigating, 
developing, and maintaining the nation's water and related 
environmental resources. In addition, the Civil Works program also 
provides disaster response as well as engineering and technical 
services. The Corps' headquarters is located in Washington, D.C., with 
eight regional divisions, and 38 districts that carry out its domestic 
civil works responsibilities. 

Each year, the Corps' Civil Works program receives funding through the 
Energy and Water Development Appropriations Act. The act normally 
specifies a total sum for several different appropriation accounts, 
including investigations, construction, and operation and maintenance, 
to fund projects related to the nation's water resources. The funds 
appropriated to the Corps are "no year" funds, which means that they 
remain available to the Corps until spent. Table 1 shows the 
appropriations received in fiscal years 2003 and 2004 for the 
investigations, construction, and operation and maintenance accounts. 

Table 1: Fiscal Years 2003 and 2004 Appropriations: 

Dollars in thousands. 

Appropriations accounts: Investigations; 
Fiscal year 2003 budget authority: $135,019; 
Fiscal year 2004 budget authority: $116,949. 

Appropriations accounts: Construction; 
Fiscal year 2003 budget authority: $1,756,012; 
Fiscal year 2004 budget authority: $1,722,319. 

Appropriations accounts: Operation and Maintenance; 
Fiscal year 2003 budget authority: $1,940,167; 
Fiscal year 2004 budget authority: 1,967,925. 

Total; 
Fiscal year 2003 budget authority: $3,831,198; 
Fiscal year 2004 budget authority: $3,807,193. 

Source: Fiscal years 2003 and 2004 Energy and Water Development 
Appropriations Acts. 

[End of table]

The conference report accompanying the Energy and Water Development 
Appropriations Act specifically lists individual investigations, 
construction, and operation and maintenance projects and the amount of 
funds designated for each project. In effect, this provides the Corps 
with its priorities for accomplishing its water resource projects. In 
recent years, the Congress has appropriated fewer funds than the sum of 
the amount designated to individual projects in the conference report. 
The difference between the total amount designated for projects in the 
conference report and the full appropriation is known as savings and 
slippage. As directed by the Congress, the Corps reduces the conference 
report amount for each project by a percentage to allow for savings and 
slippage and then releases the entire amount of each projects' funding 
to the districts' project managers for executing projects.[Footnote 4] 
However, once the Corps has allotted the funds to specific projects, 
the Corps may reprogram the funds to other projects. 

Reprogramming Authority: 

Reprogramming is the shifting of funds from one project or program to 
another within an appropriation or fund account for purposes other than 
those contemplated at the time of appropriation. A reprogramming 
transaction changes the amount of funds provided to at least two 
projects-the donor project and the recipient project. However, more 
than two projects are often involved in a single reprogramming action. 
For example, in an effort to make effective use of available funding, 
the Corps may move funds from a construction project that has slipped 
due to inclement weather and reprogram the funds to one or more 
construction projects that are ahead of schedule or experiencing cost 
overruns. 

The authority to reprogram funds is implicit in an agency's 
responsibility to manage its funds; no specific additional statutory 
authority is necessary. While there are no governmentwide reprogramming 
guidelines, the Congress exercises control over an agency's spending 
flexibility by providing guidelines or nonstatutory instructions on 
reprogramming in a variety of ways. For example, some reprogramming and 
reporting guidelines have evolved from informal agreements between 
various agencies and their congressional oversight committees. 
Reprogramming guidelines frequently involve some form of notification 
to the House and Senate appropriations committees prior to the 
action.[Footnote 5] (In this report, notification to the House and 
Senate appropriations committees will be referred to as congressional 
notification or notifying the Congress.) In addition to notification, 
reprogramming arrangements sometimes also provide for committee 
approval prior to the movement of funds that exceed certain thresholds. 

The Corps' reprogramming guidelines have evolved over nearly 50 years, 
stemming from direction provided to the Corps through congressional 
reports and informal agreements with the House and Senate 
Appropriations Committees.[Footnote 6] In 1995, the Corps published 
revised internal reprogramming guidance based upon previous 
congressional direction (U.S. Army Corps of Engineers, Engineering 
Regulation ER 11-2-201). These reprogramming guidelines set forth 
procedures and polices on reprogramming actions for civil works 
activities under investigations, construction, and operation and 
maintenance appropriations titles, among others. 

Under the 1995 guidance, the Corps was permitted to reprogram 
construction funds up to 15 percent of the base amount of a project for 
any fiscal year. The base amount is the amount listed in the conference 
report plus any funds carried in from previous fiscal years and 
adjusted for funds sequestered, deferred, rescinded, or released from 
deferral.[Footnote 7] Any reprogramming action(s) that exceeded the 15 
percent threshold required the Corps to coordinate its intentions with 
both the House and Senate Appropriations Committees. There were two 
exceptions to the 15 percent limitation. The Corps may reprogram up to 
$300,000, without regard to percentage, for projects on which the 
amount available for the fiscal year is $2 million or less, and the 
Corps may move up to $5 million per construction project without regard 
to the percentage limitation when the increased requirement results 
from a settled contractor claim, increased contractor earnings due to 
accelerated rate of operations, or real estate deficiency judgments. 

For investigations projects, the Corps was permitted to reprogram up to 
$25,000 for projects that have a base amount of $25,000 or less. When 
the base amount exceeded $25,000, the reprogramming authority was 100 
percent of the base up to $50,000 and 25 percent of the increment over 
$50,000, not to exceed a total reprogramming of $150,000. Any 
reprogramming action(s) that exceeded these thresholds required the 
Corps to coordinate with the Congress its intention to reprogram funds. 
The 1995 guidance does not outline specific thresholds for 
congressional notification in the operation and maintenance 
appropriation. According to Corps officials, the agency interpreted the 
guidance as allowing unlimited reprogramming authority without 
congressional notification thresholds for operation and maintenance 
projects. 

During the spring of 2004, the Corps received new reprogramming 
direction from both the House and Senate Appropriations Committees. On 
May 27, 2004, the Corps issued an internal memorandum changing the 
Corps' existing reprogramming guidance to reflect direction that was 
subsequently provided in the House of Representatives Committee on 
Appropriations Report accompanying the 2005 Energy and Water 
Development Appropriation Bill (House Report 108-554 accompanying H.R. 
4614). The new guidance required the Corps to notify the Congress for 
any intended single reprogramming action on construction and operation 
and maintenance projects that exceeded $300,000 plus 20 percent of the 
base amount and to obtain approval on any project's cumulative 
reprogramming actions that exceeded $4 million. The base amount under 
House Report 108-554 was defined as the amount appropriated for the 
project or program in the budget plus any amounts carried over from 
previous fiscal years or reprogrammed during the budget year. For 
investigations, the Corps was the required to notify the Congress for 
any intended single reprogramming action that exceeded $50,000 plus 25 
percent of the base and to obtain approval on a project's cumulative 
reprogramming actions that exceeded $250,000. 

The Corps followed this guidance until the end of November 2004. At 
that time, the Corps again received new direction from the Congress, 
contained in the conference report accompanying the 2005 Energy and 
Water Development Appropriation Act. These guidelines provided 
cumulative reprogramming percentage thresholds for investigations, 
construction, and operation and maintenance accounts. The guidelines 
further required the Corps to provide quarterly reports notifying the 
Congress of reprogramming actions that fell between certain thresholds 
and required congressional approval for reprogramming actions that 
exceeded an upper threshold limit. The guidelines also allowed certain 
categories of reprogramming actions to be excluded from counting toward 
congressional notification thresholds. Appendix II shows the 1995 and 
2004 Corps reprogramming guidance. 

