This is the accessible text file for GAO report number GAO-12-662R entitled 'DOD Financial Management: Improvements Needed in Prompt Payment Monitoring and Reporting' which was released on June 26, 2012. This text file was formatted by the U.S. Government Accountability Office (GAO) to be accessible to users with visual impairments, as part of a longer term project to improve GAO products' accessibility. Every attempt has been made to maintain the structural and data integrity of the original printed product. Accessibility features, such as text descriptions of tables, consecutively numbered footnotes placed at the end of the file, and the text of agency comment letters, are provided but may not exactly duplicate the presentation or format of the printed version. The portable document format (PDF) file is an exact electronic replica of the printed version. We welcome your feedback. Please E-mail your comments regarding the contents or accessibility features of this document to Webmaster@gao.gov. This is a work of the U.S. government and is not subject to copyright protection in the United States. It may be reproduced and distributed in its entirety without further permission from GAO. Because this work may contain copyrighted images or other material, permission from the copyright holder may be necessary if you wish to reproduce this material separately. GAO-12-662R: United States Government Accountability Office: Washington, DC 20548: June 26, 2012: The Honorable Carl Levin: Chairman: The Honorable John McCain: Ranking Member: Committee on Armed Services: United States Senate: Subject: DOD Financial Management: Improvements Needed in Prompt Payment Monitoring and Reporting: The Prompt Payment Act, as amended, requires executive-branch agencies, including the Department of Defense (DOD), to pay late- payment penalties when they do not pay their invoices for commercial payments on time. DOD's Prompt Payment Act implementing regulations provide that DOD components should take advantage of discounts offered when a contract or invoice allows an economically justified discount for early payment.[Footnote 1] Given concern that DOD sometimes incurred late-payment penalties and had not taken full advantage of prompt-payment discounts, the committee report accompanying the 2012 national defense authorization legislation directed that GAO review and report on the issue.[Footnote 2] To address this requirement, and as agreed upon with your offices, our objectives were to (1) determine whether DOD's process for monitoring and reporting on its late-payment penalties and discounts lost accurately reflected the extent of such penalties paid and discounts lost and (2) report on any causes DOD identified for incurring late-payment penalties and forgoing prompt- payment discounts. To address our first objective, we analyzed applicable laws, regulations, and DOD documents to identify requirements related to prompt payments, reviewed documentation, and interviewed officials to obtain explanations and clarifications on DOD's process and controls for tracking and reporting on late-payment penalties and discounts lost across DOD. To address our second objective, we interviewed DOD officials and reviewed documentation, including the problems and corrective actions DOD reported on its financial operations metrics briefings, to determine DOD's identified causes of late-payment penalties incurred and discounts lost. We conducted this performance audit from October 2011 to June 2012 in accordance with generally accepted government auditing standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based on our audit objectives. Results in Brief: We found that while DOD has a process in place for monitoring and reporting on late-payment penalties, this process has significant flaws and omissions that result in incomplete and inaccurate data, thereby limiting the effectiveness of the process. Specifically, DOD's performance measure, or metric, for late-payment penalties did not include about $54 billion of commercial payments subject to the Prompt Payment Act, and DOD did not assess the data for accuracy or completeness. In addition, at the time of our review, DOD was not monitoring or reporting on discounts lost across the department because, DOD officials stated, the metric had consistently met its goal. The deficiencies we found in DOD's process for monitoring and reporting on late-payment penalties and discounts lost significantly increase the risk to the accuracy and completeness of reported data, thus preventing DOD officials and congressional oversight committees