[Alabama] REDWING CARRIERS, INC. (Saraland) (ALD980844385)
| Site ID: ALD980844385 |
| Site name and region | Location, county, and size of site | Date EPA added site to National Priorities List (NPL) | When added to NPL, buildings present at site | When added to NPL, site also had | Primary contaminants at site | Causes of contamination | Public health advisory issued | Primary financial responsibility for site |
| Redwing Carriers, Incorporated (Saraland) Region=4 | 527 US Highway 43, Saraland AL 36571 / Mobile / 5 acres | Feb. 1990 | residential housing | industrial waste | PAHs, metals, pesticides | chemical use and/or disposal, transportation | No | EPA |
| EPA's site ID=ALD980844385 |
| Start date(s) for any planned or in-progress studies to determine best cleanup methods | Projected signing date(s) for any unsigned record(s) of decision (ROD) specifying cleanup actions to be performed |
| Not applicable | Not applicable |
| EPA's site ID=ALD980844385 |
| Date(s) of signed ROD(s) specifying cleanup actions to be performed | Date of most recent amendment, if ROD has been amended | Explanation for ROD specifying "No action" or "No further action" |
| Dec. 1992 | No amendment | Not applicable |
| EPA's site ID=ALD980844385 |
| Start date(s) for design of cleanup methods | Completion date(s) for design of cleanup methods | Party responsible for cleanup |
| Oct. 1993 | 1st quarter, FY 2000 | Private |
| May 1996 | 1st quarter, FY 2000 | EPA |
| EPA's site ID=ALD980844385 |
| Cleanup action(s) performed at site and party conducting action(s) | Type of action taken | Contaminated media addressed | Start date(s) for action(s) | Completion date(s) for action(s) | Volumes addressed | Volumes remaining |
| Long-term/Private | Pump and treat (Extracting and then treating contaminated groundwater) | Groundwater | 1st quarter, FY 2000 | 4th quarter, FY 2003 | ||
| Long-term/EPA | Pump and treat (Extracting and then treating contaminated groundwater) | Groundwater | Not reported | Not reported | ||
| Short-term/Private | Disposal | Sludge | July 1985 | Jan. 1986 | 10 cubic yards (estimated) already addressed | |
| Long-term/Private | Excavation | Soil | 1st quarter, FY 2000 | 4th quarter, FY 2002 | 39,000 cubic yards (estimated) remaining to be excavated, 39,000 cubic yards (estimated) remaining to be treated | |
| Long-term/EPA | Excavation | Soil | Not reported | Not reported | ||
| Short-term/EPA | Incineration | Soil | Oct. 1996 | May 1997 | 17,546 cubic yards already excavated, 17,546 cubic yards already treated | |
| Short-term/EPA | Disposal | Solid Waste | Aug. 1995 | Oct. 1995 | 78 cubic yards (estimated) already addressed |