The Corps Reprogrammed Significant Amounts of Funds among Hundreds of 
Projects: 

In fiscal years 2003 and 2004, the Corps reprogrammed funds over 7,000 
times (3,415 actions in fiscal year 2003 and 3,641 actions in fiscal 
year 2004) among investigations and construction projects. Sixty-three 
percent (988 of 1,578) of fiscal year 2003 and 64 percent (998 of 
1,533) of fiscal year 2004 investigations and construction projects had 
funds either moved in and/or out. On average, of the projects that had 
at least one reprogramming, there were approximately 3.6 (3.5 in fiscal 
year 2003 and 3.6 in fiscal year 2004) actions per project. Corps-wide 
reprogramming data on operation and maintenance projects are not 
available. 

In terms of dollars, in fiscal years 2003 and 2004, the Corps 
reprogrammed approximately $2.1 billion of the $3.7 billion available 
for investigations and construction project funds. Additionally, the 
average amount of funds moved per reprogramming action was 
approximately $298,026 ($306,133 in fiscal year 2003 and $290,423 in 
fiscal year 2004) for investigations and construction projects. 

Because the Corps could not provide us with Corps-wide reprogramming 
data for operations and maintenance projects, we reviewed the 107 
operations and maintenance projects in our sample and found that the 
Corps reprogrammed funds 459 times for this sample, which averaged to 
4.29 reprogramming actions per project. These 459 reprogramming actions 
totaled approximately $31 million, and the average amount of funds 
moved per operation and maintenance reprogramming action was $67,592. 

The Corps Followed Internal Guidance That Allowed Extensive 
Reprogrammings Without Congressional Notification: 

For the majority of the reprogrammings that we reviewed as part of our 
sample of 271 projects, the Corps followed the reprogramming guidance 
it had in place at the time (under both the Corps' 1995 guidance and 
the May 2004 guidance). In the few instances where the guidance was not 
followed, most involved the Corps failing to notify the Congress when 
it intended to reprogram funds that would exceed certain limits. The 
Corps' reprogramming guidance allowed most reprogrammings to be 
categorized as fund movements that did not count toward the 
congressional notification thresholds. As a result, the Corps was able 
to follow its reprogramming guidance, but still conduct a large number 
of fund movements (that represented a major deviation from the funding 
direction the Congress provided for the projects in its conference 
report) and not have to inform the Congress of the changes and the 
reason for the changes. 

The Corps Generally Followed Its Reprogramming Guidance: 

In our sample of 271 projects, reprogramming actions related to only 8 
projects did not follow the reprogramming guidance in place at the time 
when the funds were moved.[Footnote 8] For these 8 projects, there were 
a total of 12 movements of funds that did not conform to the 
reprogramming guidance. One of these movements occurred during the 
period from October 1, 2003, to May 26, 2004, when the Corps' 
reprogramming guidance was contained in the 1995 guidance. The 
remaining 11 movements occurred after May 26, 2004, when the Corps' 
guidance was revised in accordance with the direction provided in House 
Report 108-554. Table 2 lists the projects and the reprogramming 
actions, and describes how the Corps failed to follow its guidance. 

Table 2: Projects Where the Corps Failed to Follow Reprogramming 
Guidance: 

Project: Green and Barren Rivers Navigation Disposition in Kentucky; 
Action: Reprogrammed $25,000 into the project; 
Guidance not followed: Exceeded congressional notification threshold 
and did not notify the Congress. 

Project: New York City Watershed in New York; 
Action: Revoked $800,000; 
Guidance not followed: Exceeded congressional notification threshold 
and did not notify the Congress until after the funds were moved. 

Project: McAlpine Locks and Dam in Kentucky and Indiana; 
Action: Moved $5.3 million into the project using accelerated 
contractor earnings authority; 
Guidance not followed: Exceeded limit for accelerated earnings 
movements and the reason funds were moved was not a correct use of this 
authority. 

Project: Ramapo River at Oakland in New Jersey; 
Action: Revoked $600,000; revoked $1,700,000; revoked $600,000; 
Guidance not followed: Exceeded congressional notification threshold 
and did not notify the Congress or notified the Congress after the 
funds were moved. 

Project: Ohio River Flood Protection in Indiana; 
Action: Revoked $500,000; 
Guidance not followed: Exceeded congressional notification threshold 
and did not notify the Congress. 

Project: New York and New Jersey Harbor; 
Action: Revoked $6,900,000; revoked $8,587,000; revoked $8,500,000; 
Guidance not followed: Exceeded congressional notification threshold 
and did not notify the Congress until after the funds were moved. 

Project: Bonneville Powerhouse Phase 1 in Oregon and Washington; 
Action: Restored $332,000 prior years savings and slippage; 
Guidance not followed: Exceeded congressional notification threshold 
and did not notify the Congress. 

Project: Plattsburgh Harbor in New York; 
Action: Revoked $625,000; 
Guidance not followed: Exceeded congressional notification threshold 
and did not notify the Congress. 

Source: GAO. 

[End of table]

In general, in cases where the Corps failed to notify the Congress of 
its intention to move funds in excess of the notification threshold, 
Corps officials said that the actions were conducted at the district 
and that the district personnel were confused about the guidance. 
Additional information on the eight projects and 12 movements are 
provided in appendix III. 

The Corps' Reprogramming Guidance Allows Numerous Movements of Funds 
without Congressional Notification: 

Although in the majority of cases we reviewed the Corps complied with 
its guidance, this guidance has been developed in such a manner that it 
provides the agency with maximum flexibility to move funds without 
notifying the Congress. Specifically, we found that most movements of 
funds that were actually reprogramming actions were categorized by the 
Corps, in accordance with its guidance, as other types of fund 
movements, which did not have to be reported to the Congress. For 
example, the Corps guidance allowed reprogrammings to be categorized 
under one of the following categories, which did not count toward 
congressional notification. 

* Revocations, which are movements of funds out of a project. 

* Restorations of current year savings and slippage, which are 
movements of funds into a project to restore that projects' current 
year savings and slippage reduction. 

* Restorations of prior year savings and slippage/revocation, which are 
movements of funds into a project to restore savings and slippage 
reductions and/or funds reprogrammed out of a project in prior fiscal 
years. 

* Restorations of current year revocations, which are movements of 
funds into a project to restore funds previously reprogrammed out of 
that project in the same fiscal year. 

* $5 million accelerated contractor earnings, which are movements of 
funds into a project to cover increased project requirements due to 
settled contractor claims, increased contractor earnings due to 
accelerated rate of operations, or a real estate deficiency judgment. 

The Corps used another category--"reprogram"--to categorize some 
movements of funds into a project. However, this category was seldom 
used and, according to Corps officials, when it was used, in most cases 
was generally limited to amounts under the congressional notification 
threshold. Figure 1 shows the reprogramming categories that were most 
commonly used for the investigations, construction, and operation and 
maintenance appropriations and which categories counted and did not 
count towards the congressional notification thresholds under the 
Corps' 1995 and 2004 guidance. 

Figure 1: Reprogramming Categories during Fiscal Years 2003 and 2004: 

[See PDF for image] 

[End of figure] 

The following three examples illustrate how the Corps can move large 
amounts of funds into or out of a project without notifying the 
Appropriations Committees and still be in compliance with its guidance. 
For the first project, the New York and New Jersey Harbor construction 
project in fiscal year 2003, the Corps moved over $65 million in and 
out of the project in the following 10 separate actions. 

* April 15, 2003; $28,052,000 revoked (funds needed for other projects);

* April 23, 2003; $2,685,000 restoration of current year revocation 
(funds needed to continue project);

* May 7, 2003; $400,000 restoration of current year revocation (no 
explanation in file);

* June 4, 2003; $13,200,000 restoration of current year revocation (no 
explanation in file);

* June 9, 2003; $5,758, 000 revoked (funds needed for other projects);

* July 18, 2003; $8,782,000 restoration of current year revocation (no 
explanation in file);

* August 22, 2003; $1,600,000 restoration of current year revocation 
(funds needed to continue project);

* September 4, 2003; $1,700,000 restoration of current year revocation 
(funds needed to continue project);

* September 4, 2003; $2,500,000 restoration of current year revocation 
(no explanation in file); and: 

* September 26, 2003; $460,000 restoration of current year revocation 
(funds needed to continue project). 