from obtaining the reliable and comprehensive data they need for assessing the extent of any issues concerning late-payment penalties and discounts lost across DOD. According to DOD officials and reports, a major contributor to late-payment penalties incurred and discounts lost was the late receipt of documents necessary to validate receipt and acceptance of goods or services and make payments. We are recommending that DOD establish procedures for identifying all DOD systems that process commercial payments, validating completeness and accuracy of late-payment penalty metric data, and monitoring discounts lost. In commenting on a draft of our report, DOD concurred with our recommendations and cited planned corrective actions to address the issues that gave rise to our recommendations. Background: DOD makes most of its commercial payments to vendors and contractors through systems operated by the Defense Finance and Accounting Service (DFAS), the finance and accounting organization for DOD.[Footnote 3] In general, such payments are made after matching an invoice with (1) a signed contract, purchase order, or other contractual document, to ensure that the purchase of goods or services was authorized; (2) a receiving/acceptance report, to ensure that the goods or services ordered have been received or accepted, or both; and (3) the official accounting records, to ensure that funds have been obligated and are available for use. The office of the Deputy Chief Financial Officer (DCFO) monitors DOD performance measures and various aspects of DOD's financial operations through its monthly financial operations metrics, including the ratio of late-payment penalties paid per million dollars in payments. [Footnote 4] As part of its metrics process, each year the DCFO works with DFAS to establish goals--including Prompt Payment Act goals-- towards improved efficiencies, financial stewardship, and productivity in its financial operations. DFAS compiles the results of its financial operations metrics (metric data), and each month the DCFO tracks the metric data--including data on late-payment penalties--and compares them against DOD's goals. The metric data are scored and receive a "green" rating when they meet the goal, and a "yellow" or "red" rating--depending on severity--when they do not. Each month, DFAS officials, the DCFO, and other DOD officials meet to discuss DOD- wide metric data that received a "red" or "yellow" rating, determine the causes for metric data that do not meet the goals, and agree on any corrective actions to address them. Metric data that meet or exceed the goals and receive a "green" rating are generally not discussed at these monthly meetings. Incomplete and Inaccurate Data Undermine DOD's Prompt Payment Act Monitoring: In our review of DOD's monitoring of payments related to the Prompt Payment Act, we found deficiencies in the completeness and accuracy of the data used to monitor and report on late-payment penalties. The late-payment penalty metric data did not include nine systems that process commercial payments, and the metric data had not been validated. Regarding discounts lost, we found that monitoring had not been conducted DOD-wide since fiscal year 2007 and that there were deficiencies in the completeness of the data DOD provided us from systems within DOD's components. Deficiencies in the Monitoring Process for Late-Payment Penalties: We found deficiencies in both the completeness and accuracy of the data the DCFO uses to monitor and report on late-payment penalties. These deficiencies limit the effectiveness of DOD's monitoring and reporting process. According to DCFO reports, the ratio of late- payment penalties paid to million dollars of invoices paid has decreased 81 percent since 2001, from an average of $343 in penalties in fiscal year 2001 to $65 in fiscal year 2011 (see figure 1). Figure 1: Late-Payment Penalties Paid per Million Dollars of Invoices Paid (DFAS Systems Only), Fiscal Years 2001-2011: [Refer to PDF for image: line graph] Fiscal year: 2001; Dollars per million dollars of invoices paid: $343. Fiscal year: 2002; Dollars per million dollars of invoices paid: $224. Fiscal year: 2003; Dollars per million dollars of invoices paid: $160. Fiscal year: 2004; Dollars per million dollars of invoices paid: $138. Fiscal year: 2005; Dollars per million dollars of invoices paid: $137. Fiscal year: 2006; Dollars per million dollars of invoices paid: $124. Fiscal year: 2007; Dollars per million dollars of invoices paid: $140. Fiscal year: 2008; Dollars per million dollars of invoices paid: $143. Fiscal year: 