The amount moved was more than 4 times the cumulative threshold amount 
of $15,665,850 for this project, and the April 15, 2003, movement of 
$28,052,000, by itself, exceeded the threshold. Yet under the 1995 
Corps guidance, none of these 10 actions were categorized as actions 
that counted toward the notification threshold and therefore the Corps 
did not have to notify the Congress of these movements. 

Similarly, in fiscal year 2003, the Corps moved a total of over $3.1 
million in and out of the Ohio River Greenway Public Access 
construction project in Indiana in the following seven separate 
actions. 

* April 22, 2003; $1,011,000 revoked (excess funds);

* April 23, 2003; $313,000 revoked (no explanation in file);

* May 14, 2003; $1,112,000 restoration of current year revocation (no 
explanation in file);

* June 17, 2003; $150, 000 revoked (no explanation in file);

* September 5, 2003; $342,000 revoked (excess funds);

* September 9, 2003; $146,000 revoked (no explanation in file); and: 

* September 29, 2003; $27,000 revoked (excess funds). 

The amount moved was more than 10 times the cumulative threshold amount 
of $300,000 for this project, yet under the 1995 Corps guidance, none 
of these seven actions were categorized as actions that counted toward 
the notification threshold and the Congress was not notified of the 
movements. 

In the third project, in fiscal year 2003, the Corps moved a total of 
over $10.1 million into the Columbia River Fish Mitigation construction 
project in Oregon in the following seven separate actions. 

* May 9, 2003; $4,700,000 restoration of current year savings and 
slippage (needed for contract payments);

* July 16, 2003; $200,000 restoration of current year savings and 
slippage (needed for continuation of programmed activities);

* July 22, 2003; $500,000 restoration of current year savings and 
slippage (needed for critical research items);

* September 8, 2003; $456,000 restoration of current year savings and 
slippage (needed for contractor earnings);

* September 12, 2003; $87,000 restoration of current year savings and 
slippage (needed to pay contractor);

* September 22, 2003; $408,300 restoration of current year savings and 
slippage (no explanation provided); and: 

* September 24, 2003; $3,772,000 restoration of current year savings 
and slippage (no explanation provided). 

The amount moved exceeded the cumulative threshold amount of $9,256,350 
for this project, yet under the 1995 Corps guidance, none of these 
seven actions were categorized as actions that counted toward the 
notification threshold and the Congress was not notified of these 
movements. In all of these examples, if all the movements of funds had 
been categorized as "reprogrammings" and therefore had counted toward 
the notification threshold, the Corps would have had to notify the 
Congress that it intended to reprogram funds for these projects. 

The consequence of the Corps' guidance is that it allowed the Corps to 
categorize reprogrammings in fiscal years 2003 and 2004 so that few 
reprogramming actions counted toward notification thresholds. We found 
that from October 1, 2002, through May 26, 2004, when the Corps' 1995 
guidance was in effect, because of the way the Corps categorized 
movements of funds, only 18.2 percent of investigations movements and 
14.5 percent of construction movements counted toward the notification 
thresholds. (There was no notification threshold for operation and 
maintenance projects.) From May 27 to October 30, 2004, when the 
guidance was revised and made more restrictive, 79 percent of 
investigations movements and 74 percent of construction movements 
counted toward the notification thresholds. 

On the basis of our review of 271 projects, if all movements of funds 
counted toward the notification threshold, the Corps would have had to 
notify the Congress about its intention to reprogram in 47 percent of 
the projects in fiscal year 2003 and 10 percent of the projects in 
fiscal year 2004. (This assumes that the amount of each movement counts 
toward the threshold whether the funds are moved into or out of the 
project. The results are similar, however, if the cumulative impact of 
the movements are totaled (netted). For example, if the movements are 
netted, a movement into a project for $100,000 would offset another 
$100,000 movement out of that same project for a total of $0 counting 
toward the threshold. If movements were netted, the Corps would have 
had to notify the Congress about its intention to reprogram in 36 
percent of the projects in fiscal year 2003 and 6 percent of the 
projects in fiscal year 2004.) Instead, for the projects included in 
our sample, the Congress received notifications of intended 
reprogrammings for less than 1 percent of the projects in fiscal year 
2003 and about 2 percent of the projects in fiscal year 2004. 

In discussing the manner in which the Corps conducted reprogrammings 
during fiscal years 2003 and 2004, Corps officials said that the number 
of reprogrammings and the manner in which they were categorized was 
necessary to fund projects during a period of restricted budgets. We 
believe, however, the movements of funds previously discussed are 
reprogrammings that should be counted toward congressional notification 
thresholds. The number of reprogrammings and the amount of the 
reprogrammings conducted by the Corps can result in a significant 
deviation from the funding profile the Congress provided for the 
projects in its conference report, yet the Congress was seldom informed 
of the changes and the reason for the changes. Such notification would 
provide the Congress with information concerning where the Corps was 
spending its funds and would allow the Congress to provide oversight of 
Corps activities. 

The Corps Reprogrammed Funds for Various Reasons: 

Because the Corps typically allocates all its appropriations to 
authorized projects and does not keep any centralized funds available 
for unexpected project contingencies, reprogramming provides the 
flexibility to shift funds to respond to project changes and unforeseen 
events. Some of the reasons why the Corps reprogrammed funds in fiscal 
years 2003 and 2004 include weather factors, contract disputes, 
infrastructure malfunctions, new policy requirements, delays in 
securing cost-sharing agreements, unanticipated project starts, and 
savings and slippage. However, the Corps also reprogrammed funds for 
reasons that were inconsistent with the Corps' guidance, such as to 
achieve the Corps' goal of carrying zero funds into the next fiscal 
year and to restore funds to donor projects without regard to funding 
needs. 

The Corps Reprogrammed Funds to Respond to Project and Funding Changes: 

Project and program managers at the Corps typically estimate project 
needs 1 to 2 years prior to receiving appropriated funds. As with all 
agencies that are funded through the annual budget process, by the time 
the Corps obtains its funding, factors upon which such estimates were 
based may have changed and unforeseen events may have occurred. 
Responding to circumstances such as unexpected weather patterns, 
infrastructure emergencies, and hurdles in obtaining cost-share funding 
may require the use of reprogramming actions. 

For example, weather may have significant impacts on project costs and 
schedules. Unusually good weather may impact the execution of a project 
by extending the construction season and allowing more work to be 
completed; whereas unexpected weather may cause work delays. Weather 
may also impact project costs by causing damage that must be repaired. 
The Corps has often used reprogramming actions to adjust funding to 
accommodate unanticipated weather impacts. For example, in fiscal year 
2004, mud slides, caused by heavy rains, which breached the top of the 
dam embankment at the Joe Pool Lake operations and maintenance project 
in Texas, required emergency maintenance to stabilize the banks of the 
lake. The Corps reprogrammed $43,000 into the project to ensure the 
stability and safety of the dam. 

The Corps has also used reprogramming to fund repairs required as the 
result of unexpected infrastructure malfunctions, such as a lock 
failure on a waterway. In November 2002, an upstream lock gate 
malfunctioned at the John Day Lock and Dam on the Columbia River in 
Oregon. It took the Corps several months to repair the gate. While 
repairs were being made, the Corps found additional structural damage 
and had to award a new contract to fix these problems. In fiscal years 
2003 and 2004, the Corps reprogrammed nearly $21 million dollars into 
the project to cover the cost of the repairs. 

Similarly, for investigations projects, one-half of the funds for most 
feasibility studies must be provided by a cost share partner, such as a 
local or state government. Delays in securing this second-party funding 
may sometimes slow or halt a project's schedule and allow the funds to 
be reprogrammed to other projects that could use the funds. For 
example, in the Metropolitan Louisville Mill Creek Basin investigations 
project in Kentucky, the project's local cost-share sponsor decided not 
to fund the project and the land needed to begin the study could not be 
acquired. As a result, most of the project's funds could not be used by 
the Corps and about 90 percent of project's fiscal year 2004 funds were 
reprogrammed to projects that could use the funds. 