2009; Dollars per million dollars of invoices paid: $127. Fiscal year: 2010; Dollars per million dollars of invoices paid: $79. Fiscal year: 2011; Dollars per million dollars of invoices paid: $65; $19 million[A]. Source: DOD. Note: Data are from September 2011 financial operations metric briefing. [A] Total dollar amount for fiscal year 2011 based on DFAS-provided data does not include late-payment penalties for non-DFAS systems. [End of figure] While these data show a significant drop in late-payment penalties as a proportion of invoice amounts paid, in our analysis of DOD data used to support this reporting, we found that the trend may be misleading because in compiling the late-payment penalty metric data, DFAS did not consider late-payment penalties on about $54 billion in payments subject to the Prompt Payment Act from nine systems (see table 1). These systems were all systems that process commercial payments. According to DOD officials, the nine systems we identified whose data were not considered in the late-payment penalty metric are systems run and operated by DOD components and not DFAS. Table 1: DOD Systems and Payment Amounts Considered and Not Considered in the Late-Payment Penalty Metric, Fiscal Year 2011: Dollars in millions: System name: Mechanization of Contract Administration Services (MOCAS); Payments: considered in late-payment penalty metric (from DFAS systems)[A]: $161,298.6. System name: Computerized Accounts Payable System-Windows (CAPS-W); Payments: considered in late-payment penalty metric (from DFAS systems)[A]: $39,525.4. System name: U.S. Army Corps of Engineers Financial Management System (CEFMS); Payments not considered in late-payment penalty metric (from nine non- DFAS systems)[A]: $28,047.9. System name: Enterprise Business System (EBS); Payments: considered in late-payment penalty metric (from DFAS systems)[A]: $23,721.9. System name: Automated Voucher Examining and Disbursing System (AVEDS); Payments: considered in late-payment penalty metric (from DFAS systems)[A]: $18,396.7. System name: Integrated Accounts Payable (IAPS); Payments: considered in late-payment penalty metric (from DFAS systems)[A]: $18,388.0. System name: OnePay (OP); Payments: considered in late-payment penalty metric (from DFAS systems)[A]: $18,104.1. System name: TRICARE Oracle Federal Financials (OFF); Payments not considered in late-payment penalty metric (from nine non- DFAS systems)[A]: $16,869.8. System name: Standard Automated Voucher Examination System (SAVES); Payments: considered in late-payment penalty metric (from DFAS systems)[A]: $6,056.8. System name: Defense Enterprise Accounting and Management System (DEAMS); Payments not considered in late-payment penalty metric (from nine non- DFAS systems)[A]: $4,374.3. System name: General Fund Enterprise Business System (GFEBS); Payments not considered in late-payment penalty metric (from nine non- DFAS systems)[A]: $2,528.7. System name: Transportation Financial Management System (TFMS); Payments: considered in late-payment penalty metric (from DFAS systems)[A]: $2,333.1. System name: Military Sealift Command Financial Management System (MSC- FMS); Payments not considered in late-payment penalty metric (from nine non- DFAS systems)[A]: $1,625.8. System name: Financial Accounting and Budget System (FABS); Payments: considered in late-payment penalty metric (from DFAS systems)[A]: $1,119.7. System name: Defense Agencies Initiative (DAI); Payments not considered in late-payment penalty metric (from nine non- DFAS systems)[A]: $474.3. System name: Nonappropriated Fund Information Standard System (NAFISS); Payments not considered in late-payment penalty metric (from nine non- DFAS systems)[A]: $370.8. System name: Transportation Management System (TMS); Payments not considered in late-payment penalty metric (from nine non- DFAS systems)[A]: $119.1. System name: Computerized Accounts Payable System-Clipper (CAPS-C); Payments: considered in late-payment penalty metric (from DFAS systems)[A]: $7.3. System name: Navy Enterprise Resource Planning (ERP) System; Payments not considered in late-payment penalty metric (from nine non- DFAS systems)[A]: [B]. System name: Total[C]; Payments: considered in late-payment penalty metric (from DFAS systems)[A]: $288,951.5; Payments not considered in late-payment penalty metric (from nine non- DFAS systems)[A]: $54,410.6. Source: GAO analysis of DOD data. [A] Commercial payments reported by DOD as subject to the Prompt Payment Act. [B] Navy ERP could not provide the amount of commercial payments subject to the Prompt Payment Act because it does not