The Corps Also Reprogrammed Funds for Reasons That Were Inconsistent 
with the Corps' Guidance: 

In managing its national program, the Corps also conducted some 
reprogramming actions for reasons that were inconsistent with the 
Corps' internal reprogramming guidance. The Corps' Civil Works training 
manual on reprogramming advises program managers to round reprogramming 
requests to the thousands or tens of thousands of dollars and states 
that minor reprogramming to close out accounts is not permitted. The 
Corps' internal reprogramming guidance also advises that staff should 
not engage in small reprogrammings actions, but instead round 
transactions to the nearest $1,000. The guidance cites the negative 
administrative impact of such actions by stating that "minor 
reprogrammings cause additional accounting and paperwork efforts at all 
levels and increase the risk of errors." However, the Corps conducted 
reprogramming actions simply to achieve an internal goal of a zero 
carry-over balance for each project at the end of the fiscal year. Such 
reprogramming actions resulted in numerous shifts of funds of small 
dollar amounts, thereby increasing the administrative burden on 
managers. 

Achieving 100 percent execution of project funds and zero carry-over 
balances was a management goal of the Corps' Civil Works program during 
the time frame covered by our review. Realization of this goal was one 
of the primary performance metrics for project managers, who were rated 
on their ability to reach this target. In regard to achieving this 
goal, the Chief of the Civil Works Programs Integration Division noted 
that he had verbalized to Corps managers that "nothing else was 
acceptable." Several Corps program managers commented that this 
internal performance measure resulted in large numbers of reprogramming 
actions. If project managers felt that they could not execute all of 
their project's funds, they had an incentive to reprogram funds out of 
their project's account, since their performance was measured by their 
ability to execute only funds remaining for the project. Such 
reprogramming actions make it easier for a manager to reach the 100 
percent execution target and, therefore, receive a higher performance 
rating. 

Many of these actions occurred at the end of the fiscal year as project 
managers scrutinized their budgets for any funds that could not be 
expended within the fiscal year. Some of these reprogrammings were 
beneficial because the funds were moved to projects with year-end 
funding needs. However, some program managers told us that they felt 
the need to locate even excess "pennies" at the end of the fiscal year 
in order to achieve the target of zero carry over. As a result, in 
fiscal years 2003 and 2004, more reprogrammings occurred during the 
last month of the fiscal year than any other. For all investigations 
and construction projects in fiscal years 2003 and 2004, approximately 
23 percent of the reprogrammings conducted by the Corps occurred in the 
last month of the fiscal year, resulting in 1,617 actions moving over 
$235 million. Just over 6 percent of these movements were for amounts 
of $1,000 or under. We found similar results for our sample of 271 
projects. About 35 percent of the reprogrammings occurred in the last 
month of the fiscal year (343 actions moving over $31 million). Just 
over 13 percent of these movements were for amounts of $1,000 or under, 
with one as small as 6 cents. We found other projects, not included in 
our sample, with year-end reprogramming actions of $0.07, $13.42, 
$13.84, $14.00, $23.36, and $25.00. Reprogramming such small amounts of 
funds may unnecessarily strain administrative resources. 

Removing most of a project's funding at the end of the fiscal year may 
also result in the Corps overlooking short-term project needs, 
particularly those at the beginning of the next fiscal year, and ends 
up resulting in additional unnecessary reprogramming actions. For 
example, in the Grand Isle and Vicinity construction project in 
Louisiana, the Corps revoked $28,000 on the last day of fiscal year 
2003, based on the rationale that it was surplus to the project's 
needs. However, just over 1 week later, in fiscal year 2004, $17,000 
was restored to the project, according to the Corps, to pay labor 
costs. 

Reprogramming actions to restore funds to donor projects from projects 
that did not have a surplus also appears to be inconsistent with the 
Corps' reprogramming guidance. Corps reprogramming guidance states that 
only funds surplus to current year requirements should be a source for 
reprogramming and that temporary borrowing or loaning is inconsistent 
with sound project management practices. Despite this guidance, in 
fiscal years 2003 and 2004, we found several instances where the Corps 
returned funds to a donor project from projects that had funding needs 
and did not have surplus funds. In some instances, separate 
reprogramming actions to transfer funds out of a project to repay a 
donor, and to transfer funds into that same project in order to 
complete work schedules, occurred on the same day or within a few days 
or weeks. For example, on May 1, 2003, the Corps reprogrammed $425,000 
out of the Johnson Creek Upper Trinity River construction project in 
Texas to repay a donor project. On the same day, the Corps reprogrammed 
$1.5 million into the Johnson Creek project to provide funds for 
property acquisition necessary to keep the project on schedule. 

The Corps' Reprogramming Activities Resulted in Inefficient Management 
of Funds: 

As stated previously, Corps reprogramming guidance states that only 
funds surplus to current year requirements should be a source for 
reprogramming and that temporary borrowing or loaning is inconsistent 
with sound project management practices and increases the Corps' 
administrative burden. In fiscal year 2003 and fiscal year 2004, the 
Corps managed its civil works project funds using a "just-in-time" 
reprogramming strategy. The basis for this strategy was to allow for 
the movement of funds from projects that do not have urgent funding 
needs to projects that need funds immediately. While the just-in-time 
approach may have moved funds rapidly, its implementation sometimes 
resulted in uncoordinated and unnecessary movements of funds from 
project to project. We found that funds were moved into projects that 
had a reported "need," but were subsequently removed because they were 
"excess," revoked from projects without regard to their near-term 
funding requirements, reprogrammed into and out of the same project on 
the same day, moved into and out of the same project multiple times a 
year, and reprogrammed without a system to evaluate the priority level 
of the affected projects. This strategy has resulted in numerous 
reprogrammings that may otherwise have been unnecessary if the Corps 
had employed a financial planning and management process in which 
funding priorities had been clearly established. In addition, the 
relative convenience and ease of reprogramming within Corps districts 
may have resulted in increased numbers of reprogrammings and 
reprogrammings from projects with funding needs. 

In our review of projects from fiscal years 2003 and 2004, we found 
that funds were moved into projects, only to be subsequently revoked 
because they were excess to the project's funding needs. For example, 
in fiscal year 2004, 7 percent of the funds (totaling almost $154.6 
million) from every nonearmarked construction project were revoked in 
order to provide funding to projects designated as "national 
requirements" by the Corps. The national requirements projects were a 
group of projects to which Corps headquarters management had promised 
to restore funding that had been revoked in previous years. These 
projects included the Houston-Galveston navigation channel construction 
project in Texas, New York and New Jersey Harbor, Comite River 
diversion channel in Louisiana, Guadalupe River channel improvement in 
California, Lackawanna River at Scranton levee project in Pennsylvania, 
three navigation projects in Alaska (Saint Paul Harbor, Nome Harbor, 
and Wrangell Harbor), and various projects under the Continuing 
Authorities Program.[Footnote 9]

After the Corps moved the $154.6 million into the national requirements 
projects, the Corps revoked over a quarter of those funds, $38.8 
million, from these projects because they actually did not need the 
funds. For example, one national requirements construction project, New 
York and New Jersey Harbor, received $24.9 million. All of these funds, 
plus an additional $10.3 million, were excess to the needs of the 
project at the time and were subsequently reprogrammed to other 
projects. Corps officials in the New York District told us that, prior 
to receiving the national requirements funds, they had informed Corps 
headquarters that they could not use the additional funds. Corps 
headquarters officials said that the district had requested the funds 
based on need. Other national requirements projects that received funds 
that were subsequently reprogrammed include: 

* The Comite River construction project received almost $3 million. 
Later in fiscal year 2004, the Corps revoked nearly $1.5 million (about 
50 percent) of that funding. 