systemically identify whether commercial payments are subject to the Prompt Payment Act. [C] Due to rounding, the total amounts do not equal the sum of the individual system amounts in the table. [End of table] While DFAS reported a total of about $19 million in late-payment penalties for fiscal year 2011 (see figure 1), these data are incomplete because the DCFO did not consider the complete population of commercial payments when reporting late-payment penalties in fiscal year 2011. For example, DOD provided us information that indicates that the nine non-DFAS systems we identified incurred almost $2 million in late-payment penalties in 2011, bringing fiscal year 2011 late-payment penalties to almost $21 million. Although DOD took steps to include some of these commercial payments in the data for its late- payment penalty metric during the course of our work,[Footnote 5]additional payments and late-payment penalties that are associated with non-DFAS systems may still be unidentified. We also found--and DOD officials confirmed--that the DCFO does not assess its late-payment penalty metric data for accuracy or completeness. Standards for Internal Control in the Federal Government states that for organizational performance measures, controls should be in place to validate the propriety and integrity of the measures. [Footnote 6]Further, the DCFO handbook states that successful measures need to be reliable, and should be verified to ensure that they represent the desired data. Although the late-payment penalty amounts provided to us are relatively small compared to DOD's total commercial payment amounts, we are unable to conclude as to the completeness and accuracy of the $21 million in late-payment penalties due to questions about the completeness of the population of systems that process commercial payments and the lack of validation and verification control. In addition, these issues prevent DOD officials and congressional oversight from obtaining reliable and comprehensive data on the extent of any issues concerning late-payment penalties across DOD. DCFO Is Not Monitoring Discounts Lost DOD-Wide: The DCFO has not monitored discounts lost at the DOD-wide level since fiscal year 2007 and does not have procedures to evaluate the risk and magnitude of discounts lost to determine whether it should resume monitoring discounts lost in DOD-wide metrics if the risk increases beyond an acceptable level. Standards for Internal Control in the Federal Government states that separate evaluation of controls is useful, and that the scope and frequency of such evaluations should depend primarily on risk assessments and the effectiveness of ongoing monitoring procedures. Officials stated the DCFO ceased monitoring discounts lost because the metrics consistently delivered results that ranked "green" (i.e., met their goal) and no longer warranted DOD-wide monitoring. However, as reflected in figure 2, we found that the reported discounts-lost metric only met its goal of 4 percent for 2 months in fiscal year 2007. Figure 2: Percentage of the Number of Offered Discounts Lost in Fiscal Year 2007: [Refer to PDF for image: line graph] Percent per million dollars of invoices paid: Date: October 2006; Percentage of discounts lost (by number): 5.5%. Goal rate: 4%. Date: November 2006; Percentage of discounts lost (by number): 4.8%. Goal rate: 4%. Date: December 2006; Percentage of discounts lost (by number): 6.2%. Goal rate: 4%. Date: January 2007; Percentage of discounts lost (by number): 5.4%. Goal rate: 4%. Date: February 2007; Percentage of discounts lost (by number): 3.9%. Goal rate: 4%. Date: March 2007; Percentage of discounts lost (by number): 4.1%. Goal rate: 4%. Date: April 2007; Percentage of discounts lost (by number): 4.5%. Goal rate: 4%. Date: May 2007; Percentage of discounts lost (by number): 3.2%. Goal rate: 4%. Date: June 2007; Percentage of discounts lost (by number): 5.7%. Goal rate: 4%. Date: July 2007; Percentage of discounts lost (by number): 7.7%. Goal rate: 4%. Date: August 2007; Percentage of discounts lost (by number): 7.3%. Goal rate: 4%. Date: September 2007; Percentage of discounts lost (by number): 7.8%. Goal rate: 4%. Source: DOD. Note: Data are from fiscal year 2007 financial operations metric briefings. [End of figure] For the systems it operates, DFAS tracks both the number of discounts lost and the dollar value of the discounts lost, and reports its findings to the managers of DOD activities. While these figures are useful for management, they are not discussed at DFAS's monthly meeting with the DCFO, and thus fall outside of the DCFO's