* The Lackawanna River at Scranton construction project received $15 
million. Later in fiscal year 2004, the Corps revoked $5 million (about 
33 percent) of that funding. 

* The Houston-Galveston construction project received nearly $28 
million. Later in fiscal year 2004, the Corps revoked about $7.25 
million (about 26 percent) of that funding. 

The use of the just-in-time strategy also resulted in funds being 
removed from projects without considering their near-term funding 
requirements, such as projects with impending studies. For example, on 
August 1, 2003, the Corps revoked $85,000 from the Saw Mill River and 
Tributaries investigation project in New York with the explanation that 
the funds were excess to the project's needs in the current year. Six 
weeks later, however, on September 15, 2003, $60,000 of funding was 
reprogrammed back into the project in order to initiate a feasibility 
study. Corps documents explaining the revocation of funds from the Saw 
Mill River and Tributaries project indicate the Corps' awareness of the 
project's impending needs, acknowledging that funds for the project 
would be needed again in September 2003 to execute a feasibility study. 

We also determined that under the just-in-time reprogramming strategy, 
funds were moved into and out of the same project on the same day. 
Overall, we found that 3 percent of investigations and construction 
projects in fiscal year 2003 and 2 percent of investigations and 
construction projects in fiscal year 2004 moved funds into and out of 
the same project on the same day. Some specific examples include, on 
February 6, 2004, the Corps reprogrammed just over $2 million into the 
Mill Creek construction project in Ohio from the Olmsted ($1,500,000) 
and Pond Creek ($550,000) projects and reprogrammed out $272,000 the 
same day. The Corps explained that they initiated the $272,000 
revocation in order to balance the books from previous reprogrammings. 
Also, in fiscal year 2003, the Corps used 18 separate actions to 
reprogram approximately $25 million into and about $10.5 million out of 
the Central and Southern Florida construction project, including three 
separate occasions when funds were both moved into and out of the 
project on the same day. 

Furthermore, the Corps reprogrammed funds in and out of some projects 
numerous times during a single fiscal year. For instance, in 12 
separate actions in fiscal year 2004, the Corps reprogrammed a total of 
$166,000 into the Dalles Lock and Dam operation and maintenance project 
in Washington and Oregon and revoked a total of $817,000. Many of these 
actions took place only days or weeks apart from one another. 

* March 9, 2004; $76,000 revoked;

* March, 23, 2004; $261,000 revoked;

* May 27, 2004; $31,000 revoked;

* June 29, 2004; $200,000 revoked;

* July 6, 2004; $38,000 revoked;

* July 28, 2004; $40,000 reprogrammed;

* August 4, 2004; $18,000 reprogrammed;

* August 12, 2004; $125,000 revoked;

* August 24, 2004; $105,000 reprogrammed;

* August 31, 2004; $3,000 reprogrammed;

* September 17, 2004; $8,000 revoked; and: 

* September 29, 2004; $78,000 revoked. 

Similarly, in the San Antonio Channel Improvements construction project 
in Texas, the Corps reprogrammed slightly over $1.9 million into and 
$81,000 out of the project in 15 separate actions in fiscal year 2004. 
Forty percent of the actions took place in the final weeks of the 
fiscal year, with six separate transactions recorded between September 
13 and September 30. 

The just-in-time reprogramming strategy also moved money into and out 
of projects without regard to the relative priorities of the projects. 
During the period of our study, the Corps lacked a set of formal, Corps-
wide priorities for use when deciding to reprogram funds from one 
project to another. Instead, according to the Chief of the Civil Works 
Programs Integration Division, during fiscal years 2003 and 2004, 
reprogramming decisions were left up to the intuition of program and 
project managers at the district level. While this decentralized system 
might have allowed for prioritized decision making at the district 
level, when reprogramming actions occurred across districts or across 
divisions, the Corps lacked any formal system of evaluation as to 
whether funds were moving into or out of high priority projects. The 
lack of a Corps-wide priority system limits its ability to effectively 
manage its appropriations, especially in an era of scarce funding 
resources when choices have to be made between competing needs of donor 
and recipient projects. 

Finally, the Corps' practice of allocating all funds to projects as 
soon as the funds are allotted to the Corps, coupled with the 
reprogramming flexibility provided to the districts, may result in an 
elevated number of reprogramming actions. Typically, once the Corps 
receives appropriated funds from the Congress, the Corps disperses all 
of these funds directly into project accounts at the district level. 
Allocating funding in this manner, according to Corps officials, is 
done to remain consistent with congressional direction. However, 
projects that have experienced delays in the time period between the 
Corps initial budget submittal and the agency's receipt of its 
appropriation may receive more money than they are able to spend. In 
some cases we reviewed, the Corps dispersed an entire fiscal year's 
worth of funding to a project even though they knew that the project 
manager could not spend all of the funding. This type of allotment 
system may result in an elevated number of reprogramming actions. For 
instance, within 2 weeks after the Corps dispersed its fiscal year 2003 
appropriation to specific projects, it made 369 reprogramming actions 
to realign funding in its investigations and construction 
appropriations; within 2 weeks after dispensing fiscal year 2004 
dollars, the Corps made 64 such actions. 

The flexibility provided to district managers once they receive their 
funding may also increase the number of reprogramming transactions. 
Corps reprogramming guidance allows the districts to reprogram funds up 
to a certain amount without notifying division or headquarters staff. 
According to some Corps program managers, the relative ease of 
conducting reprogramming actions at the district level, without the 
need to obtain division or headquarters approval, creates incentives 
for project managers to transfer funds among projects within the 
district even if it creates a greater number of reprogramming actions. 
For example, when project managers have an immediate need for funds, 
they may be more likely to reprogram funds between projects within 
their own district, even if the donor project has a need for funds in a 
few weeks or months, because the guidance allows them to do so. 

The Corps' reprogramming practices place a large demand on the 
administrative resources of the agency. In fiscal year 2003, after 
receiving their appropriated funds from the Congress, the Corps 
conducted at least one reprogramming action every business day of the 
fiscal year except for 4; after receiving their funds in fiscal year 
2004, the Corps conducted at least one reprogramming action on every 
business day of the fiscal year except for 14. Each reprogramming 
action conducted requires the Corps to expend time and personnel 
resources to locate donor projects, file necessary paperwork, and in 
some cases obtain the approval of appropriate Corps staff and, 
possibly, the Congress. In particular, locating sources of donor 
funding is often a time-consuming process, as the project manager 
seeking funding must wait for other project managers to acknowledge 
excess funds and offer them for use on other projects. 

Conclusions: 

The ability to move funds among projects is a useful and necessary 
management tool to adjust project funding to reflect changing 
conditions and needs over the life of a civil works project. For an 
agency like the Corps, which has responsibility for hundreds of 
projects, the ability to reprogram funds, if used effectively, provides 
the flexibility to take funds from a project that cannot spend allotted 
funds because of delays due to factors such as bad weather or labor 
problems and move those funds to a project that has a need for 
additional funding to accelerate or complete ongoing work. However, the 
Corps' reprogramming guidance allows movements of funds by categorizing 
reprogrammings as fund movements that do not count toward notifying the 
Congress. As a result, following its guidance, the Corps is able to 
effect major deviations from the funding direction the Congress 
provided for projects in its conference report and does not have to 
inform the Congress of the changes and the reason for the changes. 
Because the Corps' reprogramming reflects the direction and guidance 
provided by the appropriations committees and this guidance has changed 
over time, we believe that the Corps needs to reach agreement with the 
Congress on what types and levels of reprogramming actions are 
appropriate for the Corps to conduct without congressional 
notification. 

Reprogramming has become the Corps' routine way of managing project 
funds, and the Corps has used reprogramming as a substitute for an 
effective and fiscally prudent financial planning, management, and 
priority-setting system for its Civil Works program. The Corps 
allocates all funding to the projects, on an annual basis, at the 
beginning of the year and has no available means, other than 
reprogramming, to adjust project funding as circumstances change during 
the year. As a result, reprogramming has been used extensively for 
moving funds among projects in an environment where most projects have 
unmet funding needs and very few have excess funding. In addition, 
there is no formal system to prioritize potential donor or recipient 
projects and no financial planning occurs to monitor project schedules 
and progress. Instead, decisions are made instantly to meet immediate 
funding needs. Consequently, funds are frequently moved from projects 
that have or will have the need for those funds in the not too distant 
future and are shifted to other projects, some which have funding needs 
and some that do not. 

Recommendations for Executive Action: 

To eliminate the burden of excessive reprogramming actions and to 
provide better financial management of projects, we recommend that the 
Secretary of Defense direct the Commanding General and Chief of 
Engineers of the U.S. Army Corps of Engineers to take the following 
five actions: 

* work with congressional committees to provide meaningful and 
consistent guidance for the investigations, construction, and operation 
and maintenance appropriations for what actions count as reprogrammings 
and what reporting thresholds should apply on a program and project 
basis;

* develop a financial planning and management system for the 
investigations, construction, and operation and maintenance 
appropriations that, at a minimum,

* changes the way the Corps allocates funds from an annual basis to a 
more frequent basis that reflect actual schedule and project 
performance;

* periodically reviews project schedules and performance and revises 
funding allocations as needed; and: 

* develops and implements criteria for setting reprogramming 
priorities; and: 

* provide direction and training to change the culture prevalent 
throughout the Corps that reprogramming is an acceptable, routine 
financial management practice and instead place greater emphasis on the 
use of financial planning approaches and priority-setting mechanisms 
for managing project funding. 

Agency Comments and Our Evaluation: 

We provided a draft of this report to the Department of Defense for its 
review and comment. The Department stated that the report was very 
constructive and concurred with four of the five recommendations. 
Specifically, the Department concurred with the recommendation that the 
Corps work with congressional committees to provide meaningful and 
consistent guidance for the investigations, construction, and operation 
and maintenance appropriations as to which actions count as 
reprogrammings and what reporting thresholds should apply on a program 
and project basis. The Department said the Corps is preparing an 
Engineer Circular that will address the reprogramming direction 
provided in the House report accompanying the fiscal year 2005 
appropriations for energy and water development. The Department also 
said that the Corps is coordinating with the appropriate House and 
Senate subcommittees and the Engineer Circular is scheduled to be 
issued in the first quarter of fiscal year 2006. 

The Department concurred with our recommendation that the Corps develop 
a financial planning and management system for the investigations, 
construction, and operation and maintenance appropriations that 
periodically reviews project schedules and performance and revises 
funding allocations as needed. The Department said that during the 
first quarter of fiscal year 2006, the Corps intends to institute 
improvements in project scheduling to provide more reliable estimates 
of funding capabilities and to emphasize periodic reviews of project 
schedules, performance, and funding allocations. 

The Department concurred with our recommendation that the Corps develop 
a financial planning and management system for the investigations, 
construction, and operation and maintenance appropriations that 
develops and implements criteria for setting reprogramming priorities. 
The Department said that the Engineer Circular to be issued in the 
first quarter of fiscal year 2006 will include criteria to prioritize 
reprogramming actions. 

The Department concurred with our recommendation that the Corps provide 
direction and training to change the culture prevalent throughout the 
Corps that reprogramming is an acceptable, routine financial management 
practice and instead place greater emphasis on the use of financial 
planning approaches and priority-setting mechanisms for managing 
project funding. The Department said that the forthcoming Engineer 
Circular and subsequent training of project managers will strengthen 
limits on reprogramming and ensure understanding of those limits. 

Regarding our recommendation that the Corps develop a financial 
planning and management system for the investigations, construction, 
and operation and maintenance appropriations that changes the way the 
Corps allocates funds from an annual basis to a more frequent basis 
that reflects actual schedule and project performance, the Department 
did not concur. The Department said that it is important that the Corps 
continue to allocate all funds provided by the Congress for each 
project and that any deviation from that amount would be regarded as a 
reprogramming and would not reflect the intent of the Congress. The 
Department also said that withholding funds from the initial allocation 
would add administrative burden, increase uncertainty in execution, and 
would not aid in scheduling and schedule review. 

We disagree with the Department's views on the effects of changing the 
Corps allocation of funds from an annual basis to a more frequent basis 
during the fiscal year. While the conference report includes amounts 
for each project and that amount does reflect the intent of the 
Congress, changes often occur in the funding needs and project 
expenditure capabilities from the time the Corps submits its budget 
estimates until the appropriation is received 18 or more months later. 
As a result, when the appropriation is received, projects may not need 
the amount of funds included in the conference report or may need 
additional funds. Our recommendation would allow the Corps to make 
these known needed changes before allocating all funds to a project. 
This would serve to streamline the process and eliminate the 
administrative burden of making project funding allocations that the 
Corps knows it is going to reallocate through reprogramming actions 
almost immediately after the initial allocations are made. Providing 
periodic allocations of funds during the year, especially when coupled 
with reviews of project schedules, performance, and fund allocations 
and the development and implementation of criteria for setting 
reprogramming priorities -which the Department said the Corps will 
implement -should allow the Corps to better spend its limited funds in 
accordance with the intent of the Congress. Use of these tools will 
allow the Corps to allocate funds based on the most recent project 
information to those projects with the highest priority and the most 
immediate need. We also disagree that the use of periodic allotments 
would result in uncertainty in execution. Instead, periodic allocation 
of funds would provide increased certainty in execution of projects 
that needed funds and would not affect the execution of projects that 
did not have a current need for funds. 

In addition to the Department of Defense's overall comments on our 
draft report (see app. IV for the full text of the Department's 
comments), the Corps provided a number of technical comments and 
clarifications, which we incorporated in this report as appropriate. 

As arranged with your offices, unless you publicly announce its 
contents earlier, we plan no further distribution of this report until 
30 days after the date of this report. At that time, we will send 
copies of the report to interested congressional committees, the 
Commanding General and Chief of Engineers of the U.S. Army Corps of 
Engineers, and the Director of the Office of Management and Budget. We 
will make copies available to others on request. In addition, this 
report will be available at no charge on the GAO Web site at 
[Hyperlink, http://www.gao.gov]. 

If you or your staff have questions about this report, please call me 
at (202) 512-3841 or contact me at [Hyperlink, mittala@gao.gov]. 
Contact points for our Offices of Congressional Relations and Public 
Affairs may be found on the last page of this report. Key contributors 
to this report are listed in appendix V. 

Signed by: 

Anu K. Mittal: 
Director, Natural Resources and Environment: 

[End of section]

Appendixes: 

Appendix I: Scope and Methodology: 

To determine the extent to which the Corps reprogrammed appropriated 
funds among investigations, construction, and operation and maintenance 
projects in fiscal years 2003 and 2004, we obtained relevant funding 
and project data from the Corps. However, the Corps could not provide 
data about reprogramming of operation and maintenance project funds. We 
determined, based on written documentation, interviews with Corps 
officials, and electronic data testing, that the data were sufficiently 
reliable for our purposes. 

To determine if the Corps followed internal guidance and congressional 
direction when reprogramming funds and why the Corps conducted 
reprogramming funds, we obtained the Corps' internal guidance for 
reprogramming and congressional reports and correspondence that 
contained direction for conducting reprogramming. We selected four 
Corps divisions randomly with probabilities proportional to the number 
of projects and judgmentally selected one district from each of those 
divisions for review. The divisions and districts selected were Great 
Lakes & Ohio River (Louisville District), North Atlantic (New York 
District), Northwestern (Portland District), and Southwestern (Fort 
Worth District). Within the four districts, we randomly selected a 
total of 271 projects from the population of investigations, 
construction, and operation and maintenance projects that had funds 
reprogrammed during fiscal years 2003 and 2004. For the selected 
projects, we reviewed project files and held discussions with managers 
to obtain background information on the project and information on the 
amount, date, and reason for each reprogramming. File information was 
entered into a data collection instrument to ensure uniformity. This 
information was entered into a spreadsheet for analysis. The 
spreadsheet was independently verified with the data collection 
instruments. We compared the Corps' reprogramming activities for each 
selected project to the internal guidance and congressional direction 
that was in effect at the time the reprogramming was conducted. 