monitoring process. Although the DCFO stopped monitoring discounts lost, DFAS provided us information that indicates the ratios of both the number and dollars of discounts lost have generally been increasing (see fig. 3). Discounts lost, as a percentage of the number of discounts offered, equaled 8 percent in fiscal year 2011, twice the fiscal year 2007 DCFO goal of 4 percent, which was the last goal set by the DCFO for discounts lost. DFAS currently has a goal for the number of discounts lost of 5 percent. The DFAS data further show that although the ratio of the number of discounts lost decreased from fiscal years 2010 to 2011, the ratio of the dollars of discounts lost increased to 25 percent. DFAS currently has a goal for the percentage of discounts lost in dollars of 4 percent. Figure 3: Percentage of the Value and Number of Offered Discounts Lost, Fiscal Years 2005-2011: [Refer to PDF for image: line graph] Fiscal year: 2005; Percentage of discounts lost (by dollars): 12.5%; Percentage of discounts lost (by number): 4.8%. Fiscal year: 2006; Percentage of discounts lost (by dollars): 11.1%; Percentage of discounts lost (by number): 6.9%. Fiscal year: 2007; Percentage of discounts lost (by dollars): 14.7%; Percentage of discounts lost (by number): 5.4%. Fiscal year: 2008; Percentage of discounts lost (by dollars): 18.5%; Percentage of discounts lost (by number): 7.2%. Fiscal year: 2009; Percentage of discounts lost (by dollars): 13.2%; Percentage of discounts lost (by number): 7%. Fiscal year: 2010; Percentage of discounts lost (by dollars): 21.2%; Percentage of discounts lost (by number): 10%. Fiscal year: 2011; Percentage of discounts lost (by dollars): 24.9%; $8 million[A] Percentage of discounts lost (by number): 8.1%; 12,999[A]. Source: DFAS. Note: Data are from DFAS metrics data. [A] Total dollar amount and number of discounts lost for fiscal year 2011 based on DFAS-provided data does not include discounts lost for non-DFAS systems. In addition, the goal amounts for both the percentage of dollars and numbers of discounts lost are not shown because they vary and have not been set or monitored by the DCFO since fiscal year 2007. [End of figure] Although the ratios for discounts lost have generally been increasing, the amount of discounts lost is relatively small compared to DOD's total commercial payment amounts. DFAS provided us information that indicates that there was about $8 million in discounts lost for fiscal year 2011. However, as with the late-payment penalty metric, we found that for discounts lost, DFAS did not include about $78 billion in commercial payments subject to the Prompt Payment Act[Footnote 7] both from systems that it operates and does not operate. DOD-provided information, covering some of the systems not included,[Footnote 8] indicates almost $700,000 in discounts lost in fiscal year 2011, bringing the fiscal year 2011 discounts lost to almost $9 million. However, because DOD has not established procedures to identify and include all systems that process commercial payments, we are unable to conclude as to the completeness and accuracy of the almost $9 million in DOD-identified discounts lost. In addition, these issues prevent DOD officials and congressional oversight committees from obtaining reliable and comprehensive data on the extent of any issues concerning discounts lost across DOD. Absent DOD-wide monitoring of discount information, potential cost savings may be missed. DOD-Reported Causes for Late-Payment Penalties Incurred and Discounts Lost: On the basis of our discussions with DOD officials and our review of reports, we found DFAS's late receipt of necessary documents was a major contributor to late-payment penalties and discounts lost. The documents DOD officials most often cited in this regard were receiving reports, which are used to confirm DOD's receipt or acceptance, or both, of goods or services ordered and which must be submitted to DFAS before payment can be made. DOD officials told us that one of the reasons receiving reports are often late is reports are often mailed by DOD components to DFAS rather than submitted electronically. As part of its metric reporting process, DFAS tracks the reasons for the payment of late-payment penalties on commercial payments that DFAS's systems process. DFAS reported that for the payments it made in fiscal year 2011, 57 percent of the late-payment penalties were due to a delay in DFAS's receiving contract, invoice, and receipt and acceptance information from DOD components, contractors, and vendors, and 23 percent were caused by DFAS processing delays and a backlog of invoices to process. DOD reported that as it continues to deploy the Wide Area Workflow and take other measures, it will see a decline in late-payment penalties because of efficiencies gained with the electronic transmission of contract documents.[Footnote 9] Such efficiencies gained may similarly improve DOD's ability to take advantage of discounts offered and thus realize cost savings. DOD officials stated that contracts containing unclear descriptions of the items being purchased and unclear definitions of units of measure are a significant issue for a relatively few contracts that account for a relatively large amount in late-payment penalties.[Footnote 10] For example, although a contract line-item may describe the unit of measure as "one lot," the lot may consist of a variety of items and quantities delivered over time. DOD officials further stated that multiple contract modifications had resulted in contracts having extremely complex line-item structures, causing invoice processing delays due to difficulties in comparing or associating the contractor invoices to the related contract line-item. The lack of clarity can result in ambiguity regarding both the items to accept and the amount to pay for each delivery, thereby causing DOD to incur late-payment penalties and miss opportunities to obtain discounts. DOD officials told us they were addressing these issues by providing training on writing contracts and issuing DOD-wide memorandums requiring contracts to clearly define the quantity and unit of measure of the product to be delivered. Conclusions: Although the amounts DOD provided us for late-payment penalties and discounts lost appear to be relatively small compared to the amount of DOD-reported commercial payments subject to the Prompt Payment Act, deficiencies in DOD's monitoring process prevent it from comprehensively and reliably reporting the magnitude of late-payment penalties and discounts lost DOD-wide. As DOD implements new systems run and operated by the components, the percentage of the complete data population processed by DFAS systems will decrease, and the potential gap between actual and reported amounts will increase if flaws and omissions in DOD's current process for monitoring these activities are not corrected. Recommendations for Executive Action: To ensure that the Department of Defense accurately reports and effectively monitors late-payment penalties and discounts lost on commercial payments subject to the Prompt Payment Act, we recommend that the Secretary of Defense direct the Deputy Chief Financial Officer, through the Office of the Under Secretary of Defense (Comptroller), to establish procedures for: (1) identifying all DOD systems that process commercial payments and assuring that the late-payment penalties metric data are compiled from the complete population of commercial payments subject to the Prompt Payment Act, (2) validating the accuracy and completeness of the data compiled and reported as DOD's late-payment penalties metric, and: (3) monitoring discounts lost DOD-wide based on periodic risk assessments. Agency Comments and Our Evaluation: We provided a draft of this report to DOD for comment. In its written comments, which are reprinted in enclosure I, DOD concurred with all three of our recommendations. DOD also stated that it is taking actions to address our recommendations, which includes (1) identifying and reporting DOD-wide late payment penalty metrics beginning in October 2012; (2) assigning responsibility to each reporting entity for the accuracy, completeness, and validation of data reported; and (3) identifying and issuing procedures to address monitoring and reporting of discounts lost. If fully and effectively implemented, DOD's proposed actions should address the intent of our recommendations. We are sending copies of this report to the appropriate congressional committees; the Secretary of Defense, the Deputy Secretary of Defense, the Deputy Chief Management Officer, the Under Secretary of Defense (Comptroller), and other interested parties. In addition, this report is available at no charge on the GAO website at [hyperlink, http://www.gao.gov]. If you or your staff have any questions about this report, please contact me at (202) 512-9869 or khana@gao.gov. Contact points for our Offices of Congressional Relations and Public Affairs may be found on the last page of this report. GAO staff who made key contributions to this report are listed in enclosure II. Signed by: Asif A. Khan: Director, Financial Management and Assurance: Enclosures: [End of section] Enclosure I: Comments from the Department of Defense: Office of The Under Secretary Of Defense: Comptroller: 1100 Defense Pentagon Washington, DC 20301-1100 June 6, 2012: Mr. Asif A. Khan: Director, Financial Management and Assurance: U.S. Government Accountability Office: Washington, DC 20548: Dear Mr. Khan: This is the Department of Defense (DoD) response to the Government Accountability Office (GAO) draft report GAO-12-662R, "DoD Financial Management: Improvements Needed in Prompt Payment Monitoring and Reporting," dated May 16, 2012 (GAO Code 197107). Thank you for the opportunity to respond. The Department concurs with all three report recommendations. Our detailed responses are included in the enclosure. We support the need for a complete and accurate picture of DoD-wide interest payment penalties and discounts lost. The expansion of electronic commerce and other process improvements have reduced late payments and associated penalties over recent years. Systems modernizations have also moved more of our entitlement activity to systems where we have not, however, adequately captured and reported this information. We plan to maintain non-appropriated fund instrumentalities (NAFIs) separately from our traditional reporting of the appropriated fund activities. Our procedures reflect the uniqueness of the NAFIs' missions, funding, oversight, and reporting responsibilities within the Department, along with the limited authorities and responsibilities assigned to the Office of the Under Secretary of Defense (Comptroller) (OUSD(C)) for the NAFIs. Our initial approach will be to confirm that prompt payment interest data is being collected, monitored, and reported within the responsible oversight entity, but not include the NAFIs' metric data as part of the OUSD(C)'s DoD enterprise metrics data. My point of contact on this matter is Mr. M. Wayne Goff. He can be reached at wayne.goff@osd.mil or at 703-602-0374. Sincerely, Signed by: Mark E. Easton: Deputy Chief Financial Officer: Enclosure: As stated: [End of letter] GAO Draft Report Dated May 16, 2012: GAO-12-662R (GAO Code 197107): "DOD Financial Management: Improvements Needed In Prompt Payment Monitoring And Reporting" Department Of Defense (DOD) Comments To The GAO Recommendations: Recommendation 1: The GAO recommends that the Secretary of Defense direct the Deputy Chief Financial Officer, through the Office of the Under Secretary of Defense (Comptroller) to establish procedures for identifying all DoD systems that process commercial payments and assuring that the late payment penalties metric data are compiled from the complete population of commercial payments subject to the Prompt Payment Act. DoD Response: Concur. Procedures will be established to require the identification and reporting of DoD-wide late payment penalty metrics beginning October I, 2012, to the extent the data is available within the respective systems. We expect some systems will require modifications in order to collect certain data elements necessary for the metric, and thus reporting from those systems will potentially be delayed until the necessary system modifications are completed. Recommendation 2: The GAO recommends that the Secretary of Defense direct the Deputy Chief Financial Officer, through the Office of the Under Secretary of Defense (Comptroller) to establish procedures for validating the accuracy and completeness of the data compiled and reported as DoD's late payment penalties metric. DoD Response: Concur. Each Departmental reporting entity will be assigned responsibility within the aforementioned procedures for the accuracy and completeness of the data reported. These procedures will also address validating the data at the DoD enterprise level. Recommendation 3: The GAO recommends that the Secretary of Defense direct the Deputy Chief Financial Officer, through the Office of the Under Secretary of Defense (Comptroller) to establish procedures for monitoring discounts lost DoD-wide based on periodic risk assessments. DoD Response: Concur. In order to evaluate the risk and magnitude of discounts lost DoD-wide. we will initially identify the total universe of discounts lost to the extent possible given some limitations within the Department's systems. Once this data is gathered and evaluated, we expect to issue cost-effective procedures addressing the monitoring and reporting requirements for discounts lost DoD-wide by October 1, 2012. [End of section] Enclosure II: GAO Contact and Staff Acknowledgments: GAO Contact: Asif A. Khan, (202) 512-9869 or khana@gao.gov: Staff Acknowledgments: In addition to the contact named above, Michael LaForge, Assistant Director; Justin Fisher; Patrick Frey; Maxine Hattery; Jason Kelly; Jason Kirwan; Laura Pacheco; J. Mark Yoder; and Leonard Zapata made key contributions to this report. [End of section] Footnotes: [1] Generally, the Prompt Payment Act requires agencies to make payment no later than 30 days after the date they receive an invoice or by a contractually established payment date. The Department of the Treasury establishes the rate used to calculate late-payment penalties. A discount is considered to be economically justified if the discount terms effectively equal or exceed the interest the federal government charges on overdue debt that it is owed. [2] S. Rep. No.112-26, at 151 (June 22, 2011). [3] Systems that make DOD commercial payments and that are not operated by DFAS include those currently being implemented by the Army, Navy, and Air Force. [4] The process for monitoring DOD financial operations using metrics is documented by the DCFO's Performance Measurement Team in its Performance Measurement Team Handbook. [5] For example, DOD started including commercial payments from the U.S. Army Corps of Engineers Financial Management System in the December 2011 metric. [6] GAO, Standards for Internal Control in the Federal Government, [hyperlink, http://www.gao.gov/products/GAO/AIMD-00-21.3.1] (Washington, D.C.: November 1999). These standards provide the overall framework for establishing and maintaining internal control and for identifying and addressing areas at greatest risk of fraud, waste, abuse, and mismanagement. [7] The Navy ERP system, accounting for about $1 billion in fiscal year 2011 commercial payments, could not provide an amount subject to the Prompt Payment Act. [8] The Navy ERP system, as well as EBS, which accounts for $24 billion in fiscal year 2011 commercial payments subject to the Prompt Payment Act, could not provide an amount for discounts lost. [9] The Wide Area Workflow is an interactive application that allows contractors and vendors to electronically submit invoices and receiving reports, and the federal government to inspect, accept, receive, and pay electronically. [10] DOD analysis was done using late-payment penalties paid in fiscal year 2010. [End of section] GAO’s Mission: The Government Accountability Office, the audit, evaluation, and investigative arm of Congress, exists to support Congress in meeting its constitutional responsibilities and to help improve the performance and accountability of the federal government for the American people. GAO examines the use of public funds; evaluates federal programs and policies; and provides analyses, recommendations, and other assistance to help Congress make informed oversight, policy, and funding decisions. GAO’s commitment to good government is reflected in its core values of accountability, integrity, and reliability. Obtaining Copies of GAO Reports and Testimony: The fastest and easiest way to obtain copies of GAO documents at no cost is through GAO’s website [hyperlink, http://www.gao.gov]. Each weekday afternoon, GAO posts on its website newly released reports, testimony, and correspondence. To have GAO e-mail you a list of newly posted products, go to [hyperlink, http://www.gao.gov] and select “E-mail Updates.” Order by Phone: The price of each GAO publication reflects GAO’s actual cost of production and distribution and depends on the number of pages in the publication and whether the publication is printed in color or black and white. Pricing and ordering information is posted on GAO’s website, [hyperlink, http://www.gao.gov/ordering.htm]. Place orders by calling (202) 512-6000, toll free (866) 801-7077, or TDD (202) 512-2537. Orders may be paid for using American Express, Discover Card, MasterCard, Visa, check, or money order. Call for additional information. Connect with GAO: Connect with GAO on facebook, flickr, twitter, and YouTube. Subscribe to our RSS Feeds or E mail Updates. Listen to our Podcasts. Visit GAO on the web at [hyperlink, http://www.gao.gov]. To Report Fraud, Waste, and Abuse in Federal Programs: Contact: Website: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]; E-mail: fraudnet@gao.gov; Automated answering system: (800) 424-5454 or (202) 512-7470. Congressional Relations: Katherine Siggerud, Managing Director, siggerudk@gao.gov, (202) 512-4400 U.S. Government Accountability Office, 441 G Street NW, Room 7125 Washington, DC 20548. Public Affairs: Chuck Young, Managing Director, youngc1@gao.gov, (202) 512-4800 U.S. Government Accountability Office, 441 G Street NW, Room 7149 Washington, DC 20548.