To determine how effective the Corps' reprogramming strategy was in 
managing appropriated funds, we reviewed the results of our sample 
analysis and discussed those results with program managers. We also 
discussed the Corps' financial management strategy with program 
managers at Corps headquarters, division offices, and district offices 
and with individual project managers. 

[End of section]

Appendix II: Reprogramming Guidance Used by the Corps: 

[See PDF for image]

[End of figure]

[End of section]

Appendix III: Projects with Reprogrammings That Did Not Follow Corps 
Guidance: 

Fund Movements Conducted under ER 11-2-201 (October 1, 2002, to May 26, 
2004): 

Green and Barren Rivers Navigation Disposition in Kentucky: 

The cumulative threshold amount for notifying the Congress was $25,000 
for this investigations project. On April 22, 2003, $25,000 was 
reprogrammed into the project. On April 28, 2003, another $25,000 was 
reprogrammed into the project, exceeding the cumulative threshold. The 
Corps did not notify the Congress of its intention to reprogram the 
funds in excess of the threshold. Corps officials explained that they 
made a mistake and did not initially realize that the threshold had 
been exceeded. When the error was realized, the Corps revoked $25,000 
on May 29, 2003, to undo the previous error. 

Fund Movements Conducted under Guidance Based on the Direction Provided 
in the House Report 108-554 (May 27 to September 30, 2004): 

New York City Watershed in New York: 

The single action threshold was $300,000 for this construction project. 
On September 20, 2004, the Corps revoked $800,000 exceeding the single 
action threshold of $300,000. The Corps notified the Congress of its 
intention to reprogram the $800,000, on September 24, 2004, 4 days 
after the funds had been moved. 

McAlpine Locks and Dam in Kentucky and Indiana: 

The single action threshold for this construction project was 
$7,301,200 and the cumulative threshold was $4 million. (In this case, 
because of the size of the project, the threshold calculations resulted 
in a higher single action threshold than a cumulative threshold.) On 
August 6, 2004, the Corps moved $5.3 million into the project using its 
accelerated contractor earnings authority. However, the accelerated 
contractor earnings authority only allows the Corps to move up to $5 
million and it must be used for settling a contractor's claim, 
increased contractor earnings due to accelerated rate of operations, or 
real estate deficiency judgment. In addition to exceeding their 
authority to move funds under this provision, Corps officials told us 
that the funds were not moved for any of the authorized purposes. 
Rather, the funds were used to continue funding a contract. The Corps 
had awarded a contract for about $80 million for fiscal year 2004, but 
received only about $27 million for the project. To avoid a work 
stoppage, possible contractor claims, and/or possible interest 
payments, the Corps moved a large amount of funds into the project, 
including the $5.3 million. 

Ramapo River at Oakland in New Jersey: 

The single action threshold for this construction project was $311,800 
and the cumulative threshold was $4 million. On September 1, 2004, the 
Corps revoked $600,000; on September 20, 2004, the Corps revoked 
$1,700,000; and on September 29, 2004, the Corps revoked $600,000. All 
these actions exceeded the single action threshold. The Corps did not 
notify the Congress of their intention to reprogram the funds in excess 
of the thresholds on September 1 and 24. A letter was sent to the 
Congress for the September 20, 2004, action; however, the letter was 
sent on September 24, 2004, after the funds had been moved. 

Ohio River Flood Protection in Indiana: 

The single action threshold for this construction project was $430,000 
and the cumulative threshold was $4 million. On June 28, 2004, the 
Corps revoked $500,000, exceeding the single action threshold of 
$430,000. The Corps did not notify the Congress of its intention to 
reprogram the funds in excess of the threshold. Corps officials told us 
that the action was processed at the district and they were confused 
about the procedure. 

New York and New Jersey Harbor: 

The single action threshold for this construction project was 
$22,303,000 and the cumulative threshold was $4 million. (In this case, 
because of the size of the project, the threshold calculations result 
in a higher single action threshold than a cumulative threshold.) In 
2004, in 10 different actions, the Corps moved a total of $82,559,000 
in and out of the project. Specific actions that exceeded the $4 
million threshold occurred on June 17, 2004, ($6,900,000 revoked), June 
22, 2004, ($8,587,000 revoked), June 24, 2004, ($10,000,000 revoked) 
and on August 6, 2004, ($8,500,000 revoked). The Corps sent 
notification to the Congress for the June 24, 2004, action on May 13, 
2004. Letters were also sent for the other actions; however, these 
letters were sent after the funds had been moved. The letter for the 
June 22, 2004, action was sent on June 29, 2004. The letters for the 
June 17, 2004, and the August 6, 2004, actions were sent on September 
24, 2004. 

Bonneville Powerhouse Phase 1 in Oregon and Washington: 

The single action threshold for this construction project was $302,000 
and the cumulative threshold was $4 million. On May 28, 2004, the Corps 
restored $332,000 prior year savings and slippage, exceeding the single 
action threshold of $302,000. The Corps did not notify Congress of 
their intention to reprogram the funds in excess of the threshold. 
Corps headquarters officials told us that the action was processed at 
the district and they were confused about the procedure while district 
officials said that headquarters approved the action. 

Plattsburgh Harbor in New York: 

The single action threshold for this operation and maintenance project 
was $438,240 and the cumulative threshold was $4 million. On August 16, 
2004, the Corps revoked $625,000, exceeding the single action threshold 
of $438,240. The Corps did not notify the Congress of their intention 
to reprogram the funds in excess of the threshold. Corps officials told 
us that the action was processed at the district and they were confused 
about the procedure. 

[End of section]

Appendix IV: Comments from the Department of Defense: 

DEPARTMENT OF THE ARMY: 
OFFICE OF THE ASSISTANT SECRETARY: 
CIVIL WORKS: 
108 ARMY PENTAGON: 
WASHINGTON DC 20310-0108: 

23 AUG 2005: 

Ms. Anu K. Mittal: 
Director, Defense Capabilities and Management: 
U.S. Government Accountability Office: 
441 G Street, N.W. 
Washington, D.C. 20548: 

Dear Ms. Mittal: 

This is the Department of Defense (DoD) response to the GAO draft 
report, `ARMY CORPS OF ENGINEERS: Improved Planning and Financial 
Management Should Replace Reliance on Reprogramming Actions to Manage 
Project Funds,' dated August 1, 2005, (GAO Code 360533/GAO-05-946). 

The draft report is very constructive. DoD concurs with four 
recommendations and non-concurs with one recommendation (see 
enclosure). I look forward to GAO's completion and transmittal of the 
report. 

Very truly yours,

Signed for: 

John Paul Woodley, Jr. 
Assistant Secretary of the Army (Civil Works): 

Enclosure: 

GAO DRAFT REPORT -DATED AUGUST 1, 2005 GAO CODE 360533/GAO-05-946: 

"ARMY CORPS OF ENGINEERS: IMPROVED PLANNING AND FINANCIAL MANAGEMENT 
SHOULD REPLACE RELIANCE ON REPROGRAMMING ACTIONS TO MANAGE PROJECT 
FUNDS"

DEPARTMENT OF DEFENSE COMMENTS TO THE RECOMMENDATIONS: 

RECOMMENDATION 1: The GAO recommended that the Secretary of Defense 
direct that the Commanding General and Chief of Engineers of the U.S. 
Corps of Engineers work with congressional committees to provide 
meaningful and consistent guidance for the general investigations, 
construction general, and operation and maintenance appropriations for 
what actions count as reprogrammings and what reporting thresholds 
should apply on a program basis. (p. 29/GAO Draft Report): 

DOD RESPONSE: Concur. The Corps is preparing an Engineer Circular on 
reprogramming to address the direction in House Report 108-792, the 
Conference Report accompanying Fiscal Year 2005 appropriations for 
energy and water development. Coordination with the House and Senate 
subcommittees on energy and water development appropriations is under 
way. The Engineer Circular is scheduled for publication in the first 
quarter of FY 2006. 

RECOMMENDATION 2: The GAO recommended that the Secretary of Defense 
direct that the Commanding General and Chief of Engineers of the U.S. 
Corps of Engineers develop a financial planning and management system 
for the general investigations, construction general, and operation and 
maintenance appropriations that changes the way the Corps allocates 
funds from an annual basis to a more frequent basis that reflect actual 
schedule and project performance. (p. 29/GAO Draft Report): 

DOD RESPONSE: Non-Concur. It is appropriate that, upon enactment and 
apportionment of funds, the Corps continue to allocate to each project, 
program, or activity all funds provided by Congress for that project, 
program, or activity. Any deviation would be identified as a 
reprogramming. This practice ensures that the initial allocations 
reflect the intent of Congress and provide a baseline for tracking and 
reporting reprogramming activity. The Corps currently uses this 
practice in response to the direction in the FY 2005 Conference Report. 
To the extent that withholding funds from initial allocation would 
facilitate the allocation of funds to projects, programs, and 
activities other than as intended by Congress, that is, reprogramming, 
it negates the implied rationale for the procedure. In addition, 
withholding funds from initial allocation would add administrative 
burden and increase uncertainty in execution, but would not aid in 
scheduling and schedule review. 

RECOMMENDATION 3: The GAO recommended that the Secretary of Defense 
direct that the Commanding General and Chief of Engineers of the U.S. 
Corps of Engineers develop a financial planning and management system 
for the general investigations, construction general, and operation and 
maintenance appropriations that periodically reviews project schedules 
and performance and revises funding allocations as needed. (p. 29/GAO 
Draft Report): 

DOD RESPONSE: Concur. Corps management intends to institute 
improvements in project scheduling in order to provide more reliable 
estimates of current year and future year funding capabilities and to 
emphasize periodic reviews of project schedules, performance, and fund 
allocations. These improvements are scheduled to be instituted in the 
first quarter of FY 2006. 

RECOMMENDATION 4: The GAO recommended that the Secretary of Defense 
direct that the Commanding General and Chief of Engineers of the U.S. 
Corps of Engineers develop a financial planning and management system 
for the general investigations, construction general, and operation and 
maintenance appropriations that develops and implements criteria for 
setting reprogramming priorities. (p. 29/GAO Draft Report): 

DOD RESPONSE: Concur. The forthcoming Engineer Circular on 
reprogramming will strengthen limits on reprogramming, and will include 
improved decision rules and criteria to prioritize reprogramming 
actions. For instance, reprogramming actions will be limited to those 
that revoke genuinely surplus funds and are needed to support 
forthcoming obligations, and decision criteria will emphasize 
restoration of revoked funds, among other things. The Engineer Circular 
is scheduled for publication in the first quarter of FY 2006. 

RECOMMENDATION 5: The GAO recommended that the Secretary of Defense 
direct that the Commanding General and Chief of Engineers of the U.S. 
Corps of Engineers provide direction and training to change the culture 
prevalent throughout the Corps that reprogramming is an acceptable, 
routine financial management practice and instead places greater 
emphases on the use of financial planning approaches and priority-
setting mechanisms for managing project funding. (p. 29/GAO Draft 
Report): 

DOD RESPONSE: Concur. Corps management intends to institute 
improvements in project scheduling in order to provide more reliable 
estimates of current year and future year funding capabilities and to 
emphasize periodic reviews of project schedules, performance, and fund 
allocations. The forthcoming Engineer Circular on reprogramming will 
strengthen limits on reprogramming, and will include improved decision 
rules and criteria to prioritize reprogramming actions. For instance, 
reprogramming actions will be limited to those that revoke genuinely 
surplus funds and are needed to support forthcoming obligations, and 
decision criteria will emphasize restoration of revoked funds, among 
other things. Once Corps management has approved the Engineer Circular 
on reprogramming, Corps-wide training of program managers will be 
conducted to ensure universal understanding of reprogramming in 
accordance with the Engineer Circular. Training topics will include the 
improved project estimating, scheduling, and schedule review practices, 
the strengthened reprogramming limitations, and the improved priority-
setting decision rules and criteria. Training is scheduled to begin in 
the second quarter of FY 2006. 

[End of section]

Appendix V: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Anu K. Mittal (202) 512-3841: 

Staff Acknowledgments: 

In addition to the individual named above, Edward Zadjura, James D. 
Ashley, Kenneth E. Lightner Jr., John Mingus, Matthew Reinhart, 
Elizabeth Repko, Carol Herrnstadt Shulman, and Barbara R. Timmerman 
made contributions to this report. 

(360533): 

FOOTNOTES

[1] In this report, the terms "investigations" and "construction" are 
used to describe the appropriation accounts entitled "general 
investigations" and "construction, general," respectively. 

[2] Investigations are studies to determine the need, engineering 
feasibility, economic justification, and the environmental and social 
suitability of a project. Investigations also include preconstruction, 
engineering, design work, data collection, and interagency coordination 
and research activities. Construction projects are construction and 
major rehabilitation projects that relate to navigation, flood control, 
water supply, hydroelectric power, and environmental restoration. 
Operation and maintenance projects include the preservation, operation, 
maintenance, and care of existing river and harbor, flood control, and 
related activities at the projects that the Corps operates and 
maintains. 

[3] In this report, we calculate the dollar amount of reprogramming 
actions as the total amount of funds moved into and out of a project. 
For instance, if $10,000 was moved into a project and $5,000 was 
subsequently moved out in the same fiscal year, we determined the total 
dollar amount of reprogramming for that project to be $15,000. 

[4] Part of the appropriation the Corps receives in its appropriation 
act is designated or "earmarked" in the act itself for specific 
projects. In general, funds that are earmarked to specific projects are 
not available for reprogramming and savings and slippage is not 
deducted from project funding. 

[5] In most cases, the committee review process is nonstatutory and 
derives from instructions in committee reports, hearings, and other 
correspondence. 

[6] Congressional committee instructions to the Corps to reprogram 
construction project funds were first contained in the House and Senate 
reports on the 1957 Public Works Appropriation Bill. Reprogramming 
instructions have been included many times since in subsequent 
congressional reports. Congressional committee instructions to the 
Corps to reprogram investigations and operation and maintenance project 
funds were established by informal agreement and precedent over the 
years. It was first formally addressed by the Congress in the Senate 
report on the 1980 Energy and Water Development Appropriations Bill. 

[7] Sequestration is the cancellation, in accordance with the Budget 
Enforcement Act, of budgetary resources provided by discretionary 
appropriations or direct spending law. A deferral is a postponement of 
budget authority for up to 1 year. A rescission, which must be approved 
by the Congress, is a cancellation of previously approved budget 
authority. 

[8] The Corps' reprogramming guidance changed during the fiscal year 
2003 through 2004 timeframe of our review, and the guidance contains 
different, specific criteria for investigations, construction, and 
operation and maintenance projects. However, the guidance for all 
projects during this timeframe generally contains limitations on the 
amount of funds that can be reprogrammed by Corps districts and 
divisions and instructions for notifying the Congress of the Corps' 
intention to reprogram funds that exceed a specified amount. 

[9] The Continuing Authorities Program is a program that allows the 
Corps to conduct small water resource projects without specific 
congressional authorization. Included in this program are flood 
control, beach erosion, shoreline protection, and environmental 
improvement projects that range from $500,000 to $5 million. 

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site (www.gao.gov) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office

441 G Street NW, Room LM

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm

E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director,

NelliganJ@gao.gov

(202) 512-4800

U.S. Government Accountability Office,

441 G Street NW, Room 7149

Washington, D.C